Soarmar, Inc. v. Pinnconn, LLC

27 Mass. L. Rptr. 21
CourtMassachusetts Superior Court
DecidedApril 22, 2010
DocketNo. 081494
StatusPublished

This text of 27 Mass. L. Rptr. 21 (Soarmar, Inc. v. Pinnconn, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Soarmar, Inc. v. Pinnconn, LLC, 27 Mass. L. Rptr. 21 (Mass. Ct. App. 2010).

Opinion

Kaplan, Mitchell H., J.

This action arises out of a project to construct a facility for the defendant, L.A. Fitness International, LLC (“LA Fitness”), in Saugus, Massachusetts (the “Project”). LA Fitness contracted with defendant, Pinnconn, LLC (“Pinnconn”), to act as general contractor on the Project. Pinnconn, thereafter, entered into subcontracts with various parties, including the plaintiff, Soarmar, Inc. (“Soarmar”). Pinnconn failed to pay its subcontractors and was terminated by LA Fitness. Soarmar obtained a mechanics lien on the Project, pursuant to G.L.c. 254, §4, and filed this action to recover for the labor, material, and services that it provided to the Project. That lien was dissolved upon the filing of a lien bond by LA Fitness, as principal, and defendant, Insurance Company of the West (“ICWj, as surety, in the amount of the lien. Soarmar asserts claims against LA Fitness for: breach of contract; goods sold and delivered; quantum meruit; unjust enrichment; and violation of G.L.c. 93A; and against LA Fitness and ICW under the bond. LA Fitness’s and ICWs joint motion for summary judgment dismissing all claims asserted against them and Soarmar’s cross motion for summary judgment requesting that judgment enter for it in the amount of the value of the goods and services it supplied to the Project, at the subcontract prices, are now before the court. For the following reasons, LA Fitness’s and ICW’s motion is ALLOWED and Soarmar’s motion is DENIED.

FACTS

The following relevant facts are undisputed or viewed in the light most favorable to Soarmar.

LA Fitness leased the property on which the Project is constructed from Mansfield and Beacon. On or about November 29, 2007, LA Fitness entered into a contract with Pinnconn to act as the general contractor on the Project (the “Contract” or “Prime Contract”). Of significance to the pending motions are the following provisions from the general contract:

§14.3.1 Contractor shall promptly pay each Subcontractor, upon receipt of payment from the Owner, out of the amount paid to the Contractor on account of such Subcontractor’s portion of the Work, the amount to which said Subcontractor is entitled, reflecting percentages actually retained from payments to the Contractor on account of such Subcontractor’s portion of the Work.
§19.2.1 The owner may terminate the Contract if the Contractor: ... 2 fails to make payment to Subcontractors for materials or labor in accordance with agreements between the Contractor and the subcontractors ... 4 otherwise is guilty of substantial breach of a provision the Contract Documents.
§19.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 19.2.1, the Contractor shall not be entitled to receive further payment until the Work is finished.
Exhibit C [to contract], p. 2 [with respect to periodic applications for payment to the Contractor] . . . Contractor shall furnish proof of payment of construction obligations for all prior payments received by Contractor including but not limited to the partial or final releases and waivers of lien from all Lien Claimants or potential lien claimants. The furnishing of proof of payment and releases of lien as set forth herein shall be a condition precedent to Contractor’s entitlement to receive such pending payment.
On the thirtieth day of each month following the month of submission of an Application for Payment which has been submitted in accordance with the terms of this Agreement, Owner shall pay or cause to be paid to contractor ninety percent ... of the values, based upon the approve estimate of the Work completed to the date of such Application, of labor and material which have been stored at the Site ... or incorporated into the Project by the contractor during the period for which the Application for payment has been submitted.
Exhibit C [to Contract], pp. 2-3. Owner shall not be obligated to make any payment to Contractor if, and as long as, any one or more of the following conditions exist: (1) Contractor has failed to perform any of its obligations hereunder or otherwise is in default under this Agreement; (2) Contractor has failed to furnish to Owner satisfactory proof of payment to its subcontractors and suppliers and/or lien waivers and releases in the form and manner required hereunder; ... (5) Contractor has failed to make payment promptly or satisfactorily bond off or escrow fund to any lien claimants; (for the amount of any asserted or outstanding lien)...
Exhibit C [to Contract], p. 3. All payments by Owner to Contractor shall constitute trust funds in Contractor’s possession, to be applied first towards payment of all persons and entities (other than Contractor), including but not limited to, all Lien [22]*22Claimants . . . , having claims relating to the Work, before application for any other purpose.

