Skagit Railway & Lumber Co. v. Cole

25 P. 1077, 2 Wash. 57, 1891 Wash. LEXIS 9
CourtWashington Supreme Court
DecidedFebruary 10, 1891
DocketNo. 55
StatusPublished
Cited by76 cases

This text of 25 P. 1077 (Skagit Railway & Lumber Co. v. Cole) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skagit Railway & Lumber Co. v. Cole, 25 P. 1077, 2 Wash. 57, 1891 Wash. LEXIS 9 (Wash. 1891).

Opinions

The opinion of the court was delivered by

Scott, J.

— This action was brought in the district court of the third judicial district of Washington Territory, holding terms at Mt. Vernon, by the appellee against the appellant, to recover damages in the sum of $7,575 for an alleged breach of a contract entered into between the appellant and appellee, by which the appellant let to the appellee, for certain terms of years mentioned in said contract, certain lands therein described, and, in consideration of the sum of $1.50 per thousand feet stumpage, sold and gave him license to cut saw-logs, piles and spars upon said lands during said time; and further agreed to furnish to said appellee, at the reasonable market price, all the provisions and logging supplies needed by him during the continuance of said contract. The appellee claimed that he entered upon the performance of his part of the contract, and employed a large number of men, purchased a large number of teams, and invested a large amount of money in camp equipage, tools, etc., and in every respect fulfilled all the conditions of the contract on his part; but that during the months of July and August and the first part of September, 1888, the appellant refused to furnish him logging supplies and provisions, as provided in the contract, and that in consequence of such failure the appellee made thirteen [61]*61trips from his logging camp to the place of business of the appellant, at an expense of $195, for the purpose of procuring such supplies, but in consequence of the appellant’s failure to furnish them, these trips were made useless j and claimed further that during this period, in consequence of appellant’s failure to furnish such supplies, the business of the appellee was interrupted, and his teams compelled to remain idle, to his damage in the sum of $450. The appellee claimed further that the appellant failed and refused to supply him with provisions and logging appliances, as provided in said contract from the 12th day of September, 1888, for a period of six weeks continuously, and that in consequence of such failure the appellee was unable to carry on his business, and was compelled to shut down his camp and suspend his business for a period of six weeks, causing him loss and damage to the amount of $2,000. He claimed further that on the 5th day of June, 1889, at the most advantageous time for logging, the appellant again refused to supply him with provisions and logging appliances as provided in the contract, and notified him it would no longer comply with the terms of its contract, and has ever since failed and refused to do so, and in consequence oí such failure the men employed by the appellee abandoned their labors in the camp, and the appellee was unable to procure supplies or subsistence, or to maintain or operate his business to the extent of his ability, and, in place of 45,000 feet of saw-logs per day, which he had been putting into the market, was only able to put in 20,000 feet per day, causing him damage to the extent of $3,000. The appellant joined issue with the appellee upon all the material allegations of the complaint except that of the making of the contract, and the allegation that in the month of June, T889, it refused to furnish the appellee with supplies and so notified him. The appellant then pleaded in justification of its refusal to furnish supplies to [62]*62the appellee in June, 1889, two affirmative defenses, setting up in the first defense breach of the contract by the appellee, and in the second defense breach of a subsequent contract entered into between them for the securing of certain acceptances to be made by the appellant of certain orders by the appellee. The appellee joined issues with the appellant upon these defenses. The case was called for trial at Mt. Vernon on December 9, 1889, in the superior court of Skagit county, which had convened December 2d. The trial occupied several days, and resulted in a verdict and judgment in favor of appellee for the sum of $3,067.50.

