Smith Design & Constr., Inc. v. N.L. Constr. Corp.

2014 Ohio 4904
Ohio Court of Appeals·Decided November 3, 2014·No. 2014 CA 00002·Published·Cited by 1 cases

Opinion

COURT OF APPEALS

STARK COUNTY, OHIO

FIFTH APPELLATE DISTRICT

SMITH DESIGN & CONSTRUCTION, JUDGES: INC. Hon. William B. Hoffman, P. J.

Hon. W. Scott Gwin, J.

Plaintiff-Appellee Hon. John W. Wise, J.

-vs- Case No. 2014 CA 00002 N.L. CONSTRUCTION CORP.

Defendant-Appellant OPINION

CHARACTER OF PROCEEDING: Civil Appeal from the Court of Common Pleas, Case No. 2013 CV 02517

JUDGMENT: Affirmed

DATE OF JUDGMENT ENTRY: November 3, 2014

APPEARANCES: For Plaintiff-Appellee For Defendant-Appellant

JAMES M. MCHUGH IAN H. FRANK DAVID L. DINGWELL AARON S. EVENCHIK TZANGAS PLAKAS MANNOS LTD FRANTZ WARD LLP 220 Market Avenue South 2500 Key Center Eighth Floor 127 Public Square Canton, Ohio 44702 Cleveland, Ohio 44114-1230

Wise, J.

{¶1} Appellant N.L. Construction, Inc. appeals the December 18, 2013, decision of the Stark County Common Pleas Court denying its Motion to Stay Proceedings pending arbitration.

{¶2} Appellee is Smith Design & Construction, Inc.

STATEMENT OF THE FACTS AND CASE

{¶3} This case arises out of a dispute between the parties, Appellant N.L.

Construction Corporation (NL) and Smith Design & Construction, Inc. (Smith Design), associated with the construction of a maintenance facility project for the Ohio Department of Transportation (ODOT) located in Noble County, Ohio (Noble County Project).

{¶4} NL was serving as the general contractor for the Noble County Project.

During the summer of 2010, Smith Design submitted its bid to NL to be selected to provide services as a subcontractor on the job. Following the signing of a Subcontract Agreement, Smith Design began work on the project.

Prior Court of Claims Litigation

{¶5} In 2011, Appellant N.L. Construction Corp. (NL) filed suit against the Ohio Department of Administrative Services in the Ohio Court of Claims case titled N.L. Construction Corporation v. Ohio Department of Administrative Services, et al., Case No. 2011-08318, (the "Project Litigation"). NL's claims against the State in the Project Litigation arose out of NL's prime contract with the State of Ohio for construction of the ODOT Noble County Maintenance Facility Project (the "Project"). NL subcontracted with Appellee Smith Design & Construction, Inc. for a portion of the concrete and masonry work on the Project. The State asserted a counterclaim in the Project Litigation for damages and delays related primarily to Smith's work. Based on the State's counterclaim, on November 9, 2011, NL filed a third-party complaint against Smith including indemnity against the State's claims.

{¶6} On December 30, 2011, Smith, in turn, filed a counterclaim against NL.

{¶7} On August 30, 2012, and as modified by the Court's November 28, 2012, Journal Entry Approving Settlement, the judge in the Project Litigation entered summary judgment against the State of Ohio, and in turn dismissed NL's indemnity counterclaims against Smith without prejudice. Smith then voluntarily dismissed its counterclaim against NL without prejudice, ending the Project Litigation between NL and Smith.

Current Stark County litigation

{¶8} On September 25, 2013, Appellee Smith filed a new Complaint in the Stark County Court of Common Pleas against Appellant NL ("Stark Litigation"). Appellee Smith asserted claims for sums allegedly due for certain work Smith performed as a subcontractor for NL on the Project.

{¶9} On November 22, 2013, NL filed its Answer denying the allegations in the Complaint and including a Statement regarding Counterclaims claiming that NL's Counterclaims are subject to a binding arbitration provision in the written contract between NL and Smith. Contemporaneously with the Answer, NL filed a Motion to Stay Proceedings Pending Arbitration pursuant to R.C. §2711.02.

{¶10} On December 4, 2013, Appellee Smith filed its Response in Opposition to Motion to Stay.

{¶11} On December 13, 2013, Appellant NL filed its Reply in Support of the Motion to Stay Pending Arbitration including an affidavit concerning the arbitration provision in the Subcontract Terms.

