SME Holdings, LLC d/b/a Sterling Manufacturing and Engineering v. The Tool Crib, Inc.

CourtDistrict Court, E.D. Michigan
DecidedAugust 30, 2021
Docket2:19-cv-12698
StatusUnknown

This text of SME Holdings, LLC d/b/a Sterling Manufacturing and Engineering v. The Tool Crib, Inc. (SME Holdings, LLC d/b/a Sterling Manufacturing and Engineering v. The Tool Crib, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SME Holdings, LLC d/b/a Sterling Manufacturing and Engineering v. The Tool Crib, Inc., (E.D. Mich. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION SME HOLDINGS, LLC d/b/a STERLING MANUFACTURING AND Case No. 19-12698 ENGINEERING, Honorable Laurie J. Michelson Mag. Judge Elizabeth A. Stafford Plaintiff,

v.

THE TOOL CRIB, INC. OF KNOXVILLE, TENNESSEE,

Defendant.

OPINION AND ORDER DENYING CROSS MOTIONS FOR SUMMARY JUDGMENT [18][19] The parties are manufacturing parts suppliers who have done business together for over thirty years. They came to this Court to resolve a disagreement about a delivery deadline. Plaintiff/Counter-Defendant SME Holdings, LLC, d/b/a Sterling Manufacturing and Engineering (“Sterling”) produces specialty gauges for automobiles. Defendant/Counter-Plaintiff The Tool Crib, Inc. of Knoxville, Tennessee1 (“Tool Crib”) is a parts distributor that pairs manufacturers with suppliers.

1 Tool Crib says that it has been incorrectly identified in court filings as “The Tool Crib, Inc.” and its correct name is “The Tool Crib, Inc. of Knoxville, Tennessee.” (ECF No. 18, PageID.146.) To fulfill a customer order for specialty auto gauges, Tool Crib ordered the gauges from Sterling. Tool Crib promised its customer that the gauges would be delivered by July 23, 2018, but then hired Sterling to supply the parts without setting

a fixed date for delivery. The parties dispute whether the date range of “17–18 weeks” in the contract was an estimate or a deadline and each side has filed a motion for summary judgment arguing they are entitled to a judgment as a matter of law. For the reasons given, the Court will deny both motions. I. Background Sterling and the Tool Crib largely agree on the factual record and the applicable law. They agree on all of the following facts except where otherwise noted.

Sterling and Tool Crib entered into a contract for three specialty auto gauges without a date certain for delivery. Following a customer inquiry for three of the gauges, Tool Crib requested quotes from Sterling to design and build them. (ECF No. 1, PageID.16–27.) Sterling provided quotes for the three gauges that stated: “Delivery: Design & Build: 17-18 Weeks A.R.O [after receipt of order].” (ECF No. 1, PageID.18, 22, 26.) Tool Crib copied this and other relevant terms into its proposal to

the customer, JTEKT. (ECF No. 18-4, PageID.349, 353, 356.) JTEKT agreed with the proposal and submitted a purchase order to Tool Crib on June 5, 2018. (ECF No. 18- 5.) JTEKT’s purchase order modified the delivery date and stated that the gauges would be delivered by July 23, 2018. (See ECF No. 18-5, PageID.360–361.) So Tool Crib contracted to provide the gauges to its customer by July 23, 2018. But Tool Crib did not insist on the same deadline in its order from Sterling. To order the gauges, Tool Crib copied Sterling’s original quotes into purchase orders and issued them to Sterling. (ECF No. 1, PageID.18, 22, 26, 29.) Tool Crib’s purchase orders expressly referenced Sterling’s three quotes and did not provide any

additional or contrary terms regarding delivery. (Id.) Tool Crib’s purchase orders stated: “Please acknowledge receipt of this purchase order by verifying pricing and delivery by email.” (ECF No. 1, PageID.29.) Sterling did so and responded by email: “Thank you for this order. Pricing is O.K. Delivery should be 17-18 weeks as quoted.” (ECF No. 19-3, PageID.482.) A document produced by Tool Crib shows that a Tool Crib employee printed this email and wrote by hand: “est. 10/13/18” which was 17-18 weeks later. [accurate?] (ECF No. 18-6, PageID.364.)