After executing the Prime Contract, Pinnconn entered into a subcontract with Soarmar, dated January 7, 2008, to provide labor and materials on the Project (the “Subcontract”). The Subcontract referenced the Prime Contract, but LA Fitness was not a party to the Subcontract and undertook no contractual obligations to Soarmar.

Pinnconn submitted its first application for payment on December 31, 2007, and its second application on January 28, 2008. This latter application included a certification that it had completed $960,023 worth of work on the Project and requested payment of $690,996 (and acknowledged that $96,002 would be held as the 10% retainage). LA Fitness paid the amount requested in this second application to Pinnconn on March 4, 2008 (the “March 4th Payment”).

During February and March 2008, Soarmar performed work on the Project that entitled it to be paid $44,226.94 under the Subcontract. The amount of this work was included in Pinnconn’s applications for payment numbers 3 and 4, which were submitted to LA Fitness prior to the end of March 2008.

On March 25, 2008, Robert McQuade, the Chief Financial Officer of Pinnconn, told LA Fitness’s representative on the Project that Pinnconn had not paid its subcontractors anything from the March 4th payment, that money was gone, and Pinnconn had only $25,000 in assets remaining, which it was going to use to close down its operations.

On March 28, 2008, LA Fitness sent Pinnconn a Notice of Termination in which it asserted that Pinnconn was in default of the Contract for, among other things, failing to make prompt payment to its subcontractors. It thereafter entered into a new general contract with Konover to complete the Project.

On July 2, 2008, Soarmar recorded a Notice of Contract and a Statement of Account in the Essex South Registry of Deeds, pursuant to G.L.c. 254, §§4 and 8, respectively, to establish a mechanic’s lien on LA Fitness’s interest in the Project in the amount then due it under the Subcontract. On July 9, 2008, LA Fitness received notice that Soarmar had recorded a Notice of Contract. On July 30, 2008, LA Fitness, as principal, and ICW, as surety, recorded a lien bond in the penal sum of $44,226.94, pursuant to G.L.c. 254, § 14, in order to dissolve the lien. On October 27, 2008, Soarmar filed the instant complaint to enforce its claim against the lien bond and assert related claims.

DISCUSSION

A. Summary Judgment Standard

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
LaLonde v. Eissner
539 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1989)
Cullen Enterprises, Inc. v. Massachusetts Property Insurance Underwriting Ass'n
507 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1987)
Salamon v. Terra
477 N.E.2d 1029 (Massachusetts Supreme Judicial Court, 1985)
Canney v. New England Telephone & Telegraph Co.
228 N.E.2d 723 (Massachusetts Supreme Judicial Court, 1967)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Madsen v. Erwin
481 N.E.2d 1160 (Massachusetts Supreme Judicial Court, 1985)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
LaChance v. Rigoli
91 N.E.2d 204 (Massachusetts Supreme Judicial Court, 1950)
Evans v. Multicon Construction Corp.
574 N.E.2d 395 (Massachusetts Appeals Court, 1991)
Glazer v. Schwartz
176 N.E. 613 (Massachusetts Supreme Judicial Court, 1931)
Polednak v. Rent Control Board of Cambridge
494 N.E.2d 1025 (Massachusetts Supreme Judicial Court, 1986)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Bloomsouth Flooring Corp. v. Boys' & Girls' Club of Taunton Inc.
800 N.E.2d 1038 (Massachusetts Supreme Judicial Court, 2003)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)
Boyd v. National Railroad Passenger Corp.
446 Mass. 540 (Massachusetts Supreme Judicial Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
27 Mass. L. Rptr. 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/soarmar-inc-v-pinnconn-llc-masssuperct-2010.