STATE OF MAINE SUPERIOR COURT PENOBSCOT, ss Docket No. CV-OY-174 '.. r:'!,./,/ - \ '~i r.""" l[ ()
, I
BRYAN A. SMITH,
Plaintiff
v. FINDINGS AND CONCLUSIONS
CENTRAL MAINE POWER ,..-----". .. _-_. COMPANY, FILED & ENTERED SUPERIOR COURT Defendant NOV 06 2008
PENOBSCOT COUNTY
BACKGROUND
Before the Court is a Complaint brought July 11, 2007 by Bryan A. Smith against
Central Maine Power Company (CMP). It alleges that CMP negligently caused personal
injuries to Mr. Smith due to CMP's failure to adhere to minimum height requirements for
the 19.9 kV electrical distribution line located along the westerly side Route 166 in the
Town of Penobscot, Maine. Mr. Smith sustained severe electrical injuries while
"unstepping" a mast on a sailboat on October 31, 2002. At the time of the accident, Mr.
Smith was employed by Devereaux Marine, a boatyard whose operations include
launching, hauling, repairing, and storing privately owned boats, primarily sailboats.
CMP answered the Complaint on July 20, 2007, denying the allegations. It also
asserted affirmative defenses, including comparative negligence, and the allegation that
1 Mr. Smith's injuries "were caused or contributed to by others," thus absolving CMP of
any liability.
Mr. Smith is represented by Attorney Barry Mills and Attorney Lisa Cohen Lunn.
CMP is represented by Attorney Mark Dunlap. The matter was tried before this Court
beginning July 8, 2008. The parties submitted written closing arguments in rnid
September of2008. Although expected, rebuttal arguments were not filed by either party.
The Court has considered the testimony of all witnesses at trial, as well as
testimony submitted by way of depositions, all exhibits from the parties, and their closing
arguments. The Court also reviewed the legal arguments made by the parties as to
Defendant's Second Motion in Limine which dealt with the "sole proximate cause" issue,
as well as arguments made by the parties as to the Defendant's first Motion in Limine and
Motion for Partial Motion for Summary Judgment. The Court has also reviewed the
applicable provisions of the National Electrical Safety Code (Def. Exh. 1), PUC Chapter
910, the Maine Overhead High Voltage Line Safety Act, 35-A MRSA §101 et seq, and
applicable case law.
FINDINGS AND CONCLUSIONS
35-A MRSA §103 et seq establishes and governs the authority of the Public
Utility Commission to regulate utilities, including Central Maine Power. Section l04
states as follows: "The provisions of this Title shall be interpreted and construed liberally
to accomplish the purpose of this Title. The Commission has all implied and inherent
2 powers under this Title, which are necessary and proper to execute faithfully its express
powers and functions specified in this Title.
Section 101 of Title 35-A reads as follows:
The purpose of this Title is to ensure that there is a regulatory system for public utilities in the State which is consistent with the public interest and with other requirements of law. The basic purpose of this regulatory system is to assure safe, reasonable and adequate service at rates which are just and reasonable to customers and public utilities.
35-A MRSA §1501 provides that a public utility which violates, or causes or
permits a violation of this Title, may be liable in damages to a person injured as a result
of the violation.
In addition, it has long been the law in Maine that a public utility in Maine is
subject to legal principles which govern the law of negligence. In Fitts v. Central Maine
Power, 562 A,2d 690 (Me. 1989) the Maine Supreme Court held that an electric utility is
"bound to exercise due care and diligence." [Citing Edwards v. Cumberland County
Power and Light Co., 146 A, 700 (Me. 1929)]. In Fitts, the Court also stated that the
standard of care for a utility is "such care as an ordinarily reasonable and prudent person
would have exercised under like circumstances." [Citing O'Brien v. JG. White & Co.,
Inc., 128 Me. 207]. Thus, consumers of electricity in Maine are entitled to the "assurance
of a reasonable degree of safety." Id. at 212.
The Plaintiff argues that CMP was negligent because it violated PUC regulations
governing vertical height clearances, deviated from its own internal safety policies, and
failed to adequately train its employees in the application of those policies.
The Defendant's primary defense is that the PUC regulations relied upon by the
Plaintiff are not applicable to the power lines on Route 166. In addition, the Defendant
3 argues that Devereaux Marine's negligence was the sole proximate cause of Bryan
Smith's injuries. 1 In this regard, the Defendant relies on provisions of the Maine High
Voltage Wire Safety Act (MHVWSA) and OSHA standards which require a ten foot
setback, and notification to the utility, if work is done in close proximity to power lines.
