Smith v. Boston, Concord & Montreal Railroad

36 N.H. 458
CourtSupreme Court of New Hampshire
DecidedJuly 15, 1858
StatusPublished
Cited by5 cases

This text of 36 N.H. 458 (Smith v. Boston, Concord & Montreal Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Boston, Concord & Montreal Railroad, 36 N.H. 458 (N.H. 1858).

Opinion

Bell, J.

This case raises several questions of some difficulty, both as to the pleading and the construction of the contract declared on.

Of these the first is, whether breaches of several distinct and separate provisions of the contract can be properly assigned in the same count.

There can be no doubt, says Lawes, (Pleading in Assumpsit 278,) but that in assumpsit the plaintiff is not confined to assign one single breach, as he is in declaring in debt for a penalty; but may, in the former action as well as in covenant, assign as many breaches as ..he thinks proper; at all events, where he does not declare on a promise to pay a penal sum. Lee v. Hewitt, 4 East 154; Athawes v. Ash, Lawes Ast. 73, n; 2 Ch. Pl. 94, 134; 1 Chitty’s Pl. 295; 1 Saund. Pl. & Ev. 133; Com. Dig., Pl., C, 33; 2 Went. Pl. 2,10, &c.

II. 1. No time is stated when the defendants were to furnish the right of way, &c.

No time is stated in the contract, nor from the nature of the contract was it possible to state any. They must be furnished, as they should become necessary in the progress of the work. [485]*485Where an agreement is mads to do certain things, without any designation of time, the law determines they shall be done in a reasonable time. It is sufficient that the contract is stated as it is made, because the agreement is to be construed in the pleadings, as it is in the original writing.

Neither is it necessary, in alleging the breach, to aver that a reasonable time for the performance has elapsed, and the work has not been done, unless it would otherwise fail to appear from the facts stated, that the stipulation was broken. In the present case it is alleged that the contract of the plaintiff was to be completed before a fixed date, “ on or before October 20.” These stipulations must of necessity precede the completion of the contract ; and an averment that the defendants did not furnish the same at the time they ought to have been furnished, is a sufficient allegation of the breach in this respect.

II. 2. Whenever a request is necessary to be alleged in order to entitle the plaintiff to a right of action, it is necessary that such request should be stated, with time and place, which is not here done. But a request is not necessary in this case. It is not stipulated that these things should be furnished on request, nor can a request be reasonably implied. The need there would be of these things was just as apparent to the defendants as to the plaintiff; Dix v. Flanders, 1 N. H. 246 ; Watson v. Walker, 23 N. H. (3 Foster) 491; and their contract was, that they should be seasonably furnished, without any action of the plaintiff.

II. 3. Whenever an enumeration of particulars would tend to prolixity, a general statement is sufficient. 1 Saund. 116, note 1; 1 Ch. PL 240. That seems in a special manner the nature of this case. The road was twenty miles or more in length. The right of way, track iron, sleepers, and fencing, were to be furnished at all points, and borrowing pits, and station buildings, where required. In the event of any extensive failure to perform this stipulation, it must be impracticable to state the particulars without a very long and detailed statement; and it does not seem to us that such a specification could be reasonably required in a declaration. If it should appear to the court, on application, [486]*486that such specification was in fact necessary, it might he ordered. Gould’s PL IV., secs. 26, 83, 36; 1 Chitty’s PI. 240.

III. 1. It is objected that the count does not aver that the aggregate amount of all material, &c., was increased by the definite location over the amount shown by the preliminary estimates, &c. The allegation excepted to is as follows:

“ And the said plaintiff avers, that in the building and construction of said railroad, as aforesaid, the aggregate amount of material encountered by the said plaintiff, upon the whole line of said road, was increased by the definite location of the same over the amount as then, to wit, on said first day of July, A. D. 1851, shown by the preliminary estimates in the engineer’s office of said corporation,” &c.

The contract speaks of the aggregate amount of all material; the declaration uses the phrase, the aggregate amount of material, omitting all. It might make a very essential variance in the effect of the contract, if the language of the declaration could be so construed as to make the company liable for any increase of the aggregate material of each kind, instead of the aggregate of all kinds of materials, but it does not seem to us that by any fair construction the contract or the declaration can be so understood; nor does the omission of the word all in any way vary what would otherwise be the effect of the agreement.

III. 2 to 8. These exceptions all rest on the same principle. They raise the questions, whether the plaintiff is entitled to recover any thing on account of any increased aggregate of material, unless upon the allowance of the engineer. Whether it is not the province of the engineer to ascertain, if the aggregate is increased, and how much, as well as what allowance is to be made, and whether it is not the duty of the plaintiff to show that he has done so, or that he has been called upon to do it, and has refused; or that some just cause exists why that has not been done, and if such allowance is made, whether the defendants are liable until notice of it.

The views of the parties differ entirely on these questions ; the plaintiff referring to the estimates in the engineer’s office only, [487]*487for the aggregate on the preliminary location, averring, in general terms, the aggregate to have been increased, and to what extent, as matters of fact, to he proved and settled upon the trial; while the defendant contends that by the contract the engineer is made the exclusive judge of the quality and quantity of the work, and no action can be maintained, unless upon his measurement and allowance ; that it is the duty of the plaintiff to procure such measurement and allowance, and to give the defendant notice of the result, before any action can be maintained.

An agreement to refer any matters of dispute that may hereafter arise between the parties, is not unusual in contracts of insurance, of partnership, and for the construction of large buildings and other works. In general such contracts do not bar the parties of their remedies by action at law. Scott v. Avery, 20 E. L. & E. 327, 36 E. L. & E. 1; Avery v. Scott, 20 E. L. & E. 334, 8 Exch. R. 487; Goldstone v. Osborne, 2 C. & P. 550 ; Haggart v. Morgan, 4 Sandf. Sup. Ct. 198 ; Reeves v. White, 10 E. L. & E. 343; nor by suit in equity. Mexborough v. Bower, 7 Beav. 127.

They will not be specifically enforced in equity ; Blundell v. Buttargh, 17 Vesey 232 ; Milnes v. Gry, 14 Vesey 400 ; and an action at law on such an agreement affords no effectual redress for a refusal to refer, since it is not easy to show that the party has sustained any actual damage by the refusal.

If an award is actually and fairly made, in pursuance of such a stipulation, by a disinterested arbitrator, the parties are bound by it, as they are in other cases of reference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matthew Benoit v. ARNE, LLC
Supreme Court of New Hampshire, 2020
Erin Food Services, Inc. v. Derry Motel, Inc.
553 A.2d 304 (Supreme Court of New Hampshire, 1988)
Pine Gravel, Inc. v. Cianchette
514 A.2d 1282 (Supreme Court of New Hampshire, 1986)
D. M. Holden, Inc. v. Contractor's Crane Service, Inc.
435 A.2d 529 (Supreme Court of New Hampshire, 1981)
Belleau v. Hopewell
411 A.2d 456 (Supreme Court of New Hampshire, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
36 N.H. 458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-boston-concord-montreal-railroad-nh-1858.