Smit Land & Marine, Inc. v. Whc, Inc.

CourtLouisiana Court of Appeal
DecidedMay 3, 2006
DocketCA-0005-1255
StatusUnknown

This text of Smit Land & Marine, Inc. v. Whc, Inc. (Smit Land & Marine, Inc. v. Whc, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smit Land & Marine, Inc. v. Whc, Inc., (La. Ct. App. 2006).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

05-1254 consolidated with 05-1255

SMIT LAND & MARINE, INC.

VERSUS

WHC, INC.

**********

APPEAL FROM THE SIXTEENTH JUDICIAL DISTRICT COURT PARISH OF ST. MARTIN, NO. 99-61611 & NO. 99-61612 HONORABLE KEITH RAYNE JULES COMEAUX, DISTRICT JUDGE

ULYSSES GENE THIBODEAUX CHIEF JUDGE

Court composed of Ulysses Gene Thibodeaux, Chief Judge, Jimmie C. Peters, and J. David Painter, Judges.

APPEAL DISMISSED; ORDER VACATED AND CASE REMANDED.

Bernard E. Boudreaux, Jr. Murphy J. Foster, III Breazeale, Sachse & Wilson, L.L.P. One American Place - Suite 2300 P. O. Box 3197 Baton Rouge, LA 70821-3197 Telephone: (225) 387-4000 COUNSEL FOR: Defendant/Appellant - WHC, Inc.

Lloyd Noble Shields 650 Poydras Street - Suite 2400 New Orleans, LA 70130 Telephone: (504) 581-4445 COUNSEL FOR: Defendant/Appellant - WHC, Inc. David Arthur Hurlburt Hurlburt, Privat & Monrose Post Office Drawer 4407 Lafayette, LA 70501 Telephone: (337) 237-0261 COUNSEL FOR: Plaintiff/Appellee - Smit Land & Marine, Inc.

Robert Beattie McNeal 1100 Poydras Street - Suite 3600 New Orleans, LA 70163 Telephone: (504) 599-8014 COUNSEL FOR: Defendant/Appellee - Exxon Mobile Pipeline Company

L. Katherine A. Theunissen Mahtook & Lafleur P. O. Box 3089 Lafayette, LA 70502 Telephone: (337) 266-2189 COUNSEL FOR: Defendant/Appellee - National Union Fire Insurance Co.

Patricia Elise Weeks Weeks & Gonzalez 400 Magazine Street - Suite 200 New Orleans, LA 70130 Telephone: (504) 799-2888 COUNSEL FOR: Defendant/Appellee - Exxon Mobile Pipeline Company THIBODEAUX, Chief Judge.

Plaintiff-appellee, Smit Land & Marine, Inc. (“Smit”), filed a motion for

partial summary judgment regarding its claim for nonpayment of fees allegedly owed

to it under its contract with defendant-appellant, WHC, Inc. (“WHC”). The trial court

granted the motion and certified the judgment as final pursuant to La.Code Civ.P. art.

1915(B). WHC has appealed the judgment as well as the trial court’s certification of

the judgment as final. For the following reasons, the appeal is dismissed, the order

certifying the partial summary judgment as final is vacated, and the case is remanded

for trial.

I.

ISSUES

1. Did the trial court err in certifying its judgment as final and appealable pursuant to La.Code Civ.P. art. 1915(B)?

2. Did the trial court erroneously find that there is no genuine issue of material fact as to Smit’s entitlement to the unpaid fees?

II.

FACTUAL BACKGROUND

In this ongoing litigation, multiple parties are suing and/or being sued

for damages resulting from alleged acts of negligence, breach of contract, and

intentional tort, arising out of a pipeline construction job. This saga began on August

28, 1998, when Exxon Pipeline Company, now known as ExxonMobil Pipeline

Company (“Exxon”), hired general contractor, WHC, to construct approximately

forty-six miles of pipeline in an area extending from the vicinity of Anchorage,

Louisiana to the vicinity of St. James, Louisiana. This project was referred to as the

South Louisiana Pipeline Project (“the project”). On October 15, 1998, WHC hired a subcontractor, Smit, to perform directional drilling work for four pipeline crossings

for the project. One of those crossings, known as the North Mississippi River

Crossing, is the subject of this dispute.

The North Mississippi River Crossing was to be placed under the

Mississippi River near Baton Rouge, Louisiana. The subcontract required Smit to

bore one hole of a sufficient capacity to house a single bundle of pipelines, consisting

of one twenty-four-inch pipeline and two twelve-inch pipelines. The work was to be

completed within twenty-five days. The final agreed upon price for the work to be

performed by Smit on the North Mississippi River Crossing was $898,388.15.

