This text of Snake Steel, Inc. v. Holladay Construction Group, LLC (Snake Steel, Inc. v. Holladay Construction Group, LLC) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snake Steel, Inc. v. Holladay Construction Group, LLC, (Tenn. 2021).

Opinion

06/30/2021 IN THE SUPREME COURT OF TENNESSEE September 30, 2020 Session1

SNAKE STEEL, INC. v. HOLLADAY CONSTRUCTION GROUP, LLC

Appeal by Permission from the Court of Appeals Chancery Court for Davidson County No. 17-1037-III Ellen Hobbs Lyle, Chancellor ___________________________________

No. M2019-00322-SC-R11-CV ___________________________________

This appeal requires us to interpret provisions in the Prompt Pay Act, Tennessee Code Annotated sections 66-34-101 to -704, regarding retainage withheld on construction projects. The Prompt Pay Act requires the party withholding retainage—a percentage of total payment withheld as incentive for satisfactory completion of work—to deposit the funds into a separate, interest-bearing escrow account. Failure to do so results in a penalty of $300 per day. In this case, both parties agree the subcontractor’s retainage was not placed into an interest-bearing escrow account, and the retainage was not timely remitted to the subcontractor. Three years after completing its work on the contract, the subcontractor sued the contractor for unpaid retainage plus amounts due under the Prompt Pay Act. The contractor soon tendered the retainage; consequently, only the statutory penalty is at issue in this appeal. Tennessee Code Annotated section 66-34-104(c) states that, for persons required to deposit retainage into a separate interest-bearing escrow account, the penalty is assessed “per day for each and every day” retainage is not so deposited. Consonant with the statute’s language, its objective, the wrong the Prompt Pay Act seeks to prevent, and the purpose it seeks to accomplish, we hold that the $300 per day penalty is assessed each day retainage is not deposited in a statutorily-compliant escrow account. Consequently, while the subcontractor’s claim for the statutory penalty is subject to the one-year statute of limitations, if the subcontractor can establish that the contractor was required to deposit the retainage into an escrow account, the subcontractor is not precluded from recovering the penalty assessed each day during the period commencing 365 days before the complaint was filed. Accordingly, we reverse in part the trial court’s grant of summary judgment to the contractor and remand to the trial court for further proceedings.

1 We heard oral argument through videoconference under this Court’s emergency orders restricting court proceedings because of the COVID-19 pandemic. Tenn. R. App. P. 11 Appeal by Permission; Judgment of the Court of Appeals Affirmed in Part and Reversed in Part; Remanded to the Davidson County Chancery Court

HOLLY KIRBY, J., delivered the opinion of the court, in which JEFFREY S. BIVINS, C.J., and CORNELIA A. CLARK, SHARON G. LEE, and ROGER A. PAGE, JJ., joined. CORNELIA A. CLARK, J., filed a concurring opinion in which JEFFREY S. BIVINS, C.J., and SHARON G. LEE, J., joined.

Gregory L. Cashion and Petar A. Angelov, Nashville, Tennessee, for the appellant, Holladay Construction Group, LLC.

Dan E. Huffstutter, Nashville, Tennessee, for the appellee, Snake Steel, Inc.

OPINION FACTUAL AND PROCEDURAL BACKGROUND

This case began as a simple contract dispute. Defendant-Appellant Holladay Construction Group, LLC (“Holladay”) is a Tennessee-licensed general contractor. The owner of a construction site in Nashville, 2200 Charlotte Avenue, LLC (“Owner”), hired Holladay to provide general contracting services for a construction project.

In turn, Holladay hired Plaintiff-Appellee Snake Steel, Inc. (“Snake Steel”), a Tennessee corporation, as a subcontractor “to provide structural and miscellaneous steel” work as part of the larger construction project.

On approximately October 8, 2013, Holladay and Snake Steel memorialized their agreement in a written contract (the “Sub-Contract”). Initially, the Sub-Contract provided for Holladay to pay Snake Steel $336,722.00 for its work. An approved modification increased Snake Steel’s compensation to $365,411.52. In the Sub-Contract, Snake Steel agreed its payment from Holladay would be contingent on Holladay receiving payment for the construction project from Owner.

-2- The Sub-Contract also allowed Holladay to withhold a five-percent retainage from Snake Steel’s compensation until Snake Steel substantially completed its work. The retainage withheld amounted to $18,270.58.2

By September 30, 2014, Snake Steel had completed its work.3 On October 24, 2014, Holladay paid Snake Steel all amounts requested except the retainage and $32,480.004 in additional work done pursuant to a change order.

In May 2015, Holladay asked Owner to release its retainage, which included the retainage amount owed to Snake Steel. Owner released it to Holladay on May 27, 2015.

