Sleeper Village v. NGM Ins Co.

2010 DNH 173
CourtDistrict Court, D. New Hampshire
DecidedOctober 1, 2010
DocketCV-09-44-PB
StatusPublished

This text of 2010 DNH 173 (Sleeper Village v. NGM Ins Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sleeper Village v. NGM Ins Co., 2010 DNH 173 (D.N.H. 2010).

Opinion

Sleeper Village v . NGM Ins Co. CV-09-44-PB 10/01/10 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Sleeper Village, LLC

v. Case N o . 09-cv-44-PB Opinion N o . 2010 DNH 173 NGM Insurance Company

MEMORANDUM AND ORDER

Sleeper Village, LLC commenced this action by filing a

petition for declaratory judgment to recover under a performance

bond issued by NGM Insurance Company. I determined in a prior

order that Sleeper Village failed to give NGM the notice of

surety default that it was entitled to receive under the bond.

In this order, I grant NGM’s motion for summary judgment and hold

that Sleeper Village’s failure to give the required notice bars

it from maintaining a claim under the bond.

I. INTRODUCTION

Sleeper Village contracted with Moulton Construction Inc. to

build a residential development in three phases. As the contract

required, Moulton purchased a performance bond from NGM covering

the first phase of the project. A. The Performance Bond

The bond is a standard form performance bond based on Form

A312 issued by the American Institute of Architects.

Paragraph 3 of the bond identifies various conditions that

must be satisfied before the surety is obligated under the bond.

Under paragraph 3.1, the owner must first notify the contractor

and the surety that “the Owner is considering declaring a

Contractor Default and has requested and attempted to arrange a

conference with the Contractor and the Surety.” If the

conference does not resolve the dispute, paragraph 3.2 states

that the owner must “declare[] a Contractor Default and formally

terminate[] the Contractor’s right to complete the contract.” In

addition, pursuant to paragraph 3.3, the owner must “either

agree[] to pay the Balance of the Contract Price to the Surety

. . . or to a contractor selected to perform the Construction

Contract.”

If the owner complies with its obligations under paragraph

3 , the surety must exercise one of a series of options that are

specified in paragraph 4 . Paragraph 4.1 gives the surety the

option to “[a]rrange for the Contractor, with the consent of the

Owner, to perform and complete the Construction Contract.”

Paragraph 4.2 specifies that the surety may “[u]ndertake to

-2- perform and complete the Construction Contract itself, through

its agents or through independent contractors.” Paragraph 4.3

permits the surety to satisfy its obligations under the bond by

using a bidding process to identify a new contractor acceptable

to the owner to complete the project pursuant to a new bonded

contract. Finally, under paragraph 4.4, the surety may either

deny liability and provide the owner with a statement of reasons

or pay the owner directly the amount owed under the bond.

Paragraph 5 describes the notice that must be given to the

surety before the owner can enforce its rights against the

surety. Under this paragraph, if the surety has not exercised

any of the options specified in paragraph 4 with “reasonable

promptness,” then the “Surety shall be deemed to be in default on

this Bond fifteen days after the receipt of an additional written

notice from the Owner to the Surety demanding that the Surety

perform its obligations under this Bond, and the Owner shall be

entitled to enforce any remedy available to the Owner.” The only

circumstance in which the owner is not required to notify the

surety of a default before seeking to enforce the owner’s rights

under the bond is if the surety proceeds under paragraph 4.4.1 by

either denying liability or tendering a payment that the owner

refuses to accept.

-3- B. Factual Background

During the fall of 2006 and winter of 2007, various disputes

over payment and the progression of work arose between Sleeper

Village and Moulton. As a result, on January 3 0 , 2007, pursuant

to paragraph 3.1 of the bond, Sleeper Village notified Moulton

and NGM that it was considering a declaration of “Contractor

Default” and requested a meeting to discuss its various

complaints. Sleeper Village also contacted United Construction

Company (“UCC”) to obtain an estimate of the cost to complete

Moulton’s contract.

On February 1 2 , 2007, representatives from Sleeper Village

and Moulton met and discussed several outstanding contract

issues. Unable to work out their differences, on April 9, 2007,

Sleeper Village sent Moulton and NGM a declaration of contractor

default pursuant to paragraph 3.3 of the bond. Sleeper Village

noted that it was sending the declaration in accordance with the

termination procedures identified in the bond because “the

Contract [between Sleeper Village and Moulton] requires in

Paragraph 15.02.F that the termination procedures of the

Performance Bond supercede the termination provisions of

Paragraphs 15.02.B and 15.02.C of the [construction contract].”

Sleeper Village indicated that it had identified a replacement

-4- contractor and therefore suggested that NGM waive its various

performance options and, as was authorized under paragraph 4.4.1

of the bond, simply pay Sleeper Village what it was owed.

On Friday April 1 3 , 2007, NGM responded to Sleeper Village’s

declaration of contractor default. NGM noted that it would

“proceed to investigate your declaration” but because the surety

had not “completed its investigation, [NGM] cannot agree or

disagree that section 4.4.1 is the most appropriate route.” NGM

also noted that while Sleeper Village had contacted UCC, “the

surety has not seen any bids submitted by United, or by any other

contractors for the completion of the project.”

Later that same day, an employee of Sleeper Village’s on-

site construction manager sought permission from a supervisor to

contract with UCC to complete Moulton’s contract as UCC was “on

track to start Monday.” Hours later, the employee received

permission to contract with UCC. It is unclear exactly when the

contract between UCC and Sleeper Village was formally executed

but, according to a “field diary,” UCC representatives were

working on site as of the following Tuesday, April 1 8 , 2007.

Sleeper Village never formally notified NGM that it was in

default of its obligations under the bond and UCC ultimately

completed Moulton’s contract.

-5- II. STANDARD OF REVIEW

Summary judgment is appropriate when the moving party shows

that “there is no genuine issue as to any material fact and that

the movant is entitled to judgment as a matter of law.” Fed. R.

Civ. P. 56(c)(2). For the purposes of summary judgment, an issue

is “genuine” if it may reasonably be resolved by the jury in

favor of either party. Vineberg v . Bissonnette, 548 F.3d 5 0 , 56

(1st. Cir. 2008). The substantive law underlying a claim

determines if a fact is material and “[o]nly disputes over facts

that might affect the outcome of the suit under the governing law

will properly preclude the entry of summary judgment. Factual

disputes that are irrelevant or unnecessary will not be counted.”

Anderson v . Liberty Lobby, Inc., 477 U.S. 2 4 2 , 248 (1986).

III. ANALYSIS

Because I have already determined that Sleeper Village

failed to provide NGM with the notice of surety default required

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ford
548 F.3d 1 (First Circuit, 2008)
Paisner v. Renaud
149 A.2d 867 (Supreme Court of New Hampshire, 1959)
Dover Mills Partnership v. Commercial Union Insurance
740 A.2d 1064 (Supreme Court of New Hampshire, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2010 DNH 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sleeper-village-v-ngm-ins-co-nhd-2010.