Sobien v. Mullin

783 A.2d 795, 2001 Pa. Super. 259, 2001 Pa. Super. LEXIS 2621
CourtSuperior Court of Pennsylvania
DecidedAugust 31, 2001
StatusPublished
Cited by10 cases

This text of 783 A.2d 795 (Sobien v. Mullin) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sobien v. Mullin, 783 A.2d 795, 2001 Pa. Super. 259, 2001 Pa. Super. LEXIS 2621 (Pa. Ct. App. 2001).

Opinion

ORIE MELVIN, J.:

¶ 1 Appellant, James Mullin, appeals from the judgment entered on the jury verdict finding him liable for the cost incurred by Appellees, Ailisa and Frank Sobien (the Sobiens), in re-framing and siding their end wall, which had become exposed to the. elements due to Mr. Mul-lin’s removal of his condemned building. On appeal, Mr. Mullin claims the trial court erred in refusing his request for a judgment notwithstanding the verdict (JNOV). We reverse and remand.

¶ 2 This case involves party wall rights between adjoining landowners in the City of Pittsburgh, Allegheny County, Pennsylvania. The relevant facts are not seriously in dispute. Mr. Mullin has owned the lot located at 876 Progress Street for the past twenty-five years. The Sobiens purchased the adjoining lot numbered as 874 Progress Street in 1995. The buildings on the respective lots date back to the early 1900’s. The building on Mr. Mullin’s lot was built first, and its brick side wall adjacent to the Sobiens’ lot was constructed wholly within Mr. Mullin’s property line. The original owner of the Sobiens’ lot built their residence in such a manner that the interior framing of their north wall butted up against Mr. Mullin’s brick wall using it as a curtain or firewall and thereby encroached upon Mr. Mullin’s property. The structural weight bearing wooden beams ran from front to back, and there was no tie into Mr. Mullin’s side wall. The parties were unable to determine whether at the time of this construction the lots were owned individually or by the same person. However, this information was unnecessary in deciding whether the wall was intended as a party wall because the Sobiens alleged they had acquired prescriptive rights to the continued use of the wall as a protective wall.

¶ 3 On August 29, 1996, Mr. Mullin posted his building with a notice of intent to demolish and the requisite permit obtained. On September 30, 1996, demolition of Mr. Mullin’s building began pursuant to the City’s notice of condemnation. During the demolition work it was first discovered that the Sobiens’ adjacent wall did not have any exterior finishing material. After having removed the upper floor of the Mullin building the Sobiens’ third floor attic became exposed to the elements. At this point the Sobiens called the police, who directed the contractor to cover the third floor with a tarp and notified the Bureau of Building Inspection. The following day a building inspector visited the site and determined the brick wall could not remain standing independent of the building and directed the work to proceed. After a three day delay to allow the So-biens to remove their possessions, the de *797 molition of the entire building was completed. Subsequently, the Sobiens hired a contractor to rebuild their exterior wall within their property line. The total cost of repairs was $33,620.61, which consisted of cutting back the framing to within the Sobiens’ property line, enclosing the wall and making various repairs to the interior of the structure.

¶ 4 The Sobiens instituted suit to recover the cost of repairs alleging the acquisition of party wall rights through prescriptive use for more than twenty-one years. The complaint also alleged that Muhin negligently demolished the party wah and thereby deprived the Sobien structure of the support and protection it had received from the wah. Muhin filed an answer denying any liability and also a two count counterclaim seeking damages from the Sobiens. In Count I, Muhin sought damages for the allegedly unnecessary delay in the demolition of Muhin’s structure caused by the Sobiens’ complaints to the City of Pittsburgh. In Count II, Mullin sought compensation for labor and materials expended in enclosing the third floor of the Sobiens’ property. By stipulation of counsel, Count II of Muhin’s counterclaim was withdrawn, and Muhin proceeded only with Count I at trial.