It is undisputed that this work was not completed in the manner

described by the subcontract. Rather, Smit completed the North Mississippi River

Crossing by drilling two holes instead of one—one hole was used for the placement

of the two twelve-inch pipelines and the other was used for the placement of the one

twenty-four-inch pipeline. In addition, this crossing was completed thirty to forty

days beyond the original twenty-five-day deadline. Smit explained that these contract

variations resulted because it was unprepared for soil conditions it encountered. Smit

claimed that this was a result of its reliance on erroneous soil condition information

set forth in the geotechnical report provided by Exxon.

The contractor, WHC, also had work obligations under the subcontract.

WHC was to provide Smit with equipment and personnel during its “pullback” and

“preream” operations of the drilling. According to WHC, these operations required

more work than originally expected because of the problems encountered by Smit on

the job. Therefore, WHC was necessarily required to provide additional supporting

work to Smit beyond what was originally set forth in the subcontract. WHC

submitted a claim to Smit in the amount of $621,410.77 for these additional support

services and withheld this amount from final payment to Smit. 2 Smit, in turn, sued WHC. It also filed a separate action in the same

district court1 against Exxon and Eustis Engineering Co., Inc. (“Eustis Engineering”),

the engineering firm that prepared the allegedly faulty geotechnical report for Exxon.2

In both suits, Smit sought payment of the unpaid subcontract fee of $621,410.77, as

well as $2,013,063.24 in additional costs it claims to have incurred during completion

of the North Mississippi River Crossing. Smit sought additional damages for

wrongful conversion of funds, unjust enrichment, breach of contract, and unfair trade

practices under the Louisiana Unfair Trade Practices Act.

Smit also sought, from WHC only, penalties for its nonpayment of funds

pursuant to La.R.S. 9:2784. Smit claimed that months had passed since WHC had

received its final payment from Exxon for all work under their principal contract;

however, it asserted that WHC had failed to pay it within fourteen days of receiving

those funds, in violation of La.R.S. 9:2784. Therefore, Smit asked the court to

impose the statute’s maximum penalty of fifteen percent ($93,211.61) of the

$621,410.77 being withheld, along with attorney fees.

WHC answered the petition and filed a reconventional demand, naming

as defendants, Smit; Exxon; Eustis Engineering; and Smit’s bonding company,

National Union Fire Insurance Co. (“National Union”).3 In its answer, WHC alleged

that Smit materially breached the contract, was negligent, and had been paid all sums

that it was due. Alternatively, WHC asserted the defenses of “set-off, reduction,

abatement or apportionment” in regard to any damages that it might be ordered to pay

1 The two lawsuits were consolidated on July 19, 2002. 2 WHC’s claims against Eustis Engineering were severed from its reconventional demand and transferred to the 24th Judicial District Court after a contradictory hearing on Eustis Engineering’s Motion to Dismiss in January, 2003. 3 National Union provided the performance and labor material bonds to guarantee the performance by Smit of the work required by the subcontract.

3 as a result of Smit’s claims. WHC also asserted its claim for payment of the

$621,410.77 in costs and expenses it claimed to have incurred as a result of the

additional work it was required to perform.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cal's A/C & Elec v. Famous Const Corp
220 F.3d 326 (Fifth Circuit, 2000)
Curtiss-Wright Corp. v. General Electric Co.
446 U.S. 1 (Supreme Court, 1980)
Rourke v. Coursey
338 So. 2d 1197 (Louisiana Court of Appeal, 1976)
Banks v. State Farm Ins. Co.
708 So. 2d 523 (Louisiana Court of Appeal, 1998)
City of New Orleans v. New Orleans Canal, Inc.
173 So. 2d 43 (Louisiana Court of Appeal, 1965)
Van Ex Rel. White v. Davis
808 So. 2d 478 (Louisiana Court of Appeal, 2001)
RJ Messinger, Inc. v. Rosenblum
894 So. 2d 1113 (Supreme Court of Louisiana, 2005)
Holiday City Builders, Inc. v. Acadian Aviation Corp.
386 So. 2d 1019 (Louisiana Court of Appeal, 1980)
Allis-Chalmers Corp. v. Philadelphia Electric Co.
521 F.2d 360 (Third Circuit, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
Smit Land & Marine, Inc. v. Whc, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/smit-land-marine-inc-v-whc-inc-lactapp-2006.