The Defendant also claims that Devereux Marine negligently failed to train its employees
regarding working safely near power lines.
CMP's Internal Waterway Clearance Standard
The parties expended much effort in debating whether Table 232-1(8) of the
National Electrical Safety Code, and Chapter 910 of CMR 65-407 apply to the power
lines in issue. If those regulations apply, CMC would be in violation of height
requirements imposed by Maine law, and under 35-A MRSA §1501, CMP could be liable
to Bryan Smith for injuries caused by any such violations.
Before determining whether those regulatory provisions apply to the power lines
at Devereaux Marine, the Court finds that CMP violated its own standard for vertical
clearances for these power lines. That standard is similar, although not identical, to the
NESC standards found in paragraph 8 of Table 232-1. Defendant's Exhibit 30, which was
admitted by agreement, requires a 45.5 vertical clearance for these power lines. The
parties agree that their actual height was approximately 30 feet from the ground.
Gary Ricci, who has worked for CMP for over 30 years, has been responsible for
the design and planning of CMP distribution standards since 2001. He referred to
I The parties agree that Mr. Smith's exclusive remedy against Devereaux Marine is pursuant to the Maine Workers Compensation Act. The parties also stipulated that as of June 24, 2008, Maine Employer's Mutual Insurance Company (MEMIC) has paid a total of $26 I, 3 I 5. 70 on this claim.
4 Defendant's Exh. 30 as a "construction standard," and it was also referred to as
"Construction Standard 305-11." Mr. Ricci testified that the National Electrical Safety
Code standards are incorporated into his "standards book" which contains this standard.
He was asked by CMP's attorney what standard would control if there was a difference
between an NESC standard and a CMP standard, and Mr. Ricci indicated that there
would be no difference. The parties seem to agree that this standard was in effect within
the company at the time of the accident.
The internal CMP standard at issue requires a 45.5 foot vertical clearance in
"areas used for rigging and launching sailboats." The Court finds that the boatyard at
Devereaux was, at the time of this accident, such an area. The Court bases this on the
Court's view of the boatyard conducted on June 18, 2008, as well as photographs
admitted by agreement of the parties. The boatyard is filled with sailboats lined up in
rows throughout the boat yard, in areas selected based on space availability, and the need
to store and work on boats on level ground. Those areas are located just up a gradual
slope from a clearly-identifiable boat launch. Some of the boats sit in the yard without
masts. It would be obvious to any reasonable person that it is likely that sailboats are
being rigged for launching and unrigged for storage or repair at this boatyard.
In addition, the Court finds that this boatyard, in fact, rigs and launches sailboats
at this site, based upon the testimony of Andrea Devereaux, James Doyle, William
Stevenson, and the Plaintiff.
It is important to note that CMP's standard does not describe the size of the area,
or any distance requirements between rigging areas and launching areas. However, it is
clear from the view conducted that one can see the launching area from rigging areas,
5 and one can see rigging areas from the launching area. In addition, both sailboats and
launching area can be seen as soon as one pulls into the driveway, and also from Route
166. (Plaintiff's Exhibit 12.) The boatyard is clearly an "area used for rigging and
launching sailboats."
Training of eMP employees regarding vertical height clearances
On the third day of trial, five CMP employees testified about the training
programs conducted by the company for employees. The Defendant's proposed finding
number 43 concedes that it is the company's policy to make all employees responsible for
the safety of all persons around electrical lines, not just CMP employees.
Robert Bonin has worked for CMP for almost thirty years. He started as a meter
reader, then became a line worker, then a line supervisor, and he worked a safety analyst
in 2002 when the accident occurred. He was unaware of any CMP standard, or state law
or regulation, regarding vertical clearances for areas where boats may be rigged.
Carl Norman, a CMP employee since 1982, testified that he is a "lead line"
worker. He testified that he drives by the boatyard in question two to three times a month,
and had seen the crane that was located at the site, although he did not know what it was
used for. He testified that all CMP employees are trained to recognize hazards that violate
company standards, but was unaware of any standard or state regulation that dealt with
sailboat rigging areas.
Carroll Littlefield, a 35 year veteran ofCMP, was identified as a "troubleshooter"
for CMP. He said he had over the years driven by the boatyard numerous times, and had
6 seen boats stored along the road next to the power lines. Because no boats seemed to be
positioned within 10 feet of the power lines, he was not concerned with any safety issue
at the boatyard. He stated that he felt that a 27-foot vertical height requirement for power
lines at a rigging area was sufficient.
Peter Cella testified as a former member of CMP's Safety Committee. He
conceded that no training was provided to CMP personnel regarding standards for boat
rigging areas, nor were employees trained to be especially concerned about such areas.
