STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
05-1254 consolidated with 05-1255
SMIT LAND & MARINE, INC.
VERSUS
WHC, INC.
**********
APPEAL FROM THE SIXTEENTH JUDICIAL DISTRICT COURT PARISH OF ST. MARTIN, NO. 99-61611 & NO. 99-61612 HONORABLE KEITH RAYNE JULES COMEAUX, DISTRICT JUDGE
ULYSSES GENE THIBODEAUX CHIEF JUDGE
Court composed of Ulysses Gene Thibodeaux, Chief Judge, Jimmie C. Peters, and J. David Painter, Judges.
APPEAL DISMISSED; ORDER VACATED AND CASE REMANDED.
Bernard E. Boudreaux, Jr. Murphy J. Foster, III Breazeale, Sachse & Wilson, L.L.P. One American Place - Suite 2300 P. O. Box 3197 Baton Rouge, LA 70821-3197 Telephone: (225) 387-4000 COUNSEL FOR: Defendant/Appellant - WHC, Inc.
Lloyd Noble Shields 650 Poydras Street - Suite 2400 New Orleans, LA 70130 Telephone: (504) 581-4445 COUNSEL FOR: Defendant/Appellant - WHC, Inc. David Arthur Hurlburt Hurlburt, Privat & Monrose Post Office Drawer 4407 Lafayette, LA 70501 Telephone: (337) 237-0261 COUNSEL FOR: Plaintiff/Appellee - Smit Land & Marine, Inc.
Robert Beattie McNeal 1100 Poydras Street - Suite 3600 New Orleans, LA 70163 Telephone: (504) 599-8014 COUNSEL FOR: Defendant/Appellee - Exxon Mobile Pipeline Company
L. Katherine A. Theunissen Mahtook & Lafleur P. O. Box 3089 Lafayette, LA 70502 Telephone: (337) 266-2189 COUNSEL FOR: Defendant/Appellee - National Union Fire Insurance Co.
Patricia Elise Weeks Weeks & Gonzalez 400 Magazine Street - Suite 200 New Orleans, LA 70130 Telephone: (504) 799-2888 COUNSEL FOR: Defendant/Appellee - Exxon Mobile Pipeline Company THIBODEAUX, Chief Judge.
Plaintiff-appellee, Smit Land & Marine, Inc. (“Smit”), filed a motion for
partial summary judgment regarding its claim for nonpayment of fees allegedly owed
to it under its contract with defendant-appellant, WHC, Inc. (“WHC”). The trial court
granted the motion and certified the judgment as final pursuant to La.Code Civ.P. art.
1915(B). WHC has appealed the judgment as well as the trial court’s certification of
the judgment as final. For the following reasons, the appeal is dismissed, the order
certifying the partial summary judgment as final is vacated, and the case is remanded
for trial.
I.
ISSUES
1. Did the trial court err in certifying its judgment as final and appealable pursuant to La.Code Civ.P. art. 1915(B)?
2. Did the trial court erroneously find that there is no genuine issue of material fact as to Smit’s entitlement to the unpaid fees?
II.
FACTUAL BACKGROUND
In this ongoing litigation, multiple parties are suing and/or being sued
for damages resulting from alleged acts of negligence, breach of contract, and
intentional tort, arising out of a pipeline construction job. This saga began on August
28, 1998, when Exxon Pipeline Company, now known as ExxonMobil Pipeline
Company (“Exxon”), hired general contractor, WHC, to construct approximately
forty-six miles of pipeline in an area extending from the vicinity of Anchorage,
Louisiana to the vicinity of St. James, Louisiana. This project was referred to as the
South Louisiana Pipeline Project (“the project”). On October 15, 1998, WHC hired a subcontractor, Smit, to perform directional drilling work for four pipeline crossings
for the project. One of those crossings, known as the North Mississippi River
Crossing, is the subject of this dispute.
The North Mississippi River Crossing was to be placed under the
Mississippi River near Baton Rouge, Louisiana. The subcontract required Smit to
bore one hole of a sufficient capacity to house a single bundle of pipelines, consisting
of one twenty-four-inch pipeline and two twelve-inch pipelines. The work was to be
completed within twenty-five days. The final agreed upon price for the work to be
performed by Smit on the North Mississippi River Crossing was $898,388.15.
