Sleeper Village v . NGM Ins Co. CV-09-44-PB 10/01/10 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Sleeper Village, LLC
v. Case N o . 09-cv-44-PB Opinion N o . 2010 DNH 173 NGM Insurance Company
MEMORANDUM AND ORDER
Sleeper Village, LLC commenced this action by filing a
petition for declaratory judgment to recover under a performance
bond issued by NGM Insurance Company. I determined in a prior
order that Sleeper Village failed to give NGM the notice of
surety default that it was entitled to receive under the bond.
In this order, I grant NGM’s motion for summary judgment and hold
that Sleeper Village’s failure to give the required notice bars
it from maintaining a claim under the bond.
I. INTRODUCTION
Sleeper Village contracted with Moulton Construction Inc. to
build a residential development in three phases. As the contract
required, Moulton purchased a performance bond from NGM covering
the first phase of the project. A. The Performance Bond
The bond is a standard form performance bond based on Form
A312 issued by the American Institute of Architects.
Paragraph 3 of the bond identifies various conditions that
must be satisfied before the surety is obligated under the bond.
Under paragraph 3.1, the owner must first notify the contractor
and the surety that “the Owner is considering declaring a
Contractor Default and has requested and attempted to arrange a
conference with the Contractor and the Surety.” If the
conference does not resolve the dispute, paragraph 3.2 states
that the owner must “declare[] a Contractor Default and formally
terminate[] the Contractor’s right to complete the contract.” In
addition, pursuant to paragraph 3.3, the owner must “either
agree[] to pay the Balance of the Contract Price to the Surety
. . . or to a contractor selected to perform the Construction
Contract.”
If the owner complies with its obligations under paragraph
3 , the surety must exercise one of a series of options that are
specified in paragraph 4 . Paragraph 4.1 gives the surety the
option to “[a]rrange for the Contractor, with the consent of the
Owner, to perform and complete the Construction Contract.”
Paragraph 4.2 specifies that the surety may “[u]ndertake to
-2- perform and complete the Construction Contract itself, through
its agents or through independent contractors.” Paragraph 4.3
permits the surety to satisfy its obligations under the bond by
using a bidding process to identify a new contractor acceptable
to the owner to complete the project pursuant to a new bonded
contract. Finally, under paragraph 4.4, the surety may either
deny liability and provide the owner with a statement of reasons
or pay the owner directly the amount owed under the bond.
Paragraph 5 describes the notice that must be given to the
surety before the owner can enforce its rights against the
surety. Under this paragraph, if the surety has not exercised
any of the options specified in paragraph 4 with “reasonable
promptness,” then the “Surety shall be deemed to be in default on
this Bond fifteen days after the receipt of an additional written
notice from the Owner to the Surety demanding that the Surety
perform its obligations under this Bond, and the Owner shall be
entitled to enforce any remedy available to the Owner.” The only
circumstance in which the owner is not required to notify the
surety of a default before seeking to enforce the owner’s rights
under the bond is if the surety proceeds under paragraph 4.4.1 by
either denying liability or tendering a payment that the owner
refuses to accept.
-3- B. Factual Background
During the fall of 2006 and winter of 2007, various disputes
over payment and the progression of work arose between Sleeper
Village and Moulton. As a result, on January 3 0 , 2007, pursuant
to paragraph 3.1 of the bond, Sleeper Village notified Moulton
and NGM that it was considering a declaration of “Contractor
Default” and requested a meeting to discuss its various
complaints. Sleeper Village also contacted United Construction
Company (“UCC”) to obtain an estimate of the cost to complete
Moulton’s contract.
On February 1 2 , 2007, representatives from Sleeper Village
and Moulton met and discussed several outstanding contract
issues. Unable to work out their differences, on April 9, 2007,
Sleeper Village sent Moulton and NGM a declaration of contractor
default pursuant to paragraph 3.3 of the bond. Sleeper Village
noted that it was sending the declaration in accordance with the
termination procedures identified in the bond because “the
Contract [between Sleeper Village and Moulton] requires in
Paragraph 15.02.F that the termination procedures of the
Performance Bond supercede the termination provisions of
Paragraphs 15.02.B and 15.02.C of the [construction contract].”
Sleeper Village indicated that it had identified a replacement
-4- contractor and therefore suggested that NGM waive its various
performance options and, as was authorized under paragraph 4.4.1
of the bond, simply pay Sleeper Village what it was owed.
