Socony-Mobil Oil Company, Incorporated v. United States

279 F.2d 512, 150 Ct. Cl. 283, 1960 U.S. Ct. Cl. LEXIS 115, 1961 A.M.C. 2122
CourtUnited States Court of Claims
DecidedJune 8, 1960
Docket686-53
StatusPublished
Cited by3 cases

This text of 279 F.2d 512 (Socony-Mobil Oil Company, Incorporated v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Socony-Mobil Oil Company, Incorporated v. United States, 279 F.2d 512, 150 Ct. Cl. 283, 1960 U.S. Ct. Cl. LEXIS 115, 1961 A.M.C. 2122 (cc 1960).

Opinions

MADDEN, Judge.

The agencies of the United States which have taken part in the transactions with which the instant case is concerned have been the United States Maritime Commission, the War Shipping Administration and the United States Maritime Administration. The name “Maritime” as used in this opinion designates whichever one of these agencies was the active one at the relevant time.

During World War II the plaintiff purchased from Maritime eight oil tankers which Maritime had caused to be built. At the time the title passed to the plaintiff, Maritime requisitioned the use of the tankers, as it was empowered to do by section 902 of the Merchant Marine Act of 1936, 46 U.S.C.A. § 1242. Thereafter the ships were operated by the plaintiff for the United States under a standardized form of time charter, the monthly charter hire paid by the United States being made up of (1) a stated amount for the use of the tankers and (2) a stated amount for the service to be rendered by the plaintiff, which service was the operation of the tankers by the plaintiff for the Government.

Section 902(a) of the 1936 Act referred to above provided that when the United States requisitioned the use of a ship, it should, when its need for the use ceased, restore the ship to the owner in a condition as good as when taken, less ordinary wear and tear, or should pay the owner an amount sufficient to restore the ship to that condition.

The charter agreement by which the plaintiff chartered the eight tankers to the Government provided that the Government had the right to install any equipment, gear or armament on the tankers, but that before redelivery of the tankers to the plaintiff, the Government would, at its own expense and “on [514]*514its time” remove such additions, and restore the ship to the condition it was in before the additions were made. The words “on its time” meant, of course, that the Government would continue to pay the “use” part of the charter hire during the time it took to restore the ships.

The charter agreement also provided that the Government, at its option, could, instead of itself restoring the tankers to their original condition, pay the plaintiff an amount of money sufficient to pay for the reconditioning and for the time reasonably required to perform the reconditioning, the time to be paid for at the agreed charter hire rate. '

When hostilities ended in 1945, Maritime had on its hands a large number of ships under charter agreements like the one described above. It desired to terminate the charters and it reconditioned some of the ships for redelivery to the owners. But in the fall of 1945 it decided that it would be more economical and expeditious to make settlements with the owners, paying them an agreed sum of money and letting them make their own restorations. After discussion with the industry, Maritime submitted a draft form of a settlement plan, which, after further discussion and modification, became what was called the “Redelivery Program”, dated November 2, 1945, and consisting of Plans I and II.

Plan I provided for immediate redelivery to the owner, v/ith a lump sum payment to him for all his claims arising out of the charter, including, of course, compensation for the expense of making the restoration and for the disabling of the vessel from use during the time it would take to make the restoration. Plan I provided a formula for determining the lump sum payment. One factor was to include $50,000 if the degaussing system to be removed had been installed inside the hull, and $44,000 if it had been installed on the weather deck. In this factor would also be included special circumstances applicable to particular ships, such as wartime abuses by excessive loadings, excessive speeds, convoy bumpings and undue deferment of repairs. The other factor was to be “an amount equal to fifteen days’ full charter hire (use rate plus service rate).” In the negotiations the tanker owners asked for $70,000 for the restoration and 30 days’ paid time, but the terms as first stated above were the ones finally agreed to.

The plaintiff elected to take back its ships under Plan I, and was paid $622,-552.55 on account of the eight ships in question. Of this sum $394,000 was allotted to the work of restoration, and the remaining $228,552.55 was the arithmetical computation of “an amount equal to fifteen full days’ charter hire”, as Plan I stipulated. Of this latter sum, $138,624.33 was “use” charter hire for 15 days, and the balance was “service” charter hire.

The release which the plaintiff executed upon receiving the lump sum payment was, of course, very comprehensive and, among many other things, released the Government from any obligation “to pay charter hire for any period of time required to make such repairs or restorations.”

A paragraph of the Plan I agreement said:

“The acceptance by any owner of Plan I in the manner above prescribed shall constitute a compromise settlement agreement with the United States covering the claims released by the owner as above set forth * *

The charter agreement had provided that the “use rate” of hire was not subject to the Renegotiation Act of April 28, 1942, 56 Stat. 226, 245, as amended, 50 U.S.C.A.Appendix § 1191, but that the “service rate” was subject to renegotiation if it produced excess profits. Since the negotiation leading to the agreement on Plan I was, in effect, an adequate renegotiation, the parties, in order to foreclose further renegotiation, inserted in their redelivery settlement the following provision:

[515]*515“Although the formula used in determining the amount of the lump sum settlement involves an element calculated at charter hire rates, it is the fact and intention of the parties that this lump sum settlement is not in payment of articles or services but is in discharge of certain claims under the charter.”

The foregoing transactions were completed and the plaintiff got back its eight ships in November 1945. On March 8, 1946 Congress enacted the Merchant Ship Sales Act of 1946, 60 Stat. 41, 50 U.S.C.A.Appendix, §§ 1735 et seq., 1742. It did so because the Government still owned many merchant ships which it desired to sell into private ownership. The statute made detailed provision for the sale of the surplus ships at prices fixed by formulas, which prices would be fair to the Government but would attract purchasers. The only section of the Act relevant to the instant case is section 9. It provided, in effect, that any United States citizen who had purchased a ship from Maritime during World War II was entitled, if he applied for it, to an adjustment in the price paid for the ship so that its price would not exceed the price at which the same type of ship could be purchased from Maritime under the 1946 Act. Section 9(b) (6) of the Act said:

“The applicant shall credit the United States with all amounts paid by the Commission to him as charter hire for the use of the vessel (exclusive of service, if any, required under the terms of the charter) under any charter party made prior to the date of the enactment of this Act (March 8, 1946) * * *.”

The plaintiff, in June 1946, applied for adjustment of the price of the eight tankers. The only controversy between the parties in working out the adjustment was with regard to the $138,624.33 which, as we have seen, had been included in the 1945 redelivery agreement as the “use” part of “an amount equal to fifteen days’ full charter hire” at the rate fixed in the charter agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gulf Oil Corp. v. United States
154 Ct. Cl. 652 (Court of Claims, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
279 F.2d 512, 150 Ct. Cl. 283, 1960 U.S. Ct. Cl. LEXIS 115, 1961 A.M.C. 2122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/socony-mobil-oil-company-incorporated-v-united-states-cc-1960.