The parties disagree on the deadline for delivery this exchange created. Tool Crib argues that this exchange imposed a firm deadline 18 weeks from the date of the order, which was October 13, 2018. Sterling argues that it was an estimate only, evidenced by Sterling’s confirmation email treating it as an estimate and the handwritten note by a Tool Crib employee. The eighteen weeks passed. Beginning on October 17, 2018—four days past

the alleged deadline—and then repeatedly throughout the next several months, Sterling advised Tool Crib of supplier delays. (See ECF No. 19-3.) Tool Crib first requested a status update on October 17th. (Id. at PageID.483.) Sterling responded the same day and advised that “Delivery is approximately the middle to end of November.” (Id. at PageID.482.) On October 22nd, Sterling emailed JTEKT, copying Tool Crib, to request some additional details for the design. (Id. at PageID.485.) JTEKT responded and provided some of the requested information (without commenting on the delay). (Id. at PageID.485.) JTEKT emailed Sterling that they were “working on getting” the rest. (Id.)

On December 5th, Sterling emailed Tool Crib and advised them of continued supplier delays, estimating that “we may not see the [parts] until mid-January or later now.” (Id. at PageID.486.) Tool Crib responded: “We have got to step on the accelerator for all three of these gauges. . . . Can you assemble everything right now and then add the [delayed parts] when they are ready? Would this reduce the time any? We have got to do something . . .” (Id.) Sterling apologized again and stated: “We will proceed with whatever we can do at this time to show progress but the timing is

still as noted.” (Id.) The record indicates that Tool Crib did not respond. (See ECF No. 18-11; ECF No. 19-3.) On December 12th, Sterling sent a progress report to Tool Crib: “Nothing good or new. We offered to help [the sub-supplier] anyway possible but they declined . . . We are no further along today than we were last week because we need the [delayed parts]. I will stay on top of this the best possible.” (ECF No. 19-3, PageID.488.) Tool

Crib asked Sterling to confirm that the sub-supplier would ship the delayed parts on December 16th and inquired how long Sterling would need for assembly before Tool Crib could visit “for the runoff,” which appears to be some form of progress check or joint testing. (Id. (“We need to schedule our trip as soon as we can.”).) Any direct response is not in the record. The same day, a second person at Tool Crib emailed Sterling to ask whether the order had shipped. Sterling responded: “I just sent a progress report to Steve Summers. The revised delivery date is now 2/14/2019.” (ECF No. 19-3, PageID.48.) The record indicates that Tool Crib did not respond or otherwise protest. (ECF No. 18-12, PageID.414.)

On January 10, the customer, JTEKT, emailed both Tool Crib and Sterling and asked for a date to “runoff the gauges”: “I need to make travel arrangements now. I also need an update with pictures of the status so far.” (ECF No. 19-3, PageID.49.) Sterling responded with pictures and explained the delays. (Id.) Sterling did not offer a firm date for the runoff: “We are hoping . . . the last week of February . . . However it is to[o] early for me to say this date for sure . . .” (Id.) Sterling apologized for the delays and estimated that it would “have a better idea” for dates “in a couple of

weeks.” (Id.) A few hours later, Sterling emailed JTEKT and Tool Crib again and offered to cover all expenses for JTEKT to come test the first of the three gauges during the week of January 23. (ECF No. 19-3, PageID.495.) Sterling estimated that the other two “should be ready the week of February 25th for them to be run off.” (Id.) JTEKT canceled its order with Tool Crib three days later. (ECF No. 19-3, PageID.494.) JTEKT cited Sterling’s delays as the reason for the cancellation:

“[Sterling’s] last email said he would ‘shoot for the last week of February’ but ‘it is too early for me to say this date for sure’. Really? Your lead time was 17-18 weeks from PO. This would make due date 10/9/18 at the latest. It is now mid-January.” (Id.) Tool Crib forwarded the cancellation to Sterling and said, “Please give us some direction. They have cancelled the order with us.” (ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Quality Products and Concepts Co. v. Nagel Precision, Inc.
666 N.W.2d 251 (Michigan Supreme Court, 2003)
Hawkins v. Anheuser-Busch, Inc.
517 F.3d 321 (Sixth Circuit, 2008)
Flamm v. Scherer
198 N.W.2d 702 (Michigan Court of Appeals, 1972)
Schnepf v. Thomas L. McNamara, Inc.
93 N.W.2d 230 (Michigan Supreme Court, 1958)
Michael Scott v. First S. Nat'l Bank
936 F.3d 509 (Sixth Circuit, 2019)
The Ohio State Univ. v. Redbubble, Inc.
989 F.3d 435 (Sixth Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
SME Holdings, LLC d/b/a Sterling Manufacturing and Engineering v. The Tool Crib, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sme-holdings-llc-dba-sterling-manufacturing-and-engineering-v-the-tool-mied-2021.