Snyder v. Eanes Independent School District

860 S.W.2d 692, 1993 WL 302638
CourtCourt of Appeals of Texas
DecidedOctober 6, 1993
Docket3-92-568-CV
StatusPublished
Cited by64 cases

This text of 860 S.W.2d 692 (Snyder v. Eanes Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snyder v. Eanes Independent School District, 860 S.W.2d 692, 1993 WL 302638 (Tex. Ct. App. 1993).

Opinion

CARROLL, Chief Justice.

INTRODUCTION

This appeal arises from a lawsuit brought by James Snyder, as beneficiary of Phoenix Masonry of Texas, Inc., and Phoenix Masonry of Texas, Inc. (collectively, “Snyder”), appellants, alleging that Eanes Independent School District (“Eanes”) breached two construction contracts between Phoenix and Eanes. Snyder later named as additional defendants S. Don Rogers, the superintendent of Eanes, and William H. Wheeless, the Director of Support Services for Eanes, alleging that they tortiously interfered with the contracts and negligently caused Phoenix financial injury. By two separate orders, the trial court rendered summary judgment in favor of each of the defendants; Snyder appeals. As to each defendant, we will affirm the judgment of the trial court.

BACKGROUND

On February 15, 1984, Phoenix and Eanes entered into a written construction contract whereby Phoenix was to perform masonry work in connection with the construction of a fine arts facility at Westlake High School. On November 13th of that same year, Phoenix and Eanes entered into a second contract for work on library and classroom additions at Westlake High School. Both contracts consist of forms printed by the American Institute of Architects and included documents titled “Standard Form of Agreement Between Owner and Contractor” (the “Standard Agreement”) and “General Conditions of the Contract for Construction” (the “General Conditions”). The Standard Agreement provided for monthly progress payments by Eanes to Phoenix based upon certificates for payment to be issued by the architect. The General Conditions contained a provision stating that disputes were to be resolved through arbitration.

In July 1985, a dispute arose. The architect withheld certification for payment because of claimed mortar discoloration and unsatisfactory workmanship. Accordingly, *695 Eanes stopped paying the monthly progress payments to Phoenix. Despite this dispute, Phoenix continued the work and finished both projects; upon completion, Eanes occupied the buildings. In December 1985, Phoenix filed a claim through arbitration to collect payment and damages from Eanes. On December 26, 1986, the arbitrator signed an award against Eanes and in favor of Phoenix for $124,915 plus pre-award and post-award interest. Eanes paid the award, including interest, on February 27, 1987.

Snyder filed suit on August 3, 1988, against Eanes and several other defendants for additional damages related to the construction contracts. 1 Snyder added Rogers and Wheeless as defendants in its fourth amended original pleading on November 18, 1991. Eanes, Rogers, and Wheeless moved for summary judgment. On January 14, 1992, the trial court granted Rogers and Wheeless’s motions and on July 17, 1992, granted Eanes’s motion. By six points of error, Snyder appeals from the rendition of summary judgment for the defendants.

DISCUSSION AND HOLDING

The Summary Judgment in Favor of Eanes

The order granting summary judgment for Eanes did not specify on which grounds the court relied. When an order does not give a specific ground for granting the summary judgment, the nonmovant on appeal must show why each ground asserted in the motion is insufficient to support the order. Rogers v. Ricane Enters., Inc., 772 S.W.2d 76, 79 (Tex.1989); McCrea v. Cubilla, Condominium Corp., 685 S.W.2d 755, 757 (Tex.App. — Houston [1st Dist.] 1985, writ ref'd n.r.e.). To establish entitlement to summary judgment on Snyder’s breaeh-of-contract claims, Eanes had the burden of conclusively negating at least one essential element of each claim or establishing an affirmative defense as a matter of law. See Citizens First Nat’l Bank v. Cinco Exploration Co., 540 S.W.2d 292, 294 (Tex.1976).

In point of error two, Snyder contends that the trial court erred in granting summary judgment for Eanes because genuine issues of material fact exist. In Snyder’s response to Eanes’s summary-judgment motion, Snyder admits that its fourth amended original petition contains several allegations already resolved in arbitration. Snyder alleges, however, that three acts or omissions by Eanes were breaches of the construction contracts not resolved in arbitration: (1) failing to pay the arbitration award in a timely manner; (2) contacting Phoenix’s bonding company; and (3) failing to send a default notice to Phoenix. Snyder claims that genuine issues of material fact remain with regard to each of these alleged acts.

Eanes contends that the eomplained-of conduct did not breach any contractual provision. Furthermore, Eanes contends that any alleged damages were not contemplated by both parties at the time of contract formation and, thus, are not recoverable pursuant to the rule in Hadley v. Baxendale, 156 Eng. Rep. 145 (1854).

When a cause of action is based on breach of contract, the plaintiff must show that a contract existed between the parties, that the contract created duties, that the defendant breached a duty under the contract, and that the plaintiff sustained damages as a result. City of Corpus Christi v. Bayfront Assocs., Ltd., 814 S.W.2d 98, 103 (Tex.App. — Corpus Christi 1991, writ denied); Producer’s Grain Corp. v. Lindsay, 603 S.W.2d 326, 328 (Tex.Civ.App. — Amarillo 1980, no writ). The parties do not dispute that a contract was formed and that duties were created. The parties dispute, however, whether the alleged acts or omissions of Eanes constituted a breach of any contractual duty.

A. Payment of the Arbitration Award

Snyder contends that Eanes breached the contracts by failing to pay, in a timely manner, the arbitration award rendered on December 26, 1986. Eanes paid the award by *696 February 27, 1987. Snyder asserts that the contract required Eanes to pay the arbitration award within seven days after awarded. In the alternative, Snyder claims that the contracts are ambiguous regarding the payment deadline of the arbitration award and that this ambiguity raises a fact issue as to a reasonable time for payment of the award, thus precluding the rendition of summary judgment.

The meaning to be given language used in a contract is a question of law for the court, and such meaning shall be given as will carry out and effectuate, to the fullest extent, the parties’ intentions. Coker v. Coker, 650 S.W.2d 391, 393 (Tex.1983). Snyder relies on section 9.7.1 of the General Conditions, which states in part, “[I]f the Owner does not pay the Contractor within seven days after the date established in the Contract Documents any amount ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Estate of Robert S. Castleman v. .
Court of Appeals of Texas, 2025
Ledford v. Keen
9 F.4th 335 (Fifth Circuit, 2021)
Bullard v. Marker
W.D. Texas, 2019
Kelly Suter v. Univ of Texas at San Antonio
495 F. App'x 506 (Fifth Circuit, 2012)
Suter v. University of Texas
859 F. Supp. 2d 851 (W.D. Texas, 2012)
John Doe v. the Catholic Diocese of El Paso and Msgr. Thomas Rowland
362 S.W.3d 707 (Court of Appeals of Texas, 2011)
James T. Jackson, Sr. v. Thomas W. Carlson
Court of Appeals of Texas, 2009
Mansfield Heliflight, Inc. v. Bell/Agusta Aerospace Co.
507 F. Supp. 2d 638 (N.D. Texas, 2007)
Clovis Corp. v. Lubbock National Bank
194 S.W.3d 716 (Court of Appeals of Texas, 2006)
in the Interest of N.L.A., a Child
Court of Appeals of Texas, 2005

Cite This Page — Counsel Stack

Bluebook (online)
860 S.W.2d 692, 1993 WL 302638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snyder-v-eanes-independent-school-district-texapp-1993.