On Friday April 1 3 , 2007, NGM responded to Sleeper Village’s
declaration of contractor default. NGM noted that it would
“proceed to investigate your declaration” but because the surety
had not “completed its investigation, [NGM] cannot agree or
disagree that section 4.4.1 is the most appropriate route.” NGM
also noted that while Sleeper Village had contacted UCC, “the
surety has not seen any bids submitted by United, or by any other
contractors for the completion of the project.”
Later that same day, an employee of Sleeper Village’s on-
site construction manager sought permission from a supervisor to
contract with UCC to complete Moulton’s contract as UCC was “on
track to start Monday.” Hours later, the employee received
permission to contract with UCC. It is unclear exactly when the
contract between UCC and Sleeper Village was formally executed
but, according to a “field diary,” UCC representatives were
working on site as of the following Tuesday, April 1 8 , 2007.
Sleeper Village never formally notified NGM that it was in
default of its obligations under the bond and UCC ultimately
completed Moulton’s contract.
-5- II. STANDARD OF REVIEW
Summary judgment is appropriate when the moving party shows
that “there is no genuine issue as to any material fact and that
the movant is entitled to judgment as a matter of law.” Fed. R.
Civ. P. 56(c)(2). For the purposes of summary judgment, an issue
is “genuine” if it may reasonably be resolved by the jury in
favor of either party. Vineberg v . Bissonnette, 548 F.3d 5 0 , 56
(1st. Cir. 2008). The substantive law underlying a claim
determines if a fact is material and “[o]nly disputes over facts
that might affect the outcome of the suit under the governing law
will properly preclude the entry of summary judgment. Factual
disputes that are irrelevant or unnecessary will not be counted.”
Anderson v . Liberty Lobby, Inc., 477 U.S. 2 4 2 , 248 (1986).
III. ANALYSIS
Because I have already determined that Sleeper Village
failed to provide NGM with the notice of surety default required
Free access — add to your briefcase to read the full text and ask questions with AI
Sleeper Village v . NGM Ins Co. CV-09-44-PB 10/01/10 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Sleeper Village, LLC
v. Case N o . 09-cv-44-PB Opinion N o . 2010 DNH 173 NGM Insurance Company
MEMORANDUM AND ORDER
Sleeper Village, LLC commenced this action by filing a
petition for declaratory judgment to recover under a performance
bond issued by NGM Insurance Company. I determined in a prior
order that Sleeper Village failed to give NGM the notice of
surety default that it was entitled to receive under the bond.
In this order, I grant NGM’s motion for summary judgment and hold
that Sleeper Village’s failure to give the required notice bars
it from maintaining a claim under the bond.
I. INTRODUCTION
Sleeper Village contracted with Moulton Construction Inc. to
build a residential development in three phases. As the contract
required, Moulton purchased a performance bond from NGM covering
the first phase of the project. A. The Performance Bond
The bond is a standard form performance bond based on Form
A312 issued by the American Institute of Architects.
Paragraph 3 of the bond identifies various conditions that
must be satisfied before the surety is obligated under the bond.
Under paragraph 3.1, the owner must first notify the contractor
and the surety that “the Owner is considering declaring a
Contractor Default and has requested and attempted to arrange a
conference with the Contractor and the Surety.” If the
conference does not resolve the dispute, paragraph 3.2 states
that the owner must “declare[] a Contractor Default and formally
terminate[] the Contractor’s right to complete the contract.” In
addition, pursuant to paragraph 3.3, the owner must “either
agree[] to pay the Balance of the Contract Price to the Surety
. . . or to a contractor selected to perform the Construction
Contract.”
If the owner complies with its obligations under paragraph
3 , the surety must exercise one of a series of options that are
specified in paragraph 4 . Paragraph 4.1 gives the surety the
option to “[a]rrange for the Contractor, with the consent of the
Owner, to perform and complete the Construction Contract.”
Paragraph 4.2 specifies that the surety may “[u]ndertake to
-2- perform and complete the Construction Contract itself, through
its agents or through independent contractors.” Paragraph 4.3
permits the surety to satisfy its obligations under the bond by
using a bidding process to identify a new contractor acceptable
to the owner to complete the project pursuant to a new bonded
contract. Finally, under paragraph 4.4, the surety may either
deny liability and provide the owner with a statement of reasons
or pay the owner directly the amount owed under the bond.
Paragraph 5 describes the notice that must be given to the
surety before the owner can enforce its rights against the
surety. Under this paragraph, if the surety has not exercised
any of the options specified in paragraph 4 with “reasonable
promptness,” then the “Surety shall be deemed to be in default on
this Bond fifteen days after the receipt of an additional written
notice from the Owner to the Surety demanding that the Surety
perform its obligations under this Bond, and the Owner shall be
entitled to enforce any remedy available to the Owner.” The only
circumstance in which the owner is not required to notify the
surety of a default before seeking to enforce the owner’s rights
under the bond is if the surety proceeds under paragraph 4.4.1 by
either denying liability or tendering a payment that the owner
refuses to accept.