The first ground of error claimed by appellant is, that the superior court abused its discretion in refusing to grant a continuance of the cause. Appellant’s motion for a continuance was made December 10th, while the trial was in progress, and was based upon the ground that one of its attorneys, Mr. Haller, was not present. Affidavits were filed in support of the motion showing that appellant had made every exertion to have Mr. Haller present; that a few days prior to the convening of said court he had left upon a hunting trip in company with two other gentlemen, none of whom had been definitely heard from for several days, but that it was rumored he, with the others, had been drowned, and the gravest apprehensions were entertained that said rumors were true; that Mr. Haller was the principal attorney for appellant in said matter, and the one upon whom it relied to conduct its defense. (It was subsequently learned that Mr. Haller had, in fact, lost his life as reported.) Counter-affidavits were filed by appellee to the effect that Mr. Haller had said that he would not participate in the trial in consequence of a claim made by appellee that he had counseled with him previous to the commencement of said action as to the matters then in controversy therein; also that on said December 2d ap[63]*63pellee notified Mr. Burke, of the firm of Burke & Haller, that said court was in session and that he intended to have said cause called for trial. The first attorneys who appeared for appellant in the action were Cushing & Dunning, who filed a demurrer to the complaint September 20, 1889. Mr. Cushing was appellant’s secretary. On November 23d following, Cushing & Dunning and Burke & Haller filed an answer in the ease for appellant, a reply was filed by appellee, and the cause was at issue before the court convened. On December 5th appellant employed Hon. C. H. Hanford, Rochester, Lewis & Gilman and E. C. Million as attorneys for it in said action, and on December 6th C. E. Patterson was also employed as one of its attorneys therein. It appears that the case was called several times during the first week of the session, and was passed at appellant’s request, the last time on December 6th, upon a motion by appellant for a continuance to the first of the following week, which motion was granted, with the understanding that it would be the first civil cause called for trial. No exception was taken to this, appellant then expecting to have Mr. Haller present before said time had expired. It appears that appellant acted in entire good faith in the premises and made great exertions to learn 'where Mr, Haller was, aud also insisted upon its right to have him heard if possible as to the matters stated in appellee’s affidavits relating to his intended participation in the trial. Upon Monday of the following week (December 9th) the case was called and the parties proceeded to trial. No objection was made thereto by appellant, nor did it then apply for a further continuance. It now contends that it was understood when the trial was commenced that it would take several days within which to complete it, and that appellant expected Mr, Haller would arrive before any material progress had been made therein up to [64]*64December 10th, when the rumors of his drowning became rife, and its said motion for a continuance was made.

The second ground of error alleged is in regard to the refusal of the court to permit the appellant to amend its answer, except in one instance on the condition that it pay the costs accrued, and in the other refusing it entirely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re The Dependency Of: A.d.r. Reina Rife v. Dshs
Court of Appeals of Washington, 2017
State Of Washington v. Siraj Hassan Hajisomo
Court of Appeals of Washington, 2016
State v. Downing
87 P.3d 1169 (Washington Supreme Court, 2004)
Rathke v. Roberts
207 P.2d 716 (Washington Supreme Court, 1949)
Larson v. Union Investment & Loan Co.
10 P.2d 557 (Washington Supreme Court, 1932)
Beeson Brothers v. Chambers
285 P. 433 (Washington Supreme Court, 1930)
Brinnon Logging Co. v. Carlsborg Mill & Timber Co.
210 P. 945 (Washington Supreme Court, 1922)
Minneapolis Threshing MacHine Co. v. Bradford
227 S.W. 628 (Missouri Court of Appeals, 1921)
Boston Trust Co. v. Evelon Co.
164 P. 606 (Washington Supreme Court, 1917)
MacKey v. Boswell
1916 OK 1054 (Supreme Court of Oklahoma, 1916)
Schultz v. Stack-Gibbs Lumber Co.
229 F. 920 (Ninth Circuit, 1916)
Webster v. Beau
137 P. 1013 (Washington Supreme Court, 1914)
Bogart v. Pitchless Lumber Co.
130 P. 490 (Washington Supreme Court, 1913)
Federal Iron & Brass Bed Co. v. Hock
85 P. 418 (Washington Supreme Court, 1906)
Puget Sound Iron & Steel Works v. Clemmons
72 P. 465 (Washington Supreme Court, 1903)
Chesapeake & Ohio Railway Co. v. Rison
37 S.E. 320 