In February 2016, Snake Steel submitted a pay application to Holladay for its retainage. Holladay did not pay the retainage. In September 2017, Snake Steel sent Holladay a certified notice that it had not yet received its retainage.5

In September 2017, some three years after completion of its work under the Sub- Contract, Snake Steel filed suit against Holladay in the Davidson County Chancery Court. The lawsuit asserted that Snake Steel performed all of its obligations under the Sub- Contract, but Holladay failed to pay either the retainage or compensation for agreed change order work. The complaint sought damages for these two breaches of the Sub-Contract.

Pertinent to this appeal, the complaint also alleged Holladay was liable for failing to comply with the Prompt Pay Act, Tennessee Code Annotated sections 66-34-101 to - 704.6 In brief, the Prompt Pay Act requires retainage for the improvement of real property to be deposited into a separate interest-bearing escrow account. Tenn. Code Ann. § 66-34-

2 In its complaint, Snake Steel says the retainage amount was $18,720.58. However, the underlying documents in this case, including the relevant certificate of payment, state the amount as $18,270.58. The parties acknowledged this fact in their Joint Stipulations of April 2018. 3 In the record, two pay applications for the period ending September 30, 2014, one for Snake Steel and for Holladay, reflect completion of Snake Steel’s work. 4 While the parties provided differing amounts in their Joint Stipulations, $32,480.00 is the amount of the November 10, 2017 settlement check tendered to Snake Steel. Regardless, the parties do not dispute the amount. 5 Holladay received the notice two days later. 6 Unless otherwise noted, we refer to the version of the Prompt Pay Act in effect at the time of the events in this lawsuit. -3- 104(a) (2015).7 If the party responsible for establishing the escrow account fails to do so, the Act requires that party to pay the owner of the retainage a penalty of $300 per day. Id. § 66-34-104(c). There is no evidence that Snake Steel’s retainage was ever placed in an interest-bearing escrow account, while it was in either Owner’s or Holladay’s possession. In addition to other damages, Snake Steel’s complaint sought all amounts due under the Prompt Pay Act.

In October 2017, Holladay tendered a check to Snake Steel for the retainage, $18,270.58. Initially, Snake Steel refused to accept the payment. Holladay then filed its answer, responding that Snake Steel was not entitled to payment for the additional work, noting that Snake Steel had refused tender of the retainage, and denying liability under the Prompt Pay Act.

In December 2017, Holladay tendered Snake Steel payment for both the retainage and the change order work. Snake Steel accepted this payment.

In April and June 2018, the parties filed a series of joint stipulations acknowledging Snake Steel had accepted Holladay’s payment of the retainage and change order amounts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adams v. Woods
6 U.S. 336 (Supreme Court, 1805)
Gabelli v. Securities & Exchange Commission
133 S. Ct. 1216 (Supreme Court, 2013)
Calvin Gray Mills, Jr. v. Fulmarque, Inc.
360 S.W.3d 362 (Tennessee Supreme Court, 2012)
State v. Collins
166 S.W.3d 721 (Tennessee Supreme Court, 2005)
Pero's Steak and Spaghetti House v. Lee
90 S.W.3d 614 (Tennessee Supreme Court, 2002)
Scott v. Ashland Healthcare Center, Inc.
49 S.W.3d 281 (Tennessee Supreme Court, 2001)
Terry v. Niblack
979 S.W.2d 583 (Tennessee Supreme Court, 1998)
Stanbury v. Bacardi
953 S.W.2d 671 (Tennessee Supreme Court, 1997)
Foster v. Harris
633 S.W.2d 304 (Tennessee Supreme Court, 1982)
Teeters v. Currey
518 S.W.2d 512 (Tennessee Supreme Court, 1974)
Frazor v. Osborne
414 S.W.2d 118 (Court of Appeals of Tennessee, 1966)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
Hunter v. Brown
955 S.W.2d 49 (Tennessee Supreme Court, 1997)
Quality Auto Parts Co. v. Bluff City Buick Co.
876 S.W.2d 818 (Tennessee Supreme Court, 1994)
Potts v. Celotex Corp.
796 S.W.2d 678 (Tennessee Supreme Court, 1990)
Michelle RYE Et Al. v. WOMEN’S CARE CENTER OF MEMPHIS, MPLLC Et Al.
477 S.W.3d 235 (Tennessee Supreme Court, 2015)
Beacon4, LLC v. I & L Investments, LLC
514 S.W.3d 153 (Court of Appeals of Tennessee, 2016)
Linda Beard v. James William Branson
528 S.W.3d 487 (Tennessee Supreme Court, 2017)
Kenneth M. Spires v. Haley Reece Simpson
539 S.W.3d 134 (Tennessee Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Snake Steel, Inc. v. Holladay Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snake-steel-inc-v-holladay-construction-group-llc-tenn-2021.