Howard Klewen is the CMP District Line Supervisor for the Penobscot Bay area.
He also stated he was unaware of any vertical height requirements for rigging areas.
It was clear from the testimony of these employees, that CMP's safety training is
focused on the 10-foot requirements imposed by the MHVSA. While the employees were
aware of this 10-foot rule, with the exception of Mr. Ricci, no CMP employee was called
by either party to state that they were aware of the company's internal standard, much
less any state law or regulation about rigging areas. Mr. Ricci knew about the existence
of the internal standard and but seemed to believe it did not apply to the lines in question.
CMP argues that there was no need to provide this training to their employees,
because as discussed below, CMP argues that the NESC standards relied upon in part by
the Plaintiff are not applicable. This position begs the question, however, of why the
CMP employees called seemed to be unaware of the utility's own standard for "areas
used for rigging and launching sailboats." This failure to even be aware of internal
standard puts CMP in the position of having to argue that neither the NESC or internal
standards are applicable. But the failure to provide basic training about any vertical
7 clearances standards for boatyards such as Devereaux Marine undermines these
arguments.
CMP 's Prior Knowledge
CMP installed power lines along Route 166 no later than 1951. The lines were
within a public right of way, and that is still the case.
The Devereaux Marine lot is part of a parcel of land that had been in the
Devereaux family for approximately 200 years. Approximately two acres of this parcel
sit west of the power line down to Penobscot Bay, with approximately one acre sitting
east of the power line. The western portion of the parcel, which is where the accident
occurred, is bounded on the north by a private driveway that goes from Route 166 down
to the launching ramp on Penobscot Bay. It is bounded on the south by a single-phase
CMP distribution line. The western boundary is Penobscot Bay, and the eastern boundary
is Route 166 and the power line is issue. Both the single and three-phase lines carry 19.9
kV of power, and all lines are located approximately thirty feet above the ground.
The single-phase line was installed in 1985, and it replaced a previous line that
had crossed the property diagonally. This was the same year Devereaux Marine began
operating as a boatyard. Gary Ricci testified that he visited the site a couple of times
around that time period to discuss with C. Russell Devereaux, who owned the boatyard at
the time, the location of the new line. He testified that he knew that the business was
called "Devereaux Marine." He also stated that he knew from speaking with Mr.
Devereaux that the business put boats in the ocean, and took boats out of the ocean. He
denied knowing much else about what the business did. He also indicated that while he
8 knew that there was a standard for vertical clearances for rigging sailboats at the time the
single-phase line was relocated, he did not know what it was.
Andrea Devereaux testified that her father, C. Russell Devereaux, who is now
deceased, contacted CMP around the time the boatyard started operations, to ask them to
move the three-phase line to the easterly side of Route 166. She stated her father was
concerned about electrical accidents. Gary Ricci denied that Mr. Devereaux discussed
with him his desire to relocate the three-phase line, and stated that CMP was only asked
to relocate the single-phase line to service buildings at the back of the boatyard property.
CMP did relocate the single-phase line, and Devereaux Marine paid for the relocation.
In January of 1989, Andrea Devereaux Doyle and her husband, James Doyle, Jr.,
took over business operations, and incorporated under the name Devereaux Marine, Inc.
In early 1989 Mr. Doyle went to the CMP office to talk to someone about raising the
three-phase line on Route 166 so that the travel lift could move boats back and forth
across the road, and also to discuss the possibility of burying the power lines on the
property. Mr. Doyle testified that CMP personnel told him that they would do so, but
only ifhe paid for the work to be done. He stated that his business could not afford to pay
the price quoted. Sometime after the meeting with CMP, the three-phase line was raised
to enable the travel lift to go underneath the line.
In 1998, a back-stay of a sailboat came into contact with the power line in issue,
when Robert Fairweather backed a masted sailboat from the launch towards Route 166.
No one was hurt in this accident, but CMP crews had to restore power to the Town of
Castine as a result.
9 Howard Klewen testified that in March of 2002, after his promotion to District
Line Supervisor, he saw sailboats lined up along the highway. He says he stopped by and
discussed his concerns with Andrea Devereaux, who denies that any such conversation
occurred. He also testified that he gave her a safety warning, and explained the 10-foot
safety setback rule.
The Plaintiff questions Mr. Klewen's credibility on this issue, pointing out that he
was not credible when he testified that William Stevenson made admissions at the scene
of the Plaintiffs accident. The Court agrees with the Plaintiff that it is not likely that such
admissions were made, since the Court finds it was likely, based upon the testimony of
Mr. Bonin and Ms Devereaux, that Mr. Stephenson and Mr. Smith had been transported
from the scene before Mr. Klewen arrived. However, if the Defendant is correct that Mr.
