Smith-Wolf Construction, Inc. v. Hood

756 P.2d 1027, 7 U.C.C. Rep. Serv. 2d (West) 479, 12 Brief Times Rptr. 627, 1988 Colo. App. LEXIS 96, 1988 WL 55640
CourtColorado Court of Appeals
DecidedApril 28, 1988
Docket84CA0841
StatusPublished
Cited by1 cases

This text of 756 P.2d 1027 (Smith-Wolf Construction, Inc. v. Hood) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith-Wolf Construction, Inc. v. Hood, 756 P.2d 1027, 7 U.C.C. Rep. Serv. 2d (West) 479, 12 Brief Times Rptr. 627, 1988 Colo. App. LEXIS 96, 1988 WL 55640 (Colo. Ct. App. 1988).

Opinion

CRISWELL, Judge.

Defendant, A1 Hood, appeals from the district court judgment that awarded plaintiff $52,646 in damages for breach of express and implied warranties relating to a waterproofing product manufactured by *1029 defendant. We affirm in part and reverse in part.

Plaintiff entered into a subcontract with the general contractor to perform waterproofing services in conjunction with the construction of the second bore of the Eisenhower Tunnel. Prior to preparing its bid that led to this subcontract, plaintiffs agent had several conversations with defendant concerning its waterproofing product, Deckseal. In these conversations, defendant represented and warranted, among other things, that he was familiar with the requirements for such work, that his product could be used to perform the work required with only two kettles to heat the product, and that a crew of five, working with “squeegees” to apply the product to the surfaces required, could waterproof about 13,500 square feet per day.

Relying upon these representations, plaintiff prepared and presented a bid to the general contractor for a total of $153,-995, which figure included an allowance for direct costs, an allowance for pro rata overhead costs (based upon a formula provided by plaintiffs accountant), and a profit. Plaintiffs bid was accepted and a subcontract, using plaintiffs bid figure as the contract price, was executed by the general contractor and plaintiff.

Plaintiff thereupon paid defendant for all of the Deckseal product that it expected to use on the project, although only a portion of the product was initially delivered to the jobsite. However, as plaintiff commenced to use the product in the manner suggested by defendant, several problems were encountered. In the beginning, the first Deckseal supplied by defendant had hardened in its containers and could not be removed. In addition, it was impossible to heat the product to the temperature required within the time outlined by defendant with only two kettles, so that three or four kettles, and a crew of 10 or 11, rather than five, persons was required to perform the work under plaintiffs subcontract. Even so, during the first 30 days that plaintiff worked on the project, it was able to waterproof less than 7,000 square feet per

day (and on some days less than 3,000 square feet).

Plaintiff immediately informed defendant of the problems that it was encountering, and defendant advised doing a number of things to alleviate those problems, such as mixing the product with paint thinner and preheating the cans containing the product. Plaintiff followed these suggestions, but none of them resulted in any substantial improvement in the product’s initial utility.

About 30 days after plaintiffs first use of the Deckseal, however, defendant supplied additional Deckseal that had been produced some time after the date that the first batch had been manufactured. From the time that this “new” material was furnished, a substantial increase in the area being covered (up to between 8,000 and 10,000 square feet per day) was experienced, athough plaintiff continued to use three or four kettles and a crew of 10 or 11.

Altogether, plaintiff used approximately 16,000 gallons of Deckseal supplied by defendant at a cost of about $53,000. In addition, in the last few days of the work, plaintiff used approximately 4,700 gallons of another material, obtained from another source. With this product, plaintiff was finally able to achieve a daily production of work approximating the 13,500 square feet of area initially forecast by defendant, although an increased number of kettles and workers continued to be used.

Plaintiffs evidence was that its actual “cost” to perform its subcontract was $218,078, as contrasted with the $153,995 contract price that it received. This “cost” figure, like the contract figure, included actual direct labor and other costs, and an allowance for additional overhead and for profit. The trial court found that 90% of the difference between these two figures (after adjustments for amounts owed to defendant by plaintiff and for acknowledged credits due plaintiff) represented the damages incurred by plaintiff as a result of the failure of Deckseal to perform as warranted by defendant. The other 10% was attributed to other causes.

*1030 I.

Defendant first argues that, since plaintiff did not “cover,” i.e., purchase goods in substitution for those that were to be provided by the seller, upon discovery of the defect in the product, it could not recover any consequential damages for breach of warranty. We disagree.

The remedies of a buyer of goods for his seller’s breach of an express or implied warranty are enumerated by the Uniform Commercial Code (UCC). If a buyer, who has accepted the goods, then learns of their nonconformity and gives notice to the seller of that nonconformity under § 4-2-607(3), C.R.S., he may recover the difference between the actual value of the goods and their value as warranted, as well as any incidental and consequential damages. Section 4-2-714, C.R.S. See 4 R. Anderson, Uniform Commercial Code, § 2-714:3 (3d ed. 1983).

For this purpose, consequential damages include:

“Any loss resulting from general or particular requirements and needs of which the seller at the time of contracting had reason to know and which could not reasonably be prevented by cover or otherwise.” Section 4-2-715(2)(a), C.R.S. (emphasis supplied)

This statutory provision is merely a particularized statement of the general rule that a wronged party cannot recover for those damages that reasonable actions on his part would have prevented. See 4 R. Anderson, supra, § 2-715:30. This statutory provision will not prevent or reduce recovery if the buyer’s actions are reasonable and undertaken in good faith. S.J. Groves & Sons Co. v. Warner Co., 576 F.2d 524 (3rd Cir.1978); Seekings v. Jimmy GMC of Tucson, Inc., 130 Ariz. 596, 638 P.2d 210 (1981). Moreover, the burden of proving that the buyer’s losses could have been avoided is upon the seller. S.J. Groves & Sons Co. v. Warner Co., supra. See Cherokee Investment Co. v. Voiles, 166 Colo. 270, 443 P.2d 727 (1968).

Further, a seller cannot rely upon a buyer’s failure to acquire substitute goods for that seller’s defective goods, if the other goods were equally available for the seller to acquire and to provide to the buyer, and such actions on the seller’s part could have reduced the buyer’s damages. If such acquisition is reasonable under the circumstances, but neither party undertook that step, the loss should fall on the party breaching the sales agreement. See S.J. Groves & Sons Co. v. Warner Co., supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Signal Corp. v. Safety Factors, Inc.
886 P.2d 172 (Washington Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
756 P.2d 1027, 7 U.C.C. Rep. Serv. 2d (West) 479, 12 Brief Times Rptr. 627, 1988 Colo. App. LEXIS 96, 1988 WL 55640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-wolf-construction-inc-v-hood-coloctapp-1988.