Smith v. Sack

2016 Ohio 763
CourtOhio Court of Appeals
DecidedFebruary 29, 2016
Docket2015-L-081
StatusPublished
Cited by2 cases

This text of 2016 Ohio 763 (Smith v. Sack) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Sack, 2016 Ohio 763 (Ohio Ct. App. 2016).

Opinion

[Cite as Smith v. Sack, 2016-Ohio-763.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

LAKE COUNTY, OHIO

ROBERT K. SMITH, : OPINION

Plaintiff-Appellee, : CASE NO. 2015-L-081 - vs - :

JARED SACK, d.b.a. J.S. HARDSCAPES, :

Defendant-Appellant. :

Civil Appeal from the Lake County Court of Common Pleas, Case No. 14 CV 001139.

Judgment: Affirmed.

George L. Badovick, 13033 Ravenna Road, Chardon, OH 44024 (For Plaintiff- Appellee).

Katherine S. Riedel, Law Offices of Katherine S. Riedel Co., L.P.A., Jefferson Commercial Park, 1484 State Route 46 North, No. 5, Jefferson, OH 44047 (For Defendant-Appellant).

CYNTHIA WESTCOTT RICE, J.

{¶1} Appellant, Jared Sack, dba J.S. Hardscapes, appeals the judgment of the

Lake County Court of Common Pleas awarding appellee, Robert K. Smith, a refund

under the Ohio Home Solicitation Sales Act (“HSSA”) of the money he paid to appellant

in connection with a home improvement project. At issue is whether the trial court erred

in finding that Mr. Smith was entitled to a refund under the HSSA. For the reasons that

follow, the judgment is affirmed. {¶2} The statement of facts that follows is based on the evidence submitted on

summary judgment and presented at the damages hearing following the trial court’s

entry of summary judgment on the issue of liability in favor of Mr. Smith. Between

October 20, 2010 and August 16, 2013, the parties entered into a series of four

contracts for appellant to construct and install a stone patio behind Mr. Smith’s

residence, stone retaining walls surrounding the patio, and a detached stone wall along

the southern boundary of Mr. Smith’s property. The four contracts were part of one

integrated project, which was completed in four stages.

{¶3} The four contracts were evidenced by four invoices, one for each of the

four stages of the project. Upon completion of each stage, appellant submitted an

invoice to Mr. Smith. Appellant submitted to Mr. Smith the first three invoices on

October 20, 2010; April 25, 2011; and May 26, 2011, and Mr. Smith promptly paid each

in full, totaling $50,794.

{¶4} The final stage of the project was completed in August 2013. On August

16, 2013, appellant submitted the fourth and final invoice to Mr. Smith for labor and

materials in the amount of $9,427. Mr. Smith paid $2,000 of this invoice on October 10,

2013, but refused to pay the balance due to problems with appellant’s work. The

retaining wall surrounding the patio was built in two sections, a lower retaining wall and

an upper retaining wall. The upper wall was recessed by about one foot and a rock

garden was installed in the recessed area between the two levels. After the patio was

completed, part of the upper retaining wall came apart and fell to the ground. The lower

and upper retaining walls and piers facing the backyard pulled away from the patio;

were leaning outward; and pulled the patio floor out with them. Further, the lower wall

2 facing the backyard, which was about 20 feet long, was bowed in the middle along the

entire length of the wall. Due to the foregoing defects, Mr. Smith testified that the patio

was “not useable.” Appellant’s efforts to repair the defects were unsuccessful.

{¶5} On June 4, 2014, Mr. Smith filed this action against appellant, alleging

breach of contract, a violation of the Ohio Consumer Sales Practices Act (“CSPA”), and

a violation of the Ohio Home Solicitation Sales Act (“HSSA”). Mr. Smith alleged that the

transaction was a “home solicitation sale” as defined in the HSSA and that appellant

failed to provide a notice of cancellation as required by the act.

{¶6} Appellant filed an answer and counterclaim for the remaining balance

allegedly owed on the fourth contract in the amount of $7,427.

{¶7} Eight months after Mr. Smith filed the complaint, on February 10, 2015,

appellant provided Mr. Smith with four notices of cancellation, one for each contract. As

required by the HSSA, each notice provided that if Mr. Smith cancelled the contract

within the allotted time (three days), all the money he paid would be refunded to him.

Mr. Smith signed all four cancellation notices and timely mailed them to appellant on

February 12, 2015. However, appellant did not refund any of the money Mr. Smith paid

under the contracts.

{¶8} Mr. Smith filed a motion for summary judgment on his complaint and on

appellant’s counterclaim. Mr. Smith argued that since he cancelled the contracts, there

was no balance owed to appellant on the fourth contract, thus negating his

counterclaim. Further, Mr. Smith argued that after the contracts were cancelled,

appellant was required by the HSSA to return the purchase price within ten days of the

cancellations. Mr. Smith argued that since appellant failed to return the purchase price

3 or to restore the property to its original condition, he was entitled to the damages

provided for in the CSPA and the HSSA.

{¶9} In appellant’s brief in opposition, he conceded that Mr. Smith timely

cancelled the contracts, but argued that the court should exercise its discretion in

making an equitable determination of damages.

{¶10} On June 11, 2015, the trial court granted Mr. Smith’s motion for summary

judgment on the issue of liability. The court noted the parties agree that the HSSA

applies to this case and that the contracts were properly and timely cancelled by Mr.

Smith. The court found that under the HSSA, appellant was not permitted to begin work

during the time Mr. Smith was permitted to cancel. The court noted that under the act,

the three-day cancellation period does not begin to run until notice of cancellation has

been provided by the seller. The court found that since appellant began and completed

the project before the cancellation period expired, he bore the risk that the contracts

could be cancelled. The court found that because Mr. Smith timely cancelled the

contracts, he was entitled to summary judgment on his HSSA claim.

{¶11} The court noted that the complaint also included a claim under the CSPA,

but found that Mr. Smith could not recover under both the CSPA and the HSSA

because they are mutually exclusive. The court found that since Mr. Smith cancelled

the contracts, he had elected to proceed under the HSSA to recover a refund of the

amount he paid and, thus, he was not entitled to any damages under the CSPA.

{¶12} The court also entered summary judgment in favor of Mr. Smith on

appellant’s counterclaim, finding that because Mr. Smith properly cancelled the

contracts, there was no balance owed to appellant.

4 {¶13} Although the parties do not address the issue, we note the court did not

expressly dispose of Mr. Smiths’ breach-of-contract claim. However, because the court

found, based on the undisputed evidence, that Mr. Smith cancelled the contracts, the

court implicitly dismissed that claim because with no contracts, there could be no

breach. The court thus disposed of all claims and appellant’s counterclaim.

{¶14} In addition, the court scheduled a hearing to determine the appropriate

amount of damages to be awarded to Mr. Smith.

{¶15} The court held a damages hearing at which both parties presented

evidence and argument. Mr. Smith argued that because the trial court found he

properly cancelled all four contracts, pursuant to the HSSA, he was entitled to a refund

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ostigny v. France
2025 Ohio 4885 (Ohio Court of Appeals, 2025)
Grinder v. Schaaf
2025 Ohio 4723 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2016 Ohio 763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-sack-ohioctapp-2016.