Klewen warned Andrea Devereaux about the 10-foot safety setback rule, Mr. Klewen's
testimony actually supports the Plaintiff s position that CMP was aware of the safety
issues presented by the proximity of sailboat masts and the power lines along Route 166.
Mr. Klewen, as well as the CMP employees who dealt with the Mr. Devereaux and Mr.
Doyle, the CMP employees who drove by and saw the sailboat masts lined up near the
power lines, and the CMP employees who were involved in restoring power to Castine in
1998, were all on notice that Devereaux Marine was an area where sailboat masts and
power lines were in close proximity.
The Defendant argues that the 1998 incident proves little or nothing, because the
"contact had nothing to do with the act of rigging a sailboat." (Page 6, Defendant's
Proposed Findings). The Court disagrees that the accident proves nothing. The 1998
incident could have turned out as tragically as the incident that resulted in the instant
10 litigation, and it is sheer luck that it did not. The 1998 incident alone put CMP on notice
that sailboat masts could run into power lines at Devereaux Marine, given the vertical
clearances CMP maintained along Route 166. The 1998 incident, together with the
interactions between CMP and Andrea Devereaux, C. Russell Devereaux, and James
Doyle, Jr. establish that CMP was aware of the dangers presented by the close proximity
of power lines and sailboat masts at the boatyard.
Applicability ofNESC standards to Maine law
The parties have extensively briefed and argued about the applicability, as well as
the meaning, of standards set forth in Table 232-1 of the National Electrical Safety Code.
35-A MRSA 2305-A(2) provides as follows:
Except as otherwise provided in this section or by rules of the commission adopted pursuant to this section, every transmission and distribution utility, telephone utility and cable television company shall design, construct, operate and maintain its lines and equipment in conformance with the applicable provisions of the recent edition of the Standard. (emhasis added)
"Standard," according to paragraph 1C of that statute, means the National
Electrical Safety Code (NESC)-ANSI-C2.
Both parties called experts to opine about whether or not Table 232-1(8) of the
NESC applies to the power lines along Route 166. Paragraph 8 of that Table provides a
vertical clearance requirement of 45.5 feet for "established boat ramps and associated
rigging areas," as well as "areas posted with sign(s) for rigging or launching sailboats in
areas serving water bodies of more than 2,000 acres." The parties agree that Penobscot
Bay is a water body of more than 2,000 acres.
11 The Defendant, however, argues that the portion of the Table that contains
paragraph 8 is not "applicable," because the subheading above paragraph 8 suggests that
it applies only where lines cross over or overhang a launch or rigging area. The
Defendant's expert, Frank Denbrock, testified that in his view the lines in issue do not
"cross over" because that only applies if "lines are not in the roadway right of way and
cross over the roadway or a rigging area." (Defendant's Post-Trial Brief, pg. 3) He points
to the sub-heading in the table that in his view more aptly describes the surface
underneath the wires in issue: "Where wires, conductors, or cables run along and within
the limits of highways or other road rights-of-way but do not overhang the roadway."
(Def. Exhibit 1, page 77, 78). If that is the case, as a matter of Maine state law at least,
the wires need only be, according to paragraphs 9, 18.5 feet high. He emphasized his
understanding of the words "cross over" and "overhang," and also emphasized the fact
that the lines "run along and within" the highway or right-of-way of Route 166.
The Plaintiff's expert, David Marne, testified that in his view the lines did cross
over or overhang a boat ramp and associated rigging area, as well as an area posted with
signs for rigging and launching sailboats. He also testified that "common sense" would
dictate that a utility has an obligation to adhere to all applicable standards, and that by
maintaining vertical clearances according to paragraph 8 of the table, CMP would also be
complying with the 18.5 foot requirement in paragraph 9.
The Defendant further asks the Court to engage in statutory construction of the
two subheadings and to conclude that there exists an ambiguity, at least, in the Table's
use of two sub-headings. The only way to resolve the ambiguity, CMP argues, is to look
"to the statute's legislative history as well as other indicia of legislative intent in order to
12 determine" which subheading applies to the power lines along Route 166. (Def.' s
Statutory Construction Rules, pg. 2). Citing Toomey v. Town ofFrye Island, 943 A.2d
563 (Me. 2008).