{¶12} On December 18, 2013, the trial court issued a Judgment Entry noting that the Court reviewed the Motion to Stay, Response in Opposition, and Reply Brief, and the trial court denied NL's Motion to Stay. The Judgment Entry did not articulate the basis for the Court's ruling or provide an analysis of the issues.

{¶13} Appellant now appeals, assigning the following error for review:

ASSIGNMENT OF ERROR

{¶14} “I. THE TRIAL COURT ERRED AS A MATTER OF LAW IN DENYING APPELLANT N.L. CONSTRUCTION CORP.'S ("NL") MOTION TO STAY PROCEEDINGS PENDING ARBITRATION BECAUSE THE CONTRACT BETWEEN APPELLANT AND APPELLEE CONTAINS A MANDATORY AND BINDING ARBITRATION PROVISION, AND NL NEVER WAIVED ARBITRATION.

I.

{¶15} In its sole Assignment of Error, Appellant argues that the trial court erred in denying its motion to stay proceedings pending arbitration. We disagree.

{¶16} “In determining whether the trial court properly denied or granted a motion to stay the proceedings and compel arbitration, the standard of review is whether the order constituted an abuse of discretion.” Bentley v. Cleveland Browns Football Co., L.L.C., 194 Ohio App.3d 826, 2011–Ohio–3390, 958 N.E.2d 585, ¶10 (8th Dist.) “Abuse of discretion” implies more than a mere error of judgment or law, but indicates that the trial court's attitude is unreasonable, arbitrary, or unconscionable.” Blakemore v. Blakemore, 5 Ohio St.3d 217, 450 N.E.2d 140 (1983).

{¶17} The issue before the trial court was whether the Subcontractor Agreement entered into between the parties contained an enforceable arbitration clause.

{¶18} The Subcontract Agreement was signed by Scott Smith on August 9, 2010, and returned by mail to NL. On August 11, 2010, NL’s representative, Eric Kerzan, signed the documents on behalf of NL and returned a copy of the signed documents to Smith Design.

{¶19} Appellant NL maintains that the contract contained a mandatory and binding arbitration provision. Said arbitration provision is set forth in a nine (9) page document captioned “Subcontract Terms”, which Appellant claims was attached to the Subcontract Agreement along with five other documents.

{¶20} Appellee maintains that this “Subcontract Terms” document was not included with the Subcontract Agreement, and that it never agreed to the terms contained therein.

{¶21} The Subcontract Agreement in this case is a two-page document which contains the following language:

{¶22} “5. CONTRACT DOCUMENTS

{¶23} “The Subcontractor shall perform its work and is hereby bound by the following documents hereby incorporated into this Subcontract Agreement:

{¶24} “1. Subcontract Terms

{¶25} “2. Scope of Work- "A"

{¶26} “3. Contract Documents – “B”

{¶27} “4. Insurance Coverage – “C”

{¶28} “5. Safety Coverage – “D”

{¶29} “6. Drug Free Workplace Participation – “E”

{¶30} “6. ENTIRE AGREEMENT

{¶31} “This Agreement and the listed attachments in paragraph 5 above constitute the entire agreement between the parties and no other representations; promises or understandings will be recognized unless signed in writing by both parties."

{¶32} The two-page Subcontract Agreement does not contain any references to arbitration. According to Appellee, the only subcontract documents presented to Smith Design for approval and execution were as follows:

 Subcontract Agreement (2 pages)

 Subcontractor Scope of Work, Exhibit A (3 pages)

 Contract Document Specifications, Exhibit B (7 pages)

 Insurance Coverage, Exhibit C (1 page)

 Safety Rules, Exhibit D (3 pages)

 Drug Free Workplace Policy, Exhibit E (1 page)

{¶33} The document attached to the Subcontract Agreement and captioned as “Exhibit B”, states:

The following Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated as follows:

1. The Subcontract Agreement

2. The General Contract Agreement between State of Ohio and NL Construction Corp.

Free access — add to your briefcase to read the full text and ask questions with AI

Smith Design & Constr., Inc. v. N.L. Constr. Corp., 2014 Ohio 4904 (Ohio Ct. App. 2014).

2014 Ohio 4904 (Smith Design & Constr., Inc. v. N.L. Constr. Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Arbor Grove Properties v. Clear Sky Realty, Inc.
2018 Ohio 1467 (Ohio Court of Appeals, 2018)