It is undisputed that this work was not completed in the manner
described by the subcontract. Rather, Smit completed the North Mississippi River
Crossing by drilling two holes instead of one—one hole was used for the placement
of the two twelve-inch pipelines and the other was used for the placement of the one
twenty-four-inch pipeline. In addition, this crossing was completed thirty to forty
days beyond the original twenty-five-day deadline. Smit explained that these contract
variations resulted because it was unprepared for soil conditions it encountered. Smit
claimed that this was a result of its reliance on erroneous soil condition information
set forth in the geotechnical report provided by Exxon.
The contractor, WHC, also had work obligations under the subcontract.
WHC was to provide Smit with equipment and personnel during its “pullback” and
“preream” operations of the drilling. According to WHC, these operations required
more work than originally expected because of the problems encountered by Smit on
the job. Therefore, WHC was necessarily required to provide additional supporting
work to Smit beyond what was originally set forth in the subcontract. WHC
submitted a claim to Smit in the amount of $621,410.77 for these additional support
services and withheld this amount from final payment to Smit. 2 Smit, in turn, sued WHC. It also filed a separate action in the same
district court1 against Exxon and Eustis Engineering Co., Inc. (“Eustis Engineering”),
the engineering firm that prepared the allegedly faulty geotechnical report for Exxon.2
In both suits, Smit sought payment of the unpaid subcontract fee of $621,410.77, as
well as $2,013,063.24 in additional costs it claims to have incurred during completion
of the North Mississippi River Crossing. Smit sought additional damages for
wrongful conversion of funds, unjust enrichment, breach of contract, and unfair trade
practices under the Louisiana Unfair Trade Practices Act.
Smit also sought, from WHC only, penalties for its nonpayment of funds
pursuant to La.R.S. 9:2784. Smit claimed that months had passed since WHC had
received its final payment from Exxon for all work under their principal contract;
however, it asserted that WHC had failed to pay it within fourteen days of receiving
those funds, in violation of La.R.S. 9:2784. Therefore, Smit asked the court to
impose the statute’s maximum penalty of fifteen percent ($93,211.61) of the
$621,410.77 being withheld, along with attorney fees.
WHC answered the petition and filed a reconventional demand, naming
as defendants, Smit; Exxon; Eustis Engineering; and Smit’s bonding company,
National Union Fire Insurance Co. (“National Union”).3 In its answer, WHC alleged
that Smit materially breached the contract, was negligent, and had been paid all sums
that it was due. Alternatively, WHC asserted the defenses of “set-off, reduction,
abatement or apportionment” in regard to any damages that it might be ordered to pay
1 The two lawsuits were consolidated on July 19, 2002. 2 WHC’s claims against Eustis Engineering were severed from its reconventional demand and transferred to the 24th Judicial District Court after a contradictory hearing on Eustis Engineering’s Motion to Dismiss in January, 2003. 3 National Union provided the performance and labor material bonds to guarantee the performance by Smit of the work required by the subcontract.
3 as a result of Smit’s claims. WHC also asserted its claim for payment of the
$621,410.77 in costs and expenses it claimed to have incurred as a result of the
additional work it was required to perform.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
05-1254 consolidated with 05-1255
SMIT LAND & MARINE, INC.
VERSUS
WHC, INC.
**********
APPEAL FROM THE SIXTEENTH JUDICIAL DISTRICT COURT PARISH OF ST. MARTIN, NO. 99-61611 & NO. 99-61612 HONORABLE KEITH RAYNE JULES COMEAUX, DISTRICT JUDGE
ULYSSES GENE THIBODEAUX CHIEF JUDGE
Court composed of Ulysses Gene Thibodeaux, Chief Judge, Jimmie C. Peters, and J. David Painter, Judges.
APPEAL DISMISSED; ORDER VACATED AND CASE REMANDED.
