Slattery Contracting Co. v. State

56 Misc. 2d 111, 288 N.Y.S.2d 126, 1968 N.Y. Misc. LEXIS 1830
CourtNew York Court of Claims
DecidedJanuary 12, 1968
DocketClaim No. 45279
StatusPublished

This text of 56 Misc. 2d 111 (Slattery Contracting Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slattery Contracting Co. v. State, 56 Misc. 2d 111, 288 N.Y.S.2d 126, 1968 N.Y. Misc. LEXIS 1830 (N.Y. Super. Ct. 1968).

Opinion

Alexander Del Giorno, J.

This is a claim for $2,019,296.63, based upon alleged damages caused to the claimant by the State’s breaches of a construction contract, errors in the plans, interferences by the State, delays caused by the State during the performance of the contract, and also for work done for which the State refused to pay.

This contract involved the construction of a depressed six-lane concrete highway, divided by a center mall, four bridges and various retaining walls, access roads, exit ramps, grading, etc. The contract was for the construction of a portion of the Cross-Bronx Expressway, about one-half mile in length, between Walton and University Avenues.

The contract was bid on October 20, 1960, executed November 10, 1960, and was awarded November 21, 1960, at which time the claimant was directed to and did proceed with the contract work. The contract was to be completed by September 1, 1962. The contract was substantially completed by September, 1963, and accepted by the State March 10,1964.

[113]*113The State forwarded its completed final estimate on January 28, 1965, and the claim, which has not been assigned, was filed June 2,1965.

This was a difficult contract, requiring cutting of rock from some 20 feet to 90 feet in the subsurface, said rock being an element commonly found in the Borough of The Bronx, shoring up and reconstruction of the Jerome Avenue Bridge above which also passes the subway elevated, the erection of three more bridges at Macombs Bead, Jessup and Nelson Avenues, the realigning of large water and sewer mains, detour of traffic, closing of certain avenues, refacing the exposed rock in places, and shoring rock in other places with retaining walls. Certain adjacent buildings were to be underpinned while others were to be demolished.

The claimant’s bid was for $6,800,000, which is an indication of the intricate and difficult nature of the job. With supplemental work the contract totalled $9,430,056.19.

At the trial the claimant presented a scale drawing of the job site prepared from the plans. Coloring is used in the drawing to demonstrate effectively the site, the various elements of the contract and their location, as well as the areas which affected claimant’s work when redesigned, delayed or interfered with by the State. The aforesaid drawing depicts in yellow the proposed roadway; in deep red the redesigns and redesigns of redesigns made during the course of construction; and, in a lighter shade of red, or pink, the portions of the job allegedly affected by the aforesaid redesigns upon which work could not proceed or had to be performed piecemeal while the redesigns were being approved. Black hatching represents major areas of interference and consequent work stoppage while claimant awaited the redesigns. Green represents work done according to original designs.

In almost any job, but particularly in a job such as this, a certain amount of redesigning must be expected whether or not specified in the contract, and there is no doubt in the mind of the court that this was within the contemplation of this contract and, of necessity, was considered in the bidding for the contract.

A normal amount of contract designs would have to be redesigned to conform the work to be done to the actual conditions disclosed by the excavation. Experience would compel acceptance by the contractor of a fair quantity of redesigns even if not mentioned in the contract, since a large portion thereof was blind ” work and the true nature of the subsurface conditions could not be determined in advance whether there were borings or not.

[114]*114However, we find here over 70 major redesigns which, when a redesign of the redesign is considered, would present a total of some 85 major redesigns of this job and, from a study of the redesigns as presented on the said map, there is an indication that about 70% to 80% of the entire job was redesigned.

The court doubts that anyone would seriously assert that such complete overhauling of the original contract was within the contemplation of the parties at the time of the execution of the contract. This court certainly does not say so. The court concludes that this state of affairs is a clear indication that sufficient and necessary study of the area and its surroundings was not made by the State prior to the design of the job. The court cannot escape the conclusion that this was either a hurry-up job, an indifferently planned job, or an ineptly conceived job, designed upon inept or insufficient or indifferent study of the terrain, the buildings and other surrounding elements affected thereby. The court concludes that this state of affairs is equivalent to negligence on the part of the State.

As stated heretofore, some of the redesign was to be expected. However, when a redesign was made necessary, it was the duty of the State to modify, to redesign or to redesign the redesigns as quickly as possible, so that the contractor would not be held back in his work, his equipment and men would not remain idle, and the contractor would not be forced to perform contract work hither and yonder, in a hop-skip, hit-and-miss fashion.

We shall discuss in a general manner the issues herein involved. Firstly, it is well to note that the subject contract was to be completed in two years. It was intended to be joined with two other contracts performed by other contractors located immediately east and west of the subject contract. Then these three contracts were only a part of other contract work which, when taken together, were to result in this great highway, the opening of which was eagerly awaited by the State, the city and the people. Time was basically of the essence in all these contracts. Time was of the essence for the State as well as the contractor.

As far as the present contract is concerned, we find that with few exceptions time meant little to the State designers and cooperation was not easily discerned in the necessary decisions required for the redesigns. To be sure, this state of affairs created heat but shed little light. Complaints were made, letters were written, inspections were made, conferences were held, orders and counter-orders were given, redesigns were furnished which were defective (as in Wall C-4), but in almost all cases designs were furnished long after they should have been fur[115]*115uished. It did not seem necessary to the State to be concerned as to the unnecessary expenses to which this procrastination was putting the claimant, in both men and equipment. This court has presided over many contract cases, but none equalled the indifference to the interests of the claimant, or the State itself, that was disclosed by the testimony herein.

The so-called normal designs became extraordinary by virtue of bureaucratic indolence. At the trial the State’s attorney was presented with this state of affairs, on which he ably tried to defend the State. The State during the trial had recourse time and again to the provisions of the contract to justify the State’s position. Among other contentions, the State insisted that the Department of Public Works has the contractual privilege to devote a minimum of five days to review a design. The testimony herein indicates that months were spent in revising and reviewing some designs. In the factual situation confronting us, we have concluded that, were we to apply only the minimum time suggested, we would discover that the State would have spent at least three and one-half years in a two-year contract, merely to study designs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arc Engineering Corporation v. State
59 N.E.2d 180 (New York Court of Appeals, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
56 Misc. 2d 111, 288 N.Y.S.2d 126, 1968 N.Y. Misc. LEXIS 1830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slattery-contracting-co-v-state-nyclaimsct-1968.