While the Court agrees that the above argument correctly states the general rule of
statutory construction, the Defendant's position fails to recognize the import, in the
Court's view, of clear language in another provision of Maine law, namely CMR 65-407
910. The Court believes that Section 3 of the Code requires CMP to look directly at
paragraphs 7 and 8 of the NESC Table. That Section begins as follows:
All overhead lines of an aerial utility crossing water areas suitable for sailing, or public or private land and water areas posted for rigging or launching sailboats, shall comply with the vertical clearance requirements of Section 232 of the the National Electrical Safety Code, Table 232-1, sections 7 and 8 thereof, together with all applicable footnotes ... (emphasis added).
The 45.5 foot requirement for such areas first carried legal force, the parties seem
to agree, in an Order from the Public Utilities Commission dated July 19, 1988 after two
fatal accidents where sailboaters were electrocuted on Sebec Lake and on Great Pond.
That Order further noted that while new lines were required to comply with the most
recent version of the NESC, there was in fact no requirement that older lines, such as
those along Route 166, comply with the "water crossing requirements of the Code."
(Plaintiff's Exh. 5).
CMR 65-407-910 was promulgated on July I, 1990, and eliminated the
distinction between old and new lines. It also provided a definition of "areas posted for
rigging or launching sailboats" to include "any area that by signs, launching ramps, or
other special facilities, land improvements or use indicates that the area is intended to be
13 used by the public for rigging or launching sailboats." (Plaintiffs Exh. 7). When the PUC
issued its Order adopting this new Rule, it stated it was intended to "impose an additional
safety measure beyond what the current Code requires." (Plaintiffs Exh. 6).
The Court finds that Devereaux Marine is an area that, by use, "is intended to be
used by the public for rigging or launching sailboats." Therefore CMR 65-407-910 points
CMP directly to paragraphs 7 and 8 of Table 232-1 of the NESC.
The Court bases this finding on the fact that the boatyard is indeed a private
company, but its customers are, as CMP concedes, members of the public. The boatyard
along both the triple-phase and singe lines is filled with stored sailboats. The boats were
stepped and unstepped where they were stored. The Court is not persuaded that "public"
can rationally be read as narrowly as urged by CMP. According to the Defendant, only
public boat launches shown on the current public access inventory maintained by the
Department of Conservation. However, the citation relied up by the Defendant is not as
limiting as the Defendant urges. It states: "We intend that within such definition would
be all boat launching sites shown on the current public access inventory." (Emphasis
added). That provision, contained within the Order and Factual Findings and Policy
Statement of July 19, 1988 does not support the Defendant's interpretation that it applies
only to such sites. CMR 65-407-910 directs CMP to provide a 45.5 foot vertical clearance
in any area intended to be used by the public, not just those on the inventory. Such a
narrow interpretation is at odds with the liberal interpretation and construction that the
Court must apply, according to 35-A MRSA § 104.
Because the Court finds that CMR 65-407-910 controls, it is not necessary to
resolve any ambiguity that might exist in the two subheadings of Table 232-1. The Code
14 points CMP directly to paragraphs 7 and 8 of the Table. The Court therefore declines to
determine, as a matter of law, if the first clause of paragraph 8 applies to the lines along
Route 166, that is, "established boat ramps and associated rigging areas." The Court does
find as fact that the boatyard is such an associated rigging area. The Court makes that
factual finding for the same reasons that it found that the boatyard is an "area used for
rigging and launching sailboats," in the findings made above regarding CMP's internal
vertical clearance standard.
Taking these findings together - CMP's failure to comply with CMR 65-407-910,
its prior knowledge of the proximity of sailboat masts and power lines along Route 166,
its failure to follow its own vertical clearance standard, and its failure to adequately train
key safety employees about even the existence of this standard and the law of Maine -
the Court finds that CMP failed to exercise due care and diligence in its operation and
maintenance of the power lines along Route 166 in Penobscot, Maine.
Causation
The Plaintiff must prove not only that CMP was negligent, but also that CMP's
negligence was the proximate cause of Bryan Smith's injuries. CMP makes two
arguments on the issue of causation. First, it argues that there is insufficient evidence to
support the Plaintiffs argument that a 45.5 foot vertical clearance would have prevented
this accident. The second argument is that Devereaux Marine's own negligence, in the
form of violations of OSHA and MHVWSA requirements of a 10-foot setback and
notification, was the "sole proximate cause" of the Plaintiffs injuries.