Bernard E. Boudreaux, Jr. Murphy J. Foster, III Breazeale, Sachse & Wilson, L.L.P. One American Place - Suite 2300 P. O. Box 3197 Baton Rouge, LA 70821-3197 Telephone: (225) 387-4000 COUNSEL FOR: Defendant/Appellant - WHC, Inc.
Lloyd Noble Shields 650 Poydras Street - Suite 2400 New Orleans, LA 70130 Telephone: (504) 581-4445 COUNSEL FOR: Defendant/Appellant - WHC, Inc. David Arthur Hurlburt Hurlburt, Privat & Monrose Post Office Drawer 4407 Lafayette, LA 70501 Telephone: (337) 237-0261 COUNSEL FOR: Plaintiff/Appellee - Smit Land & Marine, Inc.
Robert Beattie McNeal 1100 Poydras Street - Suite 3600 New Orleans, LA 70163 Telephone: (504) 599-8014 COUNSEL FOR: Defendant/Appellee - Exxon Mobile Pipeline Company
L. Katherine A. Theunissen Mahtook & Lafleur P. O. Box 3089 Lafayette, LA 70502 Telephone: (337) 266-2189 COUNSEL FOR: Defendant/Appellee - National Union Fire Insurance Co.
Patricia Elise Weeks Weeks & Gonzalez 400 Magazine Street - Suite 200 New Orleans, LA 70130 Telephone: (504) 799-2888 COUNSEL FOR: Defendant/Appellee - Exxon Mobile Pipeline Company THIBODEAUX, Chief Judge.
Plaintiff-appellee, Smit Land & Marine, Inc. (“Smit”), filed a motion for
partial summary judgment regarding its claim for nonpayment of fees allegedly owed
to it under its contract with defendant-appellant, WHC, Inc. (“WHC”). The trial court
granted the motion and certified the judgment as final pursuant to La.Code Civ.P. art.
1915(B). WHC has appealed the judgment as well as the trial court’s certification of
the judgment as final. For the following reasons, the appeal is dismissed, the order
certifying the partial summary judgment as final is vacated, and the case is remanded
for trial.
I.
ISSUES
1. Did the trial court err in certifying its judgment as final and appealable pursuant to La.Code Civ.P. art. 1915(B)?
2. Did the trial court erroneously find that there is no genuine issue of material fact as to Smit’s entitlement to the unpaid fees?
II.
FACTUAL BACKGROUND
In this ongoing litigation, multiple parties are suing and/or being sued
for damages resulting from alleged acts of negligence, breach of contract, and
intentional tort, arising out of a pipeline construction job. This saga began on August
28, 1998, when Exxon Pipeline Company, now known as ExxonMobil Pipeline
Company (“Exxon”), hired general contractor, WHC, to construct approximately
forty-six miles of pipeline in an area extending from the vicinity of Anchorage,
Louisiana to the vicinity of St. James, Louisiana. This project was referred to as the
South Louisiana Pipeline Project (“the project”). On October 15, 1998, WHC hired a subcontractor, Smit, to perform directional drilling work for four pipeline crossings
for the project. One of those crossings, known as the North Mississippi River
Crossing, is the subject of this dispute.
The North Mississippi River Crossing was to be placed under the
Mississippi River near Baton Rouge, Louisiana. The subcontract required Smit to
bore one hole of a sufficient capacity to house a single bundle of pipelines, consisting
of one twenty-four-inch pipeline and two twelve-inch pipelines. The work was to be
completed within twenty-five days. The final agreed upon price for the work to be
performed by Smit on the North Mississippi River Crossing was $898,388.15.
It is undisputed that this work was not completed in the manner
described by the subcontract. Rather, Smit completed the North Mississippi River
Crossing by drilling two holes instead of one—one hole was used for the placement
of the two twelve-inch pipelines and the other was used for the placement of the one
twenty-four-inch pipeline. In addition, this crossing was completed thirty to forty
days beyond the original twenty-five-day deadline. Smit explained that these contract
variations resulted because it was unprepared for soil conditions it encountered. Smit
claimed that this was a result of its reliance on erroneous soil condition information
set forth in the geotechnical report provided by Exxon.
The contractor, WHC, also had work obligations under the subcontract.
