Sleeper Village v. NGM Ins Co.
Opinion
Sleeper Village v . NGM Ins Co. CV-09-44-PB 10/01/10 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Sleeper Village, LLC
v. Case N o . 09-cv-44-PB Opinion N o . 2010 DNH 173 NGM Insurance Company
MEMORANDUM AND ORDER
Sleeper Village, LLC commenced this action by filing a petition for declaratory judgment to recover under a performance bond issued by NGM Insurance Company. I determined in a prior order that Sleeper Village failed to give NGM the notice of surety default that it was entitled to receive under the bond. In this order, I grant NGM’s motion for summary judgment and hold that Sleeper Village’s failure to give the required notice bars it from maintaining a claim under the bond.
I. INTRODUCTION
Sleeper Village contracted with Moulton Construction Inc. to build a residential development in three phases. As the contract required, Moulton purchased a performance bond from NGM covering the first phase of the project.
A. The Performance Bond The bond is a standard form performance bond based on Form A312 issued by the American Institute of Architects.
Paragraph 3 of the bond identifies various conditions that must be satisfied before the surety is obligated under the bond. Under paragraph 3.1, the owner must first notify the contractor and the surety that “the Owner is considering declaring a Contractor Default and has requested and attempted to arrange a conference with the Contractor and the Surety.” If the conference does not resolve the dispute, paragraph 3.2 states that the owner must “declare[] a Contractor Default and formally terminate[] the Contractor’s right to complete the contract.” In addition, pursuant to paragraph 3.3, the owner must “either agree[] to pay the Balance of the Contract Price to the Surety . . . or to a contractor selected to perform the Construction Contract.”
If the owner complies with its obligations under paragraph 3 , the surety must exercise one of a series of options that are specified in paragraph 4 . Paragraph 4.1 gives the surety the option to “[a]rrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract.” Paragraph 4.2 specifies that the surety may “[u]ndertake to
perform and complete the Construction Contract itself, through its agents or through independent contractors.” Paragraph 4.3 permits the surety to satisfy its obligations under the bond by using a bidding process to identify a new contractor acceptable to the owner to complete the project pursuant to a new bonded contract. Finally, under paragraph 4.4, the surety may either deny liability and provide the owner with a statement of reasons or pay the owner directly the amount owed under the bond.
Paragraph 5 describes the notice that must be given to the surety before the owner can enforce its rights against the surety. Under this paragraph, if the surety has not exercised any of the options specified in paragraph 4 with “reasonable promptness,” then the “Surety shall be deemed to be in default on this Bond fifteen days after the receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner.” The only circumstance in which the owner is not required to notify the surety of a default before seeking to enforce the owner’s rights under the bond is if the surety proceeds under paragraph 4.4.1 by either denying liability or tendering a payment that the owner refuses to accept.
B. Factual Background During the fall of 2006 and winter of 2007, various disputes over payment and the progression of work arose between Sleeper Village and Moulton. As a result, on January 3 0 , 2007, pursuant to paragraph 3.1 of the bond, Sleeper Village notified Moulton and NGM that it was considering a declaration of “Contractor Default” and requested a meeting to discuss its various complaints. Sleeper Village also contacted United Construction Company (“UCC”) to obtain an estimate of the cost to complete Moulton’s contract.
On February 1 2 , 2007, representatives from Sleeper Village and Moulton met and discussed several outstanding contract issues. Unable to work out their differences, on April 9, 2007, Sleeper Village sent Moulton and NGM a declaration of contractor default pursuant to paragraph 3.3 of the bond. Sleeper Village noted that it was sending the declaration in accordance with the termination procedures identified in the bond because “the Contract [between Sleeper Village and Moulton] requires in Paragraph 15.02.F that the termination procedures of the Performance Bond supercede the termination provisions of Paragraphs 15.02.B and 15.02.C of the [construction contract].” Sleeper Village indicated that it had identified a replacement
contractor and therefore suggested that NGM waive its various performance options and, as was authorized under paragraph 4.4.1 of the bond, simply pay Sleeper Village what it was owed.
On Friday April 1 3 , 2007, NGM responded to Sleeper Village’s declaration of contractor default. NGM noted that it would “proceed to investigate your declaration” but because the surety had not “completed its investigation, [NGM] cannot agree or disagree that section 4.4.1 is the most appropriate route.” NGM also noted that while Sleeper Village had contacted UCC, “the surety has not seen any bids submitted by United, or by any other contractors for the completion of the project.”
Later that same day, an employee of Sleeper Village’s on-
site construction manager sought permission from a supervisor to contract with UCC to complete Moulton’s contract as UCC was “on track to start Monday.” Hours later, the employee received permission to contract with UCC. It is unclear exactly when the contract between UCC and Sleeper Village was formally executed but, according to a “field diary,” UCC representatives were working on site as of the following Tuesday, April 1 8 , 2007. Sleeper Village never formally notified NGM that it was in default of its obligations under the bond and UCC ultimately completed Moulton’s contract.
II. STANDARD OF REVIEW Summary judgment is appropriate when the moving party shows that “there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c)(2). For the purposes of summary judgment, an issue is “genuine” if it may reasonably be resolved by the jury in favor of either party. Vineberg v . Bissonnette, 548 F.3d 5 0 , 56 (1st. Cir. 2008). The substantive law underlying a claim determines if a fact is material and “[o]nly disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment. Factual disputes that are irrelevant or unnecessary will not be counted.” Anderson v . Liberty Lobby, Inc., 477 U.S. 2 4 2 , 248 (1986).
III. ANALYSIS
Free access — add to your briefcase to read the full text and ask questions with AI
2010 DNH 173 (Sleeper Village v. NGM Ins Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.