15 With respect to the first argument, the Court accepts many of the factual findings
proposed by the Defendant. Proposed Finding 81 asserts that the mast was 35 feet, four
inches long. Proposed Finding 80 asserts that the deck of the customer's sailboat was 9
feet 8 inches off the ground. Therefore, when the mast was placed upright at a ninety
degree angle it was approximately 45 feet from the ground. In addition, the power line in
question was approximately 30 feet from the ground. (Proposed Finding 82). The Court
also accepts Proposed Finding 79 that it "was while his back (Stevenson's) was turned
that the mast made contact with the power line." The Court would also note Proposed
Findings 75, 76 and 78 which establish that Stevenson had lowered the mast at an angle
to the Plaintiff, who was standing on the ground and holding it at approximately waist
level, when Stevenson turned his back. Finally, the butt of the mast was approximately
three feet off the ground, if one reads Proposed Finding 83 and 84 together. The Court
infers that if the Plaintiff was holding the mast straight up, and not at an angle, the tip of
the 35 foot, 4 inch mast would have been 38 feet, 4 inches in the air.
Assuming those facts are true, it is implausible that a mast of this same length,
held with a butt end three feet off the ground, at less than a 90 degree angle, would have
contacted a power line with a vertical clearance of 45.5 feet. The Court therefore finds
that this accident would not have occurred if CMP had maintained a 45.5 foot vertical
clearance.
With respect to the issue of "sole proximate cause," the Defendant points out that
Devereaux Marine had no formal training for its employees regarding working near or
under power lines. It also provided no written materials, safety equipment or signage
warning employees of such hazards. William Stevenson, the boatyard manager, was
16 unaware of the MHVWSA or OSHA regulations requiring unqualified persons to notify
CMP if they were going to be working within 10 feet of a power line. The Court agrees
that those facts have been established by the Defendant.
It has not been established on this record that the accident actually occurred while
either Mr. Stevenson or Mr. Smith were themselves within 10 feet of the power lines. 2
However, Defendant's 14 and Defendant's 15 establish that Devereaux Marine was
indeed cited by OSHA for two violations as a result of this accident. The former points
to inadequate training for working near power lines, and the latter points to a federal
regulation that prohibits any "unqualified person" from working in an elevated position in
a "such that the person and the longest conductive object" were less than 10 feet from
unguarded power lines. It is clear that the mast itself, while being handled by Mr. Smith,
actually touched the power line. Therefore, it has been established that at the time Mr.
Smith was injured, Devereaux Marine allowed him to work in violation of the federal
regulation as defined by Defendant's Exh. 15. The Court further agrees with the
Defendant that Devereaux Marine was negligent in failing to train Mr. Smith or other
"unqualified" employees about safely working under power lines, and allowing them to
handle sailboat masts too close to power lines, in violation of federal regulations and the
MHVSA. The issue for the Court is whether this negligence by Devereaux was the "sole
proximate cause" of the Plaintiffs injuries.
The Plaintiff argues that there is "no evidence that any mast on any stored boat
was ever closer than 10 feet from the power line until the instant when the mast suddenly
contacted the line, causing Bryan's injuries." (Plaintiffs Post-Trial Memorandum, pg.
2 Proposed Findings 7] and 72 posit two points in time just before the accident when the mast was just six inches outside the] 0 foot limit, and when the person handling the mast plus the mast were within] 0 feet of the power line.
17 10). The Court does not agree that this statement adequately describes the facts at hand,
since Mr. Smith was not injured while the masted boat was stored. The accident occurred
when it was being unstepped.
Considering all of the above-referenced findings proposed by the Defendant and
accepted by the Court, together with the largely-undisputed distances and measurements
taken by the parties, it can hardly be said that Devereaux Marine's negligence, such as it
was, was the "sole proximate cause" of this particular accident. The Court can envision
many scenarios by which this sailboat mast given its location, either stepped or while
being unstepped, could have come into contact with power lines which were 30 feet off
the ground. It is much more difficult to envision a scenario in which this sailboat, even if
it was located closer to the lines than it was, could have come into contact with a line
with a 45.5 foot clearance - unless perhaps it was stored directly underneath the lines,
which it was not. What caused this mast to contact the power line on October 31, 2002
was not solely that the work was performed either within10 feet of the three phase line at
some points in time during the unstepping process. The accident was caused by the fact
that this 35 foot, four inch mast, with its butt end held three feet off the ground at an
angle of less than 90 degrees, hit a power line that was set at 30 feet, and not at 45.5 feet,
as required by law. If the law allowed these lines to have a vertical clearance of 30 feet,
the Court might reach a different conclusion, but the law required the lines to have a 45.5
foot vertical clearance. 3
The basis for the "sole proximate cause" defense is "that some other actor or force
(whether or not a party) is the only proximate cause of an accident, therefore all others
3 It is perhaps worth noting that the failure to maintain proper vertical clearances for these lines is only part of the factors the Court relied upon in its finding that CMP was negligent.
18 are insulated from liability." Bukowski v. Geo. A. Harmel & Co., 157 F.R.D. 50 (S.D.