WHC was to provide Smit with equipment and personnel during its “pullback” and
“preream” operations of the drilling. According to WHC, these operations required
more work than originally expected because of the problems encountered by Smit on
the job. Therefore, WHC was necessarily required to provide additional supporting
work to Smit beyond what was originally set forth in the subcontract. WHC
submitted a claim to Smit in the amount of $621,410.77 for these additional support
services and withheld this amount from final payment to Smit. 2 Smit, in turn, sued WHC. It also filed a separate action in the same
district court1 against Exxon and Eustis Engineering Co., Inc. (“Eustis Engineering”),
the engineering firm that prepared the allegedly faulty geotechnical report for Exxon.2
In both suits, Smit sought payment of the unpaid subcontract fee of $621,410.77, as
well as $2,013,063.24 in additional costs it claims to have incurred during completion
of the North Mississippi River Crossing. Smit sought additional damages for
wrongful conversion of funds, unjust enrichment, breach of contract, and unfair trade
practices under the Louisiana Unfair Trade Practices Act.
Smit also sought, from WHC only, penalties for its nonpayment of funds
pursuant to La.R.S. 9:2784. Smit claimed that months had passed since WHC had
received its final payment from Exxon for all work under their principal contract;
however, it asserted that WHC had failed to pay it within fourteen days of receiving
those funds, in violation of La.R.S. 9:2784. Therefore, Smit asked the court to
impose the statute’s maximum penalty of fifteen percent ($93,211.61) of the
$621,410.77 being withheld, along with attorney fees.
WHC answered the petition and filed a reconventional demand, naming
as defendants, Smit; Exxon; Eustis Engineering; and Smit’s bonding company,
National Union Fire Insurance Co. (“National Union”).3 In its answer, WHC alleged
that Smit materially breached the contract, was negligent, and had been paid all sums
that it was due. Alternatively, WHC asserted the defenses of “set-off, reduction,
abatement or apportionment” in regard to any damages that it might be ordered to pay
1 The two lawsuits were consolidated on July 19, 2002. 2 WHC’s claims against Eustis Engineering were severed from its reconventional demand and transferred to the 24th Judicial District Court after a contradictory hearing on Eustis Engineering’s Motion to Dismiss in January, 2003. 3 National Union provided the performance and labor material bonds to guarantee the performance by Smit of the work required by the subcontract.
3 as a result of Smit’s claims. WHC also asserted its claim for payment of the
$621,410.77 in costs and expenses it claimed to have incurred as a result of the
additional work it was required to perform.
Regarding both Exxon and Eustis Engineering, WHC claimed that they
were both negligent and liable to it for damages because they provided information
that did not accurately portray the soil conditions that would be encountered while
drilling for the pipeline crossings. WHC’s claims against Exxon also included breach
of contract claims for its failure to provide a defense to, or to indemnify it for, the
claims brought by Smit. WHC also asserted its contractual entitlement of a twenty
percent markup for all costs for which it may be ordered to pay Smit as a result of the
differing site conditions encountered by Smit on the job.
Smit filed a motion for partial summary judgment on February 4, 2004,
seeking a judgment on the issue of whether it was owed the subcontract balance of
$621,410.77 that was being withheld by WHC. In addition, it asked for summary
judgment on the issue of its entitlement to penalties and attorney fees from WHC for
late payment, pursuant to La.R.S. 9:2784.
The trial court granted Smit’s motion on the issue of its entitlement to
the unpaid balance of its subcontract in the amount of $621,410.77. The trial court
stated that no genuine issues of material fact existed that prevented a finding that
Smit was entitled to the fee. The trial court, however, declined to grant summary
judgment on the issue of the assessment of penalties under La.R.S. 9:2784. The court
wrote:
Jurisprudence provides that whether a general contractor has reasonable cause to refuse to make payment to a subcontractor on disputes [sic] amounts is a factual inquiry that has to be made by the district court. U.S. ex rel. Cal’s A/C [&] Elec. [v.] Famous Const. Corp., 220 F.3d 326, 329 (5[th] Cir. 2000). Because a factual inquiry is needed, it is precluded from summary judgment on the issue of 4 attorney’s fees and penalties. Holiday City Builders, Inc. v. Acadian Aviation Corp., 386 So.2d 1019, 1021 (La.App. 3 Cir. 1980).