-3- B. Factual Background
During the fall of 2006 and winter of 2007, various disputes
over payment and the progression of work arose between Sleeper
Village and Moulton. As a result, on January 3 0 , 2007, pursuant
to paragraph 3.1 of the bond, Sleeper Village notified Moulton
and NGM that it was considering a declaration of “Contractor
Default” and requested a meeting to discuss its various
complaints. Sleeper Village also contacted United Construction
Company (“UCC”) to obtain an estimate of the cost to complete
Moulton’s contract.
On February 1 2 , 2007, representatives from Sleeper Village
and Moulton met and discussed several outstanding contract
issues. Unable to work out their differences, on April 9, 2007,
Sleeper Village sent Moulton and NGM a declaration of contractor
default pursuant to paragraph 3.3 of the bond. Sleeper Village
noted that it was sending the declaration in accordance with the
termination procedures identified in the bond because “the
Contract [between Sleeper Village and Moulton] requires in
Paragraph 15.02.F that the termination procedures of the
Performance Bond supercede the termination provisions of
Paragraphs 15.02.B and 15.02.C of the [construction contract].”
Sleeper Village indicated that it had identified a replacement
-4- contractor and therefore suggested that NGM waive its various
performance options and, as was authorized under paragraph 4.4.1
of the bond, simply pay Sleeper Village what it was owed.
On Friday April 1 3 , 2007, NGM responded to Sleeper Village’s
declaration of contractor default. NGM noted that it would
“proceed to investigate your declaration” but because the surety
had not “completed its investigation, [NGM] cannot agree or
disagree that section 4.4.1 is the most appropriate route.” NGM
also noted that while Sleeper Village had contacted UCC, “the
surety has not seen any bids submitted by United, or by any other
contractors for the completion of the project.”
Later that same day, an employee of Sleeper Village’s on-
site construction manager sought permission from a supervisor to
contract with UCC to complete Moulton’s contract as UCC was “on
track to start Monday.” Hours later, the employee received
permission to contract with UCC. It is unclear exactly when the
contract between UCC and Sleeper Village was formally executed
but, according to a “field diary,” UCC representatives were
working on site as of the following Tuesday, April 1 8 , 2007.
Sleeper Village never formally notified NGM that it was in
default of its obligations under the bond and UCC ultimately
completed Moulton’s contract.
-5- II. STANDARD OF REVIEW
Summary judgment is appropriate when the moving party shows
that “there is no genuine issue as to any material fact and that
the movant is entitled to judgment as a matter of law.” Fed. R.
Civ. P. 56(c)(2). For the purposes of summary judgment, an issue
is “genuine” if it may reasonably be resolved by the jury in
favor of either party. Vineberg v . Bissonnette, 548 F.3d 5 0 , 56
(1st. Cir. 2008). The substantive law underlying a claim
determines if a fact is material and “[o]nly disputes over facts
that might affect the outcome of the suit under the governing law
will properly preclude the entry of summary judgment. Factual
disputes that are irrelevant or unnecessary will not be counted.”
Anderson v . Liberty Lobby, Inc., 477 U.S. 2 4 2 , 248 (1986).
III. ANALYSIS
Because I have already determined that Sleeper Village
failed to provide NGM with the notice of surety default required
by paragraph 5 , the only remaining issue is whether that failure
relieves NGM of its obligations under the bond. Sleeper Village
argues that its failure to comply with paragraph 5 is
inconsequential for two reasons. First, it asserts that various
provisions in the construction contract supersede the notice
-6- provisions of paragraph 5 . Alternatively, it argues that NGM
cannot use paragraph 5 as a shield to protect itself from
liability because it has failed to demonstrate that it was
prejudiced by Sleeper Village’s non-compliance. I address each
argument in turn.
A. The Construction Contract
Paragraph 1 of the bond states that the owner and surety
“jointly and severally, bind themselves . . . to the Owner for
the performance of the Construction Contract, which is
incorporated herein by reference.” Relying on the fact that the
construction contract and the bond must be read together, Sleeper
Village argues that paragraphs 6.19 and 13.07 of the construction
contract either expressly supersede paragraph 5 o r , at the very
least, result in ambiguity as to whether notice of surety default
must be given before Sleeper Village can invoke its rights under
the bond. I disagree.
