Smith v. Githens

271 S.W.2d 374, 1954 Mo. App. LEXIS 365
CourtMissouri Court of Appeals
DecidedSeptember 13, 1954
Docket7251
StatusPublished
Cited by35 cases

This text of 271 S.W.2d 374 (Smith v. Githens) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Githens, 271 S.W.2d 374, 1954 Mo. App. LEXIS 365 (Mo. Ct. App. 1954).

Opinion

McDOWELL, Presiding Judge.

This appeal is by R. P. Smith, one of the plaintiffs, from a judgment of the Circuit Court of Butler County, Missouri, in an action on written contract to recover $4,-656.90, the alleged balance due on 1,289.91 tons of asphalt concrete.

The petition is in two counts. The first count alleges that plaintiffs, R. P. Smith and W. Dwight Little, were partners in the operation of Cape Asphalt Paving Company, of which R. P. Smith was sole owner.

That defendant, J. W. Githens was engaged in the general contracting business under the firm name of J. W. Githens Company.

That on or about December 11, 1950, the parties entered into a written contract whereby plaintiffs agreed, as such contractors, to furnish asphalt concrete for runways of municipal airport for the City of Hornersville required by defendant’s contract with said city at $10 per ton; that plaintiffs 'delivered 1,289.91 tons of asphalt and that there is still due and unpaid for said asphalt $4,656.90.

Count II states that plaintiff applied 2,-890 gallons of Mc-0 oil at an agreed price of ten cents per gallon and there is now due, and unpaid for said oil $287 with interest.

Defendant’s answer to count I of the petition admits the execution of the contract and pleads modification of, the same by written agreement of the parties in accordance with a letter dated October 7, 195L The answer further pleads that there was a mutual mistake in the drawing of the contract; that the agreed price was not $10 per ton as asserted therein but $1 per square yard and that defendant is indebted to plaintiff in the sum of $1,869.04 figured,on the basis of $1 per square yard, subject to-claims of interpleaders for supplies and materials furnished plaintiffs under the contract.

The answer to count II of the petition is a general denial.

The defendant’s answer in the form of counterclaim seeks to recover damages in the sum of $2,230.12 caused by the failure of plaintiffs to begin work within ten days from the date of notice from defendant to-do so, to wit, June 27, 1951. The counterclaim alleges that the work was not started until September 15,1951.

Two issues are presented to this court for judgment. First, did the trial court err in reforming the contract because of mutual mistake of fact so as to read $1 per square yard instead of $10 per ton and in finding that there was a modification of the written contract by the parties after its. execution so as to provide the price to be paid for the asphalt concrete was $1 per square yard?

*377 The second issue involved is the sufficiency of the evidence to support the judgment of the trial court in favor of the defendant on defendant’s counterclaim.

We will refer to appellant as plaintiff and to respondent as defendant.

Plaintiff first contends that there is insufficient evidence to support the court’s finding of a mutual mistake of fact.

In determining this issue we consider all of the evidence.

The evidence is: R. P. Smith and W. Dwight Little were partners engaged in the asphalt concrete paving business under the name of Cape Asphalt Paving Company; J. W. Githens, defendant, was a general contractor d/b/a J. W. Githens Company.

Defendant obtained a contract from the City of Hornersville, Missouri, for grading, seeding and paving of the municipal airport.

Not being able to do the asphalt concrete surface work he sought out plaintiffs at Cape Girardeau, Missouri, to do this work. Smith is a lawyer and it was agreed that Little would make an investigation of the cost of materials to do the work and then bid on the furnishing of asphalt concrete for the purposes of laying the runways. Smith sent Little to Kennett to negotiate the contract. Little assisted Githens in preparing his bid on the airport job and figured the cost of laying the asphalt pavement on a square yard basis. Little and Githens both testified that they entered into an oral contract whereby plaintiffs were to furnish the asphalt paving for the runways of the airport for $1 per square yard.

Little transmitted the terms of the oral agreement to Smith, who prepared the contract. Smith stated that the terms submitted to him was $10 per ton for the asphalt so furnished and he so stated in the written contract. All the copies of the contract were turned over to Little and were, :by him and defendant, executed in Little’s car in the City of Kennett December 11, 1950.

