Smith v. Sack

2016 Ohio 763
Ohio Court of Appeals·Decided February 29, 2016·No. 2015-L-081·Published·Cited by 2 cases

Opinion

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT LAKE COUNTY, OHIO

ROBERT K. SMITH, : OPINION

Plaintiff-Appellee, :

CASE NO. 2015-L-081

- vs - :

JARED SACK, d.b.a. J.S. HARDSCAPES, :

Defendant-Appellant. :

Civil Appeal from the Lake County Court of Common Pleas, Case No. 14 CV 001139. Judgment: Affirmed.

George L. Badovick, 13033 Ravenna Road, Chardon, OH 44024 (For Plaintiff- Appellee).

Katherine S. Riedel, Law Offices of Katherine S. Riedel Co., L.P.A., Jefferson Commercial Park, 1484 State Route 46 North, No. 5, Jefferson, OH 44047 (For Defendant-Appellant).

CYNTHIA WESTCOTT RICE, J.

{¶1} Appellant, Jared Sack, dba J.S. Hardscapes, appeals the judgment of the Lake County Court of Common Pleas awarding appellee, Robert K. Smith, a refund under the Ohio Home Solicitation Sales Act (“HSSA”) of the money he paid to appellant in connection with a home improvement project. At issue is whether the trial court erred in finding that Mr. Smith was entitled to a refund under the HSSA. For the reasons that follow, the judgment is affirmed.

{¶2} The statement of facts that follows is based on the evidence submitted on summary judgment and presented at the damages hearing following the trial court’s entry of summary judgment on the issue of liability in favor of Mr. Smith. Between October 20, 2010 and August 16, 2013, the parties entered into a series of four contracts for appellant to construct and install a stone patio behind Mr. Smith’s residence, stone retaining walls surrounding the patio, and a detached stone wall along the southern boundary of Mr. Smith’s property. The four contracts were part of one integrated project, which was completed in four stages.

{¶3} The four contracts were evidenced by four invoices, one for each of the four stages of the project. Upon completion of each stage, appellant submitted an invoice to Mr. Smith. Appellant submitted to Mr. Smith the first three invoices on October 20, 2010; April 25, 2011; and May 26, 2011, and Mr. Smith promptly paid each in full, totaling $50,794.

{¶4} The final stage of the project was completed in August 2013. On August 16, 2013, appellant submitted the fourth and final invoice to Mr. Smith for labor and materials in the amount of $9,427. Mr. Smith paid $2,000 of this invoice on October 10, 2013, but refused to pay the balance due to problems with appellant’s work. The retaining wall surrounding the patio was built in two sections, a lower retaining wall and an upper retaining wall. The upper wall was recessed by about one foot and a rock garden was installed in the recessed area between the two levels. After the patio was completed, part of the upper retaining wall came apart and fell to the ground. The lower and upper retaining walls and piers facing the backyard pulled away from the patio; were leaning outward; and pulled the patio floor out with them. Further, the lower wall

facing the backyard, which was about 20 feet long, was bowed in the middle along the entire length of the wall. Due to the foregoing defects, Mr. Smith testified that the patio was “not useable.” Appellant’s efforts to repair the defects were unsuccessful.

{¶5} On June 4, 2014, Mr. Smith filed this action against appellant, alleging breach of contract, a violation of the Ohio Consumer Sales Practices Act (“CSPA”), and a violation of the Ohio Home Solicitation Sales Act (“HSSA”). Mr. Smith alleged that the transaction was a “home solicitation sale” as defined in the HSSA and that appellant failed to provide a notice of cancellation as required by the act.

{¶6} Appellant filed an answer and counterclaim for the remaining balance allegedly owed on the fourth contract in the amount of $7,427.

{¶7} Eight months after Mr. Smith filed the complaint, on February 10, 2015, appellant provided Mr. Smith with four notices of cancellation, one for each contract. As required by the HSSA, each notice provided that if Mr. Smith cancelled the contract within the allotted time (three days), all the money he paid would be refunded to him. Mr. Smith signed all four cancellation notices and timely mailed them to appellant on February 12, 2015. However, appellant did not refund any of the money Mr. Smith paid under the contracts.

{¶8} Mr. Smith filed a motion for summary judgment on his complaint and on appellant’s counterclaim. Mr. Smith argued that since he cancelled the contracts, there was no balance owed to appellant on the fourth contract, thus negating his counterclaim. Further, Mr. Smith argued that after the contracts were cancelled, appellant was required by the HSSA to return the purchase price within ten days of the cancellations. Mr. Smith argued that since appellant failed to return the purchase price

or to restore the property to its original condition, he was entitled to the damages provided for in the CSPA and the HSSA.

{¶9} In appellant’s brief in opposition, he conceded that Mr. Smith timely cancelled the contracts, but argued that the court should exercise its discretion in making an equitable determination of damages.

{¶10} On June 11, 2015, the trial court granted Mr. Smith’s motion for summary judgment on the issue of liability. The court noted the parties agree that the HSSA applies to this case and that the contracts were properly and timely cancelled by Mr. Smith. The court found that under the HSSA, appellant was not permitted to begin work during the time Mr. Smith was permitted to cancel. The court noted that under the act, the three-day cancellation period does not begin to run until notice of cancellation has been provided by the seller. The court found that since appellant began and completed the project before the cancellation period expired, he bore the risk that the contracts could be cancelled. The court found that because Mr. Smith timely cancelled the contracts, he was entitled to summary judgment on his HSSA claim.

{¶11} The court noted that the complaint also included a claim under the CSPA, but found that Mr. Smith could not recover under both the CSPA and the HSSA because they are mutually exclusive. The court found that since Mr. Smith cancelled the contracts, he had elected to proceed under the HSSA to recover a refund of the amount he paid and, thus, he was not entitled to any damages under the CSPA.

{¶12} The court also entered summary judgment in favor of Mr. Smith on appellant’s counterclaim, finding that because Mr. Smith properly cancelled the contracts, there was no balance owed to appellant.

{¶13} Although the parties do not address the issue, we note the court did not expressly dispose of Mr. Smiths’ breach-of-contract claim. However, because the court found, based on the undisputed evidence, that Mr. Smith cancelled the contracts, the court implicitly dismissed that claim because with no contracts, there could be no breach. The court thus disposed of all claims and appellant’s counterclaim.

{¶14} In addition, the court scheduled a hearing to determine the appropriate amount of damages to be awarded to Mr. Smith.

{¶15} The court held a damages hearing at which both parties presented evidence and argument. Mr. Smith argued that because the trial court found he properly cancelled all four contracts, pursuant to the HSSA, he was entitled to a refund of all monies paid under the contracts, i.e., $52,794. In opposition, appellant argued that only one area of the project had damage, i.e., the upper retaining wall. He thus argued that awarding Mr. Smith a full refund would unjustly enrich him, and asked the court to instead make an equitable determination of damages.

{¶16} On June 23, 2015, the trial court entered final judgment, awarding Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Smith v. Sack, 2016 Ohio 763 (Ohio Ct. App. 2016).

2016 Ohio 763 (Smith v. Sack) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ostigny v. France
2025 Ohio 4885 (Ohio Court of Appeals, 2025)
Grinder v. Schaaf
2025 Ohio 4723 (Ohio Court of Appeals, 2025)