Slater v. Altman Co.

2013 Ohio 4405
Ohio Court of Appeals·Decided September 30, 2013·No. 2013-CA-4·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT CHAMPAIGN COUNTY

MARSHALL SLATER, dba : SLATER WELDING & ERECTORS :

: Appellate Case No. 2013-CA-4 Plaintiff-Appellee :

: Trial Court Case No. 2007-CV-215 v. :

:

THE ALTMAN COMPANY, et al. :

: (Civil Appeal from

Defendant-Appellant : (Common Pleas Court)

:

...........

OPINION

Rendered on the 30th day of September, 2013.

...........

AARON FALVO, Atty. Reg. #0076301, Blumenstiel, Evans & Falvo, LLC, 261 West Johnstown Road, Columbus, Ohio 43230 Attorney for Plaintiff-Appellee

STEVEN D. ROWE, Atty. Reg. #0020475, and ERICA A. PROBST, Atty. Reg. #0073486, Kemp, Schaeffer & Rowe Co., LPA, 88 West Mound Street, Columbus, Ohio 43230 Attorney for Defendant-Appellant

.............

HALL, J.,

{¶ 1} The Altman Company appeals from the trial court’s entry of judgment in favor of appellee Marshall Slater for $132,690 following a bench trial in this breach-of-contract action.

{¶ 2} In two related assignments of error, the Altman Company (“Altman”) challenges the legal sufficiency and manifest weight of the evidence to support the trial court’s judgment.

{¶ 3} The record reflects that Altman served as one of five prime contractors on a project to build a school for the Mechanicsburg School District. Altman worked under a construction manager, Smoot Construction Company, which managed the entire project for the school district. Altman’s contract provided for it to be the general-trades contractor. To perform its responsibilities, Altman hired a number of subcontractors. One of them was Marshall Slater, the sole proprietor of Slater Welding & Erectors. After some negotiation, Slater and Altman entered into a subcontract requiring Slater to perform steel erection on the project for $274,000.

{¶ 4} Slater and his crew began their work around February 2006. That spring, a dispute arose regarding Slater’s installation of a “shelf angle” or “relief angle.”1 Altman claimed installation of the angle was part of Slater’s contract. Slater disagreed, asserting that the contract he negotiated with Altman did not require him to install the angle. Ultimately, he refused to perform the work. Altman responded by advising Slater that it would hire someone else to install the angle and deduct the cost from his compensation.

{¶ 5} Around the same time, a second problem arose. Slater fell behind schedule in erecting the steel. He attributed his delay to two things: late steel deliveries from the steel supplier, Cape Coral Steel, and Cape Coral’s frequent delivery of steel out of sequence, which required Slater to move his equipment and crew to different parts of the building—a process that could take half a day. For its part, Altman did not dispute that late steel deliveries occurred or that Cape Coral supplied steel out of sequence. It presented testimony, however, that Slater’s

1

In construction, a “shelf angle” or “relief angle” is an L-shaped support attached laterally at various levels to the exterior of the structural framing to support the exterior veneer, typically brick or stone, so that the veneer is non-loadbearing.

delay in erecting the steel was attributable largely to having an undersized and inexperienced crew.

{¶ 6} Regardless of the cause of Slater’s delay in erecting the steel, a meeting occurred in May 2006 to discuss the problem. During the meeting, the parties discussed hiring an additional crew to assist Slater. Altman presented testimony that Slater agreed to the proposal and agreed that payment for the additional crew would be deducted from his compensation. Slater denied reaching such an agreement. He admitted that Altman proposed hiring another crew to assist him. He claimed, however, that he requested additional information from Altman about the cost and that he never received an answer. In any event, Altman promptly hired another company, Watertown Steel, to assist in the steel erection.

{¶ 7} Slater later submitted a periodic pay application to Altman requesting more than $70,000 for work performed. Altman responded with a letter advising him that he would receive approximately $10,000 after deductions for payment to Watertown Steel and for the cost of having the relief angle installed. As a result of the on-going dispute, Slater and his crew failed to appear at the job site on June 26, 2006. After negotiations with Slater failed, Altman gave him written notice that it would hire additional workers to complete his work and that the cost would be deducted from his compensation under the subcontract. Altman proceeded as it indicated and completed the steel erection at a claimed cost of $371,766.45.

{¶ 8} In September 2006, Slater filed a lien against the public funds held by Mechanicsburg in the amount of $132,690. Slater filed the present action in July 2007, alleging breach of contract and seeking foreclosure on the lien. Altman filed a counterclaim, seeking damages for the extra costs it incurred to complete the steel erection. Altman also filed a third-party complaint against Cape Coral, seeking damages for the late and out-of-sequence delivery of steel. Cape Coral subsequently filed for bankruptcy and was dismissed as a party.

{¶ 9} A lengthy bench trial in the above-captioned matter was completed in October 2009. More than three years later, the trial court filed a written decision and entered judgment in favor of Slater. In support, the trial court reasoned:

The Court finds that Defendant The Altman Company (Defendant)

materially breached the parties’ contract through its failure to pay Plaintiff pursuant to the terms of the contract, and that Plaintiff was damaged in the amount of $132,690.00 plus interest.

The Court finds that Defendant did not receive Plaintiff’s consent in the manner prescribed by their contract to reduce Plaintiff’s payment rights in order to pay for the additional steel installer, Watertown Steel, and that Defendant made improper deductions from or reductions to Plaintiff’s payments.

The Court finds that the delays in metal installation were due to the problems with timely and orderly delivery of materials from the steel supplier.

The Court finds that these supplier problems were not Plaintiff’s fault.

The Court finds that Plaintiff performed Plaintiff’s contractual obligations under the contract at least until Defendant’s material breach in payment.

The Court finds that the parties’ contract did not require Plaintiff to install the brick relief angles.

The [C]ourt finds Plaintiff’s witnesses to be more credible than those of Defendant.

Judgment in favor of Plaintiff is hereby granted for $132,690.00.

It is therefore ordered that the amount of $132,690.00 plus interest be released from the public fund to Plaintiff.

Defendant The Altman Company’s claims against Plaintiff are dismissed.

(Doc. #120 at 1-2).

{¶ 10} In its two assignments of error, which are briefed together, Altman challenges the trial court’s finding that Slater was not obligated to install relief angles. Altman also disputes the trial court’s finding that it breached the parties’ contract by failing to pay Slater. Altman insists that Slater breached the contract by falling behind on the project, agreeing to pay for an additional steel-erection crew, and then abandoning the job. Altman raises its arguments in the context of a sufficiency-of-the-evidence and manifest-weight-of-the-evidence challenge to the trial court’s judgment.

{¶ 11} “Sufficiency” is the standard used to determine whether the evidence is adequate to submit a case to the trier of fact. The test for legal sufficiency is “whether any evidence exists on every element of each claim or defense for which the party has the burden to go forward.” Eastley v. Volkman, 132 Ohio St.3d 328, 2012-Ohio-2179, 972 N.E.2d 517, 526, ¶25. A manifest-weight-of-the evidence challenge is “qualitatively and quantitatively different[.]” Id. at

Free access — add to your briefcase to read the full text and ask questions with AI

Slater v. Altman Co., 2013 Ohio 4405 (Ohio Ct. App. 2013).

2013 Ohio 4405 (Slater v. Altman Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Century Natl. Bank v. Hines
2014 Ohio 3901 (Ohio Court of Appeals, 2014)