Paragraph 6.19 of the construction contract provides in
pertinent part that the “Contractor’s obligation to perform and
complete the Work in accordance with the Contract Documents shall
be absolute.” Paragraph 13.07 (B) permits the owner to obtain
reimbursement for any costs that the owner incurs in repairing
defective work if the costs are incurred by the owner in an
-7- emergency situation or after the contractor has refused to
promptly correct the defective work in response to the owner’s
written instruction. The short response to Sleeper Village’s
attempt to rely on these provisions is that neither gives the
owner perfected rights against the surety. Regardless of any
rights that the owner has against the contractor, nothing in the
construction contract alters the procedures that the owner must
follow before it can maintain a claim against the surety.
Indeed, the construction contract expressly so provides in
paragraph 15.02.F, which states that “[i]f and to the extent that
[the] Contractor has provided a performance bond . . . the
termination procedures of that bond shall supersede the
[termination provisions set forth in the construction contract].”
Thus, an owner must still comply with paragraph 5 of the bond
before invoking its rights against the surety.
B. Failure to Prove Prejudice
Sleeper Village next argues that its failure to comply with
its obligations under paragraph 5 does not bar its claim because
NGM cannot prove that it was prejudiced by Sleeper Village’s
noncompliance. Sleeper Village bases this argument on New
Hampshire insurance law, which provides that a claim for coverage
under an occurrence-based liability insurance policy will not be
-8- defeated by late notice of a claim unless the insured can
establish that it was prejudiced by the late notice. See Dover
Mills P’ship v . Commercial Union Ins. Cos., 740 A.2d 1064, 1066-
67 (N.H. 1999). In analyzing this argument, I assume without
deciding both that the New Hampshire Supreme Court would treat a
performance bond as a contract of insurance, Concord v . Peerless
Insurance Co., 272 A.2d 5 8 8 , 590 (N.H. 1970)(applying rule
governing the interpretation of an insurance contract to the
construction of a surety bond), and that the court would require
a surety to prove prejudice resulting from the owner’s breach of
its obligations under paragraph 5 in order to relieve the surety
of its obligations under the bond. Nevertheless, I determine
that Sleeper Village’s argument is unavailing because the
evidence in the record demonstrates that NGM was prejudiced by
Sleeper Village’s noncompliance.
It is undisputed that Sleeper Village contracted with UCC to
complete the construction contract without first giving NGM the
notice of contractor default required by paragraph 5 . As a
result, NGM was deprived of its ability to exercise its rights
under paragraph 4 after receiving notice from NGM that it was in
default. When the First Circuit was asked to excuse an owner’s
failure to comply with a notice of surety default provision in
-9- similar circumstances, it determined under Massachusetts law that
“even if [the surety] must show injury, loss or prejudice [as a
result of the failure to provide notice], it meets this hurdle
given its deprivation of mitigation opportunities.” Seaboard
Sur. C o . v . Town of Greenfield, 370 F.3d 215, 220 (1st. Cir.
2004). Sleeper Villages has failed to offer a persuasive
argument as to why the New Hampshire Supreme Court would reach a
different result under New Hampshire law.1 Accordingly, I
determine that NGM has established that it was prejudiced by
Sleeper Village’s failure to provide the notice of surety default
required by paragraph 5 .
1 Sleeper Village cites Paiser v . Renaud for the proposition that the breach of a notice of surety default provision requires a showing of actual prejudice. In Paiser the New Hampshire Supreme Court found that an obligee’s failure to provide notice under the bond was not prejudicial. Paiser v . Renaud, 149 A.2d 867, 871 (N.H. 1959). However, Paiser is clearly distinguishable from the present case. In Paiser, the surety took the position that it had no responsibility under the bond. Id. Therefore, the failure of the obligee to provide notice of default would clearly not prejudice the surety because the surety had no intention of exercising any of its performance options under the bond. See id. In the present case, NGM has not asserted that it is not responsible under the bond. Therefore, Sleeper Village’s unilateral hiring of UCC and its failure to provide NGM with any notice under paragraph 5 deprived Sleeper Village of an opportunity to mitigate its exposure by exercising one of its various performance options under the bond. These actions were prejudicial to NGM’s interests as a matter of law.
-10- III. CONCLUSION
For the foregoing reasons, I grant NGM Insurance Company’s
motion for summary judgment (Doc. N o . 2 6 ) . The clerk is directed
to enter judgment and close the case.
SO ORDERED. /s/Paul Barbadoro Paul Barbadoro United States District Judge
October 1 , 2010
cc: James E . Owens, Esq. Howard B . Myers, Esq.
-11-