Iowa 1994). (Emphasis added).
The Court cannot find on this record that Devereaux Marine's negligence was
"the sole proximate cause" of Bryan Smith's injuries. The Court therefore finds that the
Plaintiff has carried its burden of proof in this negligence action.
Damages
CMP concedes in its argument that "It is clear that Bryan Smith has suffered
injuries in all categories recognized by the Maine Law Court." CMP also states that
"Plaintiff s past medical expenses and post (sic) lost wages are well established and are
not the subject of contest." (Pg. 21, Defendant' Post-Trial Brief).
The Court finds Plaintiff s past medical expenses to be $231,194.73, as agreed by
the parties.
The Plaintiff urges the Court to accept the findings of future rehabilitation costs to
be $551,913. That was the figure computed by Barbara Bate, an expert life care planner
whose report was admitted as Plaintiff s Exh. 20. The Defendant did not provide expert
opinion rebutting Ms. Bates's methodology or opinion. The Court has reviewed her
report, considered her testimony, and finds that her conclusion is well-supported by its
foundations. The Court therefore accepts that Mr. Smith's future rehabilitative needs
require this sum, which reflects a reduction to present value.
The Court therefore finds that Mr. Smith is entitled to the sum of$783,108 for
past and future medical and rehabilitation damages.
19 The Plaintiff called Lawrence Copp, a well-qualified economist, who testified by
deposition on May 29, 2008 as to Mr. Smith's lost income due to this accident. The
Defendant called no expert to challenge his methodology or conclusions. As foundation
for his opinion, Mr. Copp relied upon reports and telephone consultations with Ms. Bate
and other medical and vocational experts. Among them was Jacques Violette, a
Vocational Rehabilitation Counselor, whose report was admitted as Plaintiff's Exh. 19.
Mr. Violette determined that Mr. Smith's residual work capacity is limited to "sedentary
to light." Mr. Violette provided information about what Mr. Smith could have earned if
he was able to return to the Air Force, which had been his longstanding goal.
The Plaintiff testified that he had recently been medically discharged before the
accident from the Air Force, due to a foot injury that required surgery. The Air Force
required him to be medically "cleared" for one year before he could return to the military.
Mr. Smith testified credibly that being in the Air Force had been his goal since he was a
child. His plan was to serve as an airplane mechanic. Although this dream had been
temporarily deferred by his bunion injury, the Court accepts his testimony and finds that
it was likely that he would return to the Air Force.
The Court finds also, based on the testimony of the Plaintiff, his father and
employers, that Mr. Smith had, and still has, a strong work ethic. He has since the injury
attempted to hold jobs, even when the jobs he undertook caused him further physical pain
and injury. It is clear that one of the hardest things Mr. Smith has had to accept as part of
the devastating physical and neurological injuries he has experienced, is that no matter
how hard he tries, he will never reach his goal of serving in the Air Force.
20 The Court also finds that it is unlikely that Mr. Smith could now obtain an
advanced or associates degree. The Court bases this on the unrebutted testimony of the
Plaintiffs expert neuropsychologist, Dr. Anthony Podraza. Mr. Smith clearly has
accident-related neurological deficits, and he struggles with accident-related depression.
Finally, given the fact that he graduated from high school and went off to the Air Force,
and not to college, it seems unlikely that he was, as the Plantiff states, "college-bound"
before the accident. (Plaintiff s Post-Trial Memo, pg.46.)
The Court recognizes that there cannot be absolute certainty about the kind of
economic future Mr. Smith would have had if the accident had not occurred. However,
the Court finds that it is reasonable to assume, as the basis for projecting his future
earning potential, what he could have earned in the Air Force had he not been injured.
The Court finds based on the opinion of Mr. Copp, that the present value of Mr. Smith's
lost earnings is $1,107,523.
The total of Mr. Smith's special damages constituting past and future medical
expenses, and lost earnings, comes to $1,890,631.
In determining the amount of damages Mr. Smith should receive for his loss of
enjoyment of life, pain and suffering - what the Plaintiff calls "general damages" - the
Court considers the following facts, none of which are really subject to dispute.
Mr. Smith was in a hospital for two months. He endured many painful surgeries
and procedures. Those procedures included frequent, sometimes daily, debridements
which consist of peeling away dead skin and tissue. He has had multiple skin grafts. He
lost his right big toe, as well as the right metatarsal bone in his foot, through amputations.