Smit then moved to have the judgment certified as final and appealable
pursuant to La.Code Civ.P. art. 1915(B). WHC opposed the motion. In its Written
Reasons, the trial court stated that the judgment met the requirements for certification
and that there was no just reason for delaying the certification, reasoning that “the
unresolved issues in this case are sufficiently distinguishable from those issues
decided on the motion for partial summary judgment.”
WHC filed a suspensive appeal that challenges the certification of the
judgment as final and the trial court’s finding that there are no remaining genuine
issues of fact regarding whether Smit is entitled to the $621,410.77.
III.
LAW AND ANALYSIS
Certification of Judgment as Final Pursuant to La.Code Civ.P. art. 1915(B)
A partial summary judgment rendered pursuant to La.Code Civ.P. art.
966(E), such as the one at issue, may be immediately appealed during ongoing
litigation, but only after it has been properly designated as final by the trial court. See
Douglass v. Alton Ochsner Med. Found., 96-2825 (La. 6/13/97), 695 So.2d 953.
Accordingly, this court’s jurisdiction to decide this appeal hinges on whether that
certification was appropriate. Id.
Article 1915(B)(1) of the Code of Civil Procedure pronounces that in
order for a partial summary judgment granting relief to be designated as final for
appeal purposes, the trial court must expressly certify the judgment as final and
determine that there is no just reason for delay:
B. (1) When a court renders a partial judgment or partial summary judgment or sustains an exception in part, 5 as to one or more but less than all of the claims, demands, issues, or theories, whether in an original demand, reconventional demand, cross-claim, third party claim, or intervention, the judgment shall not constitute a final judgment unless it is designated as a final judgment by the court after an express determination that there is no just reason for delay.
A final judgment determines the merits of a controversy in whole or in part. La.Code
Civ.P. art. 1841. Therefore, even though Article 1915 dispenses with finality in the
sense of completion of the litigation, the partial judgment that is rendered should be
sufficiently final; it should dispose of the claim or dispute in regard to which the
judgment is rendered. See Van ex rel. White v. Davis, 00-206 (La.App. 1 Cir.
2/16/01), 808 So.2d 478.
The trial court’s decision to certify a partial judgment as final for appeal
purposes is to be made on a case-by-case basis, with consideration being given to the
judicial administrative interests and equities involved. Curtiss-Wright Corp. v. Gen.
Elec. Co., 446 U.S.1, 100 S.Ct. 1460 (1980); see also Banks v. State Farm Ins. Co.,
30,868 (La.App. 2 Cir. 3/5/98), 708 So.2d 523. The court may consider the following
non-exclusive list of enumerated factors when determining whether a certain partial
judgment is one that may be immediately appealable:
1) The relationship between the adjudicated and unadjudicated claims;
2) The possibility that the need for review might or might not be mooted by future developments in the trial court;
3) The possibility that the reviewing court might be obliged to consider the same issue a second time; and
4) Miscellaneous factors such as delay, economic and solvency considerations, shortening the time of trial, frivolity of competing claims, expense, and the like.
6 R.J. Messinger, Inc. v. Rosenblum, 04-1664 (La. 3/2/05), 894 So.2d 1113 at 1122
(citing Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360, 364 (3rd Cir.
1975)).
In this case, the trial court provided express, written reasons for its order
that designated the partial summary judgment as final for appeal purposes. Because
the trial court provided these explicit reasons for its determination, we are to review
the certification applying the abuse of discretion standard of review. See Messinger,
894 So.2d 1113. When applying this standard, great latitude is generally given, and
the trial court’s decision is not to be disturbed absent a finding of a clear abuse of
discretion. See Rourke v. Coursey, 338 So.2d 1197 (La.App. 3 Cir. 1976); see also
City of New Orleans v. New Orleans Canal, Inc., 173 So.2d 43 (La.App. 4 Cir. 1965).
