Smart v. United States Fidelity & Guaranty Co.

513 S.W.2d 291, 1974 Tex. App. LEXIS 2511
CourtCourt of Appeals of Texas
DecidedJuly 18, 1974
Docket5347
StatusPublished
Cited by6 cases

This text of 513 S.W.2d 291 (Smart v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smart v. United States Fidelity & Guaranty Co., 513 S.W.2d 291, 1974 Tex. App. LEXIS 2511 (Tex. Ct. App. 1974).

Opinion

OPINION

McDonald, Chief Justice.

This case grows out of a contract by defendant Petty to construct a veterinary hospital for plaintiff Dr. Smart.

Plaintiff Dr. Smart sued defendants Petty and USF & G alleging Petty contracted to construct plaintiff a veterinary hospital on plaintiffs’ land for $28,667; that USF & G executed performance and labor and material payment bonds for the job; that Petty breached the contract by pouring a defective foundation (and in the wrong location); that plaintiff paid Petty $5,600; that plaintiff called on Petty to correct deficiencies and called on USF & G to perform; that Petty abandoned the job, and USF & G refused to perform its obligations under the bonds; that Petty and USF & G wilfully joined with Mat-year a subcontractor of Petty in wrongfully recording a $4,000 lien against plaintiffs’ land; that a mechanics lien contract against plaintiffs’ land which had been executed by plaintiff solely to facilitate borrowing money from the Boerne Bank was *293 recorded; that plaintiff lost profits from his profession as a result of the breach of contract; that plaintiff lost a sale of the land as a result of the liens; that removal of the defective slab would cost $2,000.

Plaintiffs prayed for judgment freeing the land from any lien claim under the unrecorded building contract; cancellation of the recorded 24 February, 1970 mechanics lien; $5,600 plus interest from date of payment; $2,000 to remove the slab; damage for loss of sale; damages for lost profits; and exemplary damages.

Trial was to a jury which found:
1) Plaintiff delivered the mechanics lien dated 24 February, 1970 to the abstract company on condition it be assigned to the Boerne Bank.
3) Plaintiff allowed Petty reasonable opportunity to. construct the foundation in a good and workmanlike manner.
4) Petty failed to construct the foundation in a good and workmanlike manner.
6) Petty failed to substantially perform construction of the veterinary hospital in a good and workmanlike manner.
7) Prior to Smart’s payment of $5,600 to Petty, Petty represented to Smart the foundation had been completed in good and workmanlike manner.
8) 9) 10) Such representation was false; relied on by Smart when making the $5,600 payment; and was material inducement to Smart to make such payment.
IOA) Actions taken by House with respect to the Matyear lien prior to time this suit was filed were taken by House as agent of USF & G and Petty, and as attorney for Matyear.
IOB) Actions taken by House with respect to the mechanics lien claim by Petty after this suit was filed were taken by House as agent of USF & G and as attorney for Petty.
11) Prior to filing of the Matyear lien Matyear agreed with Petty or USF & G or both that the lien would be recorded against plaintiffs’ land for $4,000 owed by Petty to Matyear for the steel building.
12) Petty entered such agreement.
13) USF & G entered such agreement.
14) The Matyear lien was -recorded by Matyear pursuant to such agreement.
14A) Matyear in recording such lien was actuated by malice.
14B) Matyear did not record such lien in good faith to protect his rights he upon probable cause believed he had in Smart’s land.
15)Petty in entering such agreement was actuated by malice against Smart.
15A) Petty did not enter such agreement in a good faith effort to protect rights he upon probable cause believed he had against Smart.
16) USF & G in entering such agreement was actuated by malice against Smart.
16A) USF & G did not enter such agreement in a good faith effort to protect rights it upon probable cause believed it had against Smart.
17) Petty instigated the Matyear lien claim against Smart.
18) Petty instigated the Matyear lien claim for Petty’s own interest or to harass Smart.
19) USF & G instigated the Matyear lien claim against Smart.
20) USF & G instigated the Matyear lien claim for USF & G’s own profit or with intent to harass Smart.
20A) Prior to filing Petty’s amended cross action alleging indebtedness due him from plaintiff and a lien on plaintiffs’ land under the 24 Febru *294 ary, 1970 mechanics lien Petty and USF & G agreed such claim and lien would be made and Petty would refuse to release same.
20B) USF & G in entering such agreement was actuated by malice against Smart.
20C) USF & G did not enter such agreement in a good faith effort to protect rights it on probable cause believed it had against Smart.
20D) Petty’s filing such amended cross action and refusal to release the claim and lien was pursuant to such agreement.
21) Petty’s failure to release the mechanics lien was actuated by malice.
22) Petty’s failure to .release the mechanics lien was not based on a good faith effort to protect rights he upon probable cause believed he had in Smart’s land.
23) USF & G instigated Petty’s claim against Smart’s land under the mechanics lien.
24) USF & G instigated such claim for its own profit or with intent to harass Smart.
25) The recording of the Matyear lien was a proximate cause of Smarts being prevented from continuing construction of the veterinary hospital.
26) Petty’s refusal to release the mechanics lien was a proximate cause of Smarts being prevented from continuing construction of the veterinary hospital.
27) In December 1972, Albert Clay offered to purchase Smart’s tract free of liens for $10,500.
28) Clay was ready, willing, and able to pay such $10,500 to Smart for the land.
30A) The Petty mechanic lien was a proximate cause of Smarts being pre-
vented from accepting Clay’s offer to purchase for $10,500.
30) The Matyear lien was a proximate cause of Smarts being prevented from accepting Clay’s offer to purchase for $10,500.
31) The market value of the tract at present is $6,000.
32) Smart suffered a loss of profits proximately caused by noncompletion of the veterinary hospital.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kneip v. Unitedbank-Victoria
734 S.W.2d 130 (Court of Appeals of Texas, 1987)
Woodyard v. Hunt
695 S.W.2d 730 (Court of Appeals of Texas, 1985)
A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.
541 S.W.2d 856 (Court of Appeals of Texas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
513 S.W.2d 291, 1974 Tex. App. LEXIS 2511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smart-v-united-states-fidelity-guaranty-co-texapp-1974.