Dr. Celia McLay, a physiatrist, testified by deposition that these amputations have had
21 profound consequences for his gait, weight-bearing and stability. It is not uncommon for
him to roll his ankle and/or fall. He has a permanent limp. He has more than once
"blown out" the bottom of his right foot while walking on it because of its lack of
structural and tissue integrity. He has been urged not to work at least once by his
physiatrist because standing on his feet was preventing his foot from healing, and was in
fact re-injuring it. Mr. Smith has significant loss of feeling in his fingers of his left hand,
and the function of his hand is much diminished. He cannot feel heat or cold in this hand,
and is therefore vulnerable to burning or other injuries to this extremity.
Mr. Smith has scars that are very difficult to look at, including skin flaps on his
left wrist and a skin flap on his right foot. Both his wrist and hand are terribly disfigured.
One prominent scar is on his left side, into which his left hand had to be sewn for three
weeks to keep tissue from dying while it was healing, and he has another on his
abdomen. He had to undergo additional surgeries to have tissue expanders put in his
abdomen, and later removed, as part of the process of repairing or removing scar tissue.
Mr. Smith has significant neurocognitive defects, depression and post-traumatic
stress disorder. The Court finds that these are all related to his accident. He lost 55
pounds while in the hospital, but has gained that and much more back due to immobility.
He spent much of his time in the hospital, and while in recuperation at his parent's home,
in a drug-induced sleep. He suffers from chronic pain, although it has waxed and waned
with various medical procedures and setbacks. He had to take opiates for his pain from
the time of the accident to the spring of 2008, when he finally stopped taking them on his
own.
22 Mr. Smith used to be a runner, and can no longer do so. He is able to continue to
hunt and fish, but he must do so while seated. He often needs assistance to button pants
or shirts. He required assistance going to the bathroom for approximately six months after
the accident.
Dr. Philip Kimball conducted an evaluation ofMr. Smith for Maine Employer's
Mutual Insurance Company in January of 2008, and concluded that he has sustained a
42% whole body permanent impairment injury as a result of his electrocution.
After considering all of the above, including the Plaintiff s demeanor and
presentation at trial, the Court concludes that this is a case requiring significant
compensation for general damages. Mr. Smith has endured extreme physical pain, and
now has chronic pain. His life has been permanently altered, and in many ways
diminished. He has permanent disfigurement, and permanent physical impairment. He
has admirably tried under very difficult circumstances to work for a living, and to be as
independent as he can. Nevertheless, it is likely that his neuropsychological injuries are
permanent as well, and according to Dr. Podraza, some persons who have survived
electrocution actually decline over time in their functioning.
The Court awards Mr. Smith $3,000,000 in general damages.
The entry will be:
The Plaintiff has proven by a preponderance of the evidence that Central Maine
Power was negligent, and that its negligence proximately caused his injuries.
23 The Court finds that the Plaintiff is entitled to damages in the total amount of
$4,890,631. The Plaintiff is further entitled to interest and costs.
Counsel for the Plaintiff is directed to prepare a Judgment consistent with these
findings.
The Clerk shall note these Findings and Conclusions on the docket pursuant to
Rule 79(a) of the Maine Rules of Civil Procedure.
1113/~tf DATE b~ SUPERIOR COURT JUSTICE
24 STATE OF MAINE SUPERIOR COURT Penobscot, ss. Docket No. CV-2007-00174 rv"',' \ ,\ \ I~' L ;", I I :. I ,
BRYAN A. SMITH of Bangor, ) Penobscot County, Maine, ) ) Plaintiff, ) ) v. ) Judgment ) ------ CENTRAL MAINE POWER ) FILED & ENTERED COMPANY, a Maine corporation ) SUPERIOR COURT with its principal place of business ) NOV 1 4 2008 in Augusta, Kennebec County, ) Maine, ) PENOBSCOT COUNTY 1~ " >t'i'tA' In accordance with the Findings and Conclusions of this Court datea l"lOVemOer~, ... "1lo.T
IT IS ORDERED That Judgment be entered for Plaintiff against the Defendant in the amount of
$4,890,631 with prejudgment interest at the rate of7.99% per annum and post-judgment interest
at the rate of9.42% per annum and costs.
Dated: November l i , 2008 Jusikbea:::: 01/27/2009 MAINE JUDICIAL INFORMATION SYSTEM PENOBSCOT COUNTY SUPERIOR COURT PAGE P - PARTY VIEW BRYAN A SMITH VS CENTRAL MAINE POWER COMPANY CASE #:BANSC-CV-2007-00174
SEQ TITLE NAME DOB Any 001 PL BRYAN A SMITH BY: Lisa Lunn, Esq. & Barry Milli, ltsq. T 002 DEF CENTRAL MAINE POWER COMPANY BY: Mark Dunlap, Esq. T