In its Written Reasons, the trial court explained its decision to certify the
judgment as final for appeal purposes, as follows:
The court agrees with Smit that the unresolved issues in this case are sufficiently distinguishable from those issues decided on the motion for partial summary judgment. The court previously determined that WHC owed to Smit $621,410.77 for work performed and that WHC was not entitled to any type of setoff. The court finds that WHC’s unresolved issues in its reconventional demand are clearly separate issues. Further, the court agrees with Smit that if the judgment is not certified as final, WHC will have succeeded in accomplishing indirectly what it could not do directly; that is, to postpone the final judgment in hopes that it can in the future setoff an unliquidated claim against a liquidated one which this Court has already determined there is no genuine issue of material fact. Finally, WHC’s argument that it is concerned about the solvency of Smit is not a sufficient concern to defeat certification. As argued by Smit, it is also concerned about the solvency of WHC. The court does not find that this concern has any serious bearing on the merits of the certification.
We find that the trial court abused its discretion in certifying the partial judgment as
final for appeal purposes for multiple reasons: the existing relationship between the
adjudicated and remaining unadjudicated claims in this case, the possibility that 7 future case rulings may affect this judgment, and the possibility that this court may
have to consider this same issue in later appeals. See Curtiss-Wright, 446 U.S. 1.
This case contains cross-claims, as well as third-party claims of breach
of contract, negligence, and intentional tort, all of which arise out of the contracts and
work involved in the completion of the North Mississippi River Crossing. The trial
court’s certified judgment addressed only the slim issues placed before it by
Smit—whether the balance of the agreed upon subcontract price being withheld by
WHC ($621,410.77) was owed to Smit pursuant to the terms of the subcontract and
whether WHC was entitled to a “set-off” for its unadjudicated claims against Smit
under the subcontract. We disagree with the trial court’s position that its judgment
on the issue of Smit’s entitlement to the unpaid fee is sufficiently distinguishable
from the remaining claims. We find that when this case is considered as a whole, the
trial court’s finding of no genuine issue of material fact as to Smit’s entitlement to the
$621,410.77 is so interrelated to the remaining unadjudicated claims that it will
necessarily be affected by later judgments rendered in this case. For instance, it is
possible that this judgment could be rendered moot by a judgment ultimately rendered
in favor of WHC on its claim for accrued expenses in the exact amount as that which
has already been awarded to Smit. Moreover, subsequent rulings on liability for the
remaining claims of damages that have been asserted by both WHC and Smit against
Exxon and Eustis Engineering could affect the partial summary judgment that has
been rendered by the trial court in favor of Smit. As the trial court recognized in its
Written Reasons for its certification of the judgment as final, the $621,410.77 at issue
remains a disputed sum.
As was noted by the supreme court in the Messinger, 894 So.2d at 1122,
decision:
8 Historically, we have a policy against multiple appeals and piecemeal litigation. We also ensure that our courts operate under principles of sound judicial administration to promote judicial efficiency and economy. . . . Article 1915 . . . attempts to strike a balance between the undesirability of piecemeal appeals and the need for making review available at a time that best serves the needs of the parties.
Accordingly, we find that the interests of judicial administration and
justice to all of the parties involved outweigh any interest of Smit in having its
judgment certified as final so that it may execute on the judgment or immediately
exercise the option of having the judgment reviewed on appeal. See Messinger, 894
So.2d 1113. We do not find this to be one of those situations in which the claims of
the case are sufficiently unrelated such that the courts’ concerns regarding piecemeal
appeals are assuaged. See Curtiss-Wright, 446 U.S. 1. The appeal is hereby
dismissed, and the judgment certifying the appeal as final is vacated.
IV.
CONCLUSION
The judgment certifying the motion for partial summary judgment as
final pursuant to La.Code Civ.P. art. 1915(B)(1) in favor of Smit Land & Marine,
Inc., is vacated. This appeal is dismissed, and the case is remanded to the district
court for trial. Costs of this appeal are assessed to plaintiff-appellee, Smit Land &
Marine, Inc.
APPEAL DISMISSED; ORDER VACATED AND CASE
REMANDED.