Defendant admitted that he hurriedly read the contract.before signing it; that it contained the term, “a sum equal to $10.00' per ton.”

Little testified that at the time of the execution of the contract he thought the price to be paid was $1 per square yard. A copy of the contract was left with defendant who stated he lost it.

There was no objection by defendant as to the price of the concrete contained in the contract until after the work started in the middle of September, 1951. Smith wrote a letter, dated October 15, 1951, to defendant informing him that the base of thé runways . was in such condition as to require more asphalt concrete to lay the surface thereon. He stated that he was doing the work on a per ton basis and would not be hurt but that he thought defendant ought to know as he had bid the work in on the square yard basis.

Defendant, by letter dated October 17th, informed Smith that their contract was on a per square yard basis and unless he did the work on that basis to stop. On Monday, after receiving Smith’s letter dated October 15th, defendant went to the airport and consulted Little, who endorsed on the back of Smith’s letter, which is in evidence as plaintiff’s exhibit No. 7, the following: “This letter is void and job is to proceed on basis of square yard as of $1.00 per agreement.” Defendant offered this notation on the back of plaintiff’s exhibit No. 7 as defendant’s exhibit No. 2.

Little also signed a separate agreement with defendant in which he agreed that the contract sued on should be modified so as to read $1 per square yard. This separate agreement was not in evidence but made a part of the answer.

There was no record kept of the weights of the asphalt concrete furnished for the first week. Smith, upon learning about the matter, ordered the concrete weighed.

The city engineer testified that he made no check on the weights of the materials used; that Little had informed him that *378 the work was being done on a per yard basis. Little testified that he arrived at the weight of the pavement used for the first week by taking the number of loads used and averaging them with the weight of the loads used after they began weighing.

The evidence shows that after the work was completed plaintiff mailed statements to defendant showing the amount due figured on a per ton basis; that defendant never objected to the amount in the statements until the suit was filed.

Little, at the time of his deposition, was no longer a partner with Smith. His testimony clearly indicates his prejudice against Smith and his desire to aid defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Nationwide Life Insurance Co.
340 S.W.3d 161 (Missouri Court of Appeals, 2011)
Lunceford v. Houghtlin
170 S.W.3d 453 (Missouri Court of Appeals, 2005)
Shurgard Storage Centers v. Lipton-U. City, LLC
394 F.3d 1041 (Eighth Circuit, 2005)
Warren v. Paragon Technologies Group, Inc.
950 S.W.2d 844 (Supreme Court of Missouri, 1997)
McDonnell Douglas Corp. v. SCI Technology, Inc.
933 F. Supp. 822 (E.D. Missouri, 1996)
Hoffman v. Kaplan
875 S.W.2d 948 (Missouri Court of Appeals, 1994)
Byrd v. Liesman
825 S.W.2d 38 (Missouri Court of Appeals, 1992)
Clayton X-Ray Co. v. Evenson
826 S.W.2d 45 (Missouri Court of Appeals, 1992)
Peterson v. Continental Boiler Works, Inc.
783 S.W.2d 896 (Supreme Court of Missouri, 1990)
Hysinger v. Heeney
785 S.W.2d 619 (Missouri Court of Appeals, 1990)
Matter of Estate of Hysinger
785 S.W.2d 619 (Missouri Court of Appeals, 1990)
Becker Electric Co. v. Director of Revenue
749 S.W.2d 403 (Supreme Court of Missouri, 1988)
Sheinbein v. First Boston Corp.
670 S.W.2d 872 (Missouri Court of Appeals, 1984)
Hoffmeister Mortuaries v. Jones
660 S.W.2d 19 (Missouri Court of Appeals, 1983)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
Shaffer v. Terrydale Management Corp.
648 S.W.2d 595 (Missouri Court of Appeals, 1983)
Justus v. Webb
634 S.W.2d 567 (Missouri Court of Appeals, 1982)
Daniels v. Keenen (In Re Keenen)
19 B.R. 724 (W.D. Missouri, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
271 S.W.2d 374, 1954 Mo. App. LEXIS 365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-githens-moctapp-1954.