Skyline Products, Incorporated v. Posen Construction, Incorporaedt

430 F. App'x 485
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 18, 2011
Docket09-1573
StatusUnpublished
Cited by1 cases

This text of 430 F. App'x 485 (Skyline Products, Incorporated v. Posen Construction, Incorporaedt) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skyline Products, Incorporated v. Posen Construction, Incorporaedt, 430 F. App'x 485 (6th Cir. 2011).

Opinion

JULIA SMITH GIBBONS, Circuit Judge.

Plaintiff-appellant Skyline Products, Inc. (“Skyline”) contends that defendant-appellee Posen Construction, Inc. (“Posen”) breached a sales contract for the purchase of electronic highway information signs by failing to facilitate Skyline’s submission of design proposals to the Michigan Department of Transportation (“MDOT”) and by precipitously terminating the contract without reasonable notice. The district court granted summary judgment to Po-sen, concluding that, by failing to obtain MDOT approval of its design proposals, Skyline did not satisfy a condition precedent contained in the purchase-order agreement, thereby voiding Posen’s duty to perform under the contract.

For the following reasons, we affirm the judgment of the district court.

I.

Posen was hired as a general contractor by MDOT for a large-scale highway construction project that included the installation of Dynamic Message Signs (“DMS”), large electronic signs whose messages can be changed remotely. Posen sought subcontractor bids for the manufacturing of DMS units, for which Skyline submitted the lowest bid.

On March 20, 2006, Posen issued an initial purchase order to Skyline for two sizes of DMS units. The purchase order contained several statements relating to MDOT requirements and approval:

SUBMIT APPROVAL DRAWINGS ASAP
THIS ORDER IS CONTINGENT UPON STATE APPROVAL OF SUBMITTAL DRAWINGS
MUST BE PER MDOT SPECIFICATIONS
It is expressly understood that all labor & materials shall be in strict accordance with the owners [sic] plans and specifications
HOLD FOR RELEASE PENDING RECEIPT OF APPROVED DRAWINGS.

*488 Skyline submitted DMS shop drawings for MDOT approval. HNTB, an outside engineering firm contracted by the MDOT to provide design and construction oversight on its behalf, reviewed the submission, and in June 2006 provided comments identifying several deficiencies in the submission regarding the small DMS signs ordered by MDOT. On July 17, 2006, Skyline provided a second small-sign submittal to MDOT.

In October 2006, however, MDOT significantly revised its DMS design specifications and rejected all prior submissions. The revised specification required that there be a one-to-one ratio of circuit boards to display modules, so that each display module within a particular sign would have its own circuit board through which the signals governing the illumination of LED pixels would be passed. Po-sen then solicited new bids on the revised specifications.

On November 2, 2006, representatives from MDOT, HNTB, Posen, and Skyline attended a progress meeting on the highway construction project in which the parties discussed the revised specifications. Posen indicated that Skyline could accommodate the new specifications, but because of initial concerns in meeting production deadlines associated with the initial specifications, Skyline had already began production of a number of large DMS signs compliant with the original specifications. According to the meeting minutes, because Skyline began construction in anticipation of approval of the original shop drawings, it acknowledged that it assumed all risk and responsibility associated with the early production. The meeting minutes further indicate that all parties anticipated that delays and cost adjustments would be forthcoming in light of the revised specifications.

After some exchanges between Posen and Skyline over pricing related to the revised DMS specifications, Posen ultimately issued Skyline a revised purchase order for DMS units with the revised specifications. The November 15, 2006, revised purchase order contained the same statements regarding MDOT specifications and approval that were contained in the initial purchase order.

Skyline reviewed the revised specifications and, based on its experience in constructing DMS signs, identified a possible improvement that could be gained through an alteration of the design specifications. According to Skyline, if the signs were built without the inclusion of additional circuit boards on the backs of each LED module but rather utilized line drivers exclusively, the signs would avoid the connection problems between the circuit boards and other components that routinely plagued DMS units. It therefore decided to propose the elimination of the additional circuit boards required under the revised design specifications.

Skyline then submitted shop drawings for approval by HNTB under the revised purchase order. The first submittal, dated December 12, 2006, identified the circuit board connection issues and proposed eliminating the additional circuit boards on the back of each LED display module. On January 18, 2007, engineers from HNTB e-mailed Skyline with questions on its suggestion to alter the display module designs. Skyline responded on January 23, 2007. In its e-mail, Skyline described several advantages that it contended were associated with the use of fewer circuit boards:

There are many fewer connections to fail with 3 line drivers vs. up to 75 display drivers per sign. Less troubleshooting is involved, so repairs take less time. Also, because there are fewer boards involved, agencies need to carry fewer spare parts in inventory.

*489 On January 29, 2007, HNTB formally rejected Skyline’s submittal based upon a failure to include a five-year warranty and for not meeting the driver board specifications for the LED module. Regarding Skyline’s proposed specification revisions, HNTB noted that “[ujpon careful consideration of this request for variance, it has been decided that it is in the Department’s best interest at this time to adhere to the specification and therefore require that each display module has [sic] a separate driver board.” On January 30, 2007, however, HNTB sent an e-mail to Skyline inquiring about the cost savings associated with the possible elimination of components inside the small DMS signs. The following day, the lead engineer from HNTB called the regional sales engineer at Skyline regarding the submittal clarification questions received on January 18. The parties discussed the design and reasoning behind the single-driver-board per-line design. According to an e-mail from Skyline recounting the conversation:

David [of HNTB] agreed with us that our design is probably better but he wasn’t sure what [sic] Michelle Mueller & MDOT would agree. We left the conversation on the table and David was going to speak with Michelle to see if we can proceed with our single driver board design or if we will be required to add driver boards to match the display boards. MDOT’s worry is if the single driver board goes down they will loose the entire line of display modules and our counter was less points of failure and easier troubleshooting and maintenance.

According to Skyline, following the conversation it was Skyline’s and HNTB’s agreement that HNTB would meet with MDOT to discuss Skyline’s proposal, and if the state rejected the new proposal, Skyline would resubmit a proposal in conformity with the revised specification.

On February 2, 2007, Posen sent Skyline a letter regarding its purchase order. The letter stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
430 F. App'x 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skyline-products-incorporated-v-posen-construction-incorporaedt-ca6-2011.