¶ 5 A jury trial was held before the Honorable Cynthia A. Baldwin on February 7, 2000. At the conclusion of the Sobiens’ case, Muhin moved for a directed verdict, asserting that the Sobiens had failed to demonstrate the existence of a party wah, that no proof of an interest acquired by adverse possession had been shown, that no structural interdependence had been shown, and that an absence of negligence had been conceded. Muhin also took issue with the Sobiens re-introducing the settled matter of repairs to the third story. The motion was denied. The jury subsequently returned a verdict in favor of the Sobiens on their claim awarding $33,621.61 in damages. The jury also returned a verdict in favor of the Sobiens on Muhin’s counterclaim. Muhin filed a timely Motion for a Post-Trial Relief seeking Judgment N.O.V., or in the alternative, the grant of a new trial. The Sobiens filed a timely Motion for Delay Damages. Following the submission of briefs, the trial court entered an order dated May 31, 2000, which denied Muhin’s Motion for Posh-Trial Relief and granted the Sobiens’ Motion for Delay Damages in the amount of $3,475.29 for a total award of $37,096.90. This appeal followed. 1

¶6 Muhin presents his questions on appeal in a single statement as fohows:

Did the [trial] court ... err in failing to grant a directed verdict or judgment n.o.v. when plaintiff failed to prove any of its original ahegations, altered the theory of its case, and proceeded on a theory of strict liability and a concept of adverse possession not supported by the law?

Appehant’s brief at 3.

When reviewing a denial of judgment notwithstanding the verdict, an appehate court must decide whether there was sufficient evidence to sustain the verdict; our scope of review is very narrow: ah evidence and ah reasonable inferences drawn therefrom must be considered in the light most favorable to the verdict *798 winner. Judgment notwithstanding the verdict can be entered only if the mov-ant is entitled to judgment as a matter of law or if evidence is such that no two reasonable minds could disagree that the outcome should have been rendered in favor of the movant. We will reverse a trial court’s grant or dénial of a judgment notwithstanding the verdict only when we find an abuse of discretion or an error of law that controlled the outcome of the case.

B & L Asphalt Industries, Inc. v. Fusco, 753 A.2d 264 (Pa.Super.2000) (quoting Mitchell v. Moore, 729 A.2d 1200, 1203 (Pa.Super.1999)).

¶ 7 Party wall rights did not exist at common law. Rather, such rights are granted to adjoining landowners by statute, contract or prescription. See generally Jackman v. Rosenbaum Co., 263 Pa. 158, 106 A. 238 (1919) (reviewing the developments of the party wall system in Pennsylvania), see also 69 C.J.S. Party Walls §§ 5 and 9 (1951). Ordinarily, a party wall is constructed upon the division line, and each adjoining lot owner has an easement on his neighbor’s premises for the support or extent of use made of the party wall. Id. at § 1; Bright v. Morgan, 218 Pa. 178, 67 A. 58 (1907); 2 Thompson on Real Property, § 395 (1961); See also 53 P.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David W. Alford v. Cotton Row Hospitality, LLC
Court of Appeals of Mississippi, 2023
Kramer, K. v. Hennigan, E.
Superior Court of Pennsylvania, 2022
Whack, J. v. City of Philadelphia
Superior Court of Pennsylvania, 2022
631 N. Broad St. v. Congregation Rodeph Shalom
Superior Court of Pennsylvania, 2019
Weichert Co. of Pennsylvania, Inc. v. Herling
929 A.2d 643 (Supreme Court of Pennsylvania, 2007)
Pennsylvania Orthopaedic Society v. Independence Blue Cross
885 A.2d 542 (Superior Court of Pennsylvania, 2005)
Hooker v. State Farm Fire & Casualty Co.
880 A.2d 70 (Commonwealth Court of Pennsylvania, 2005)
Wrobel v. Conner (In Re Conner)
302 B.R. 509 (W.D. Pennsylvania, 2003)
Goldstein v. Haband Co.
814 A.2d 1214 (Superior Court of Pennsylvania, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
783 A.2d 795, 2001 Pa. Super. 259, 2001 Pa. Super. LEXIS 2621, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sobien-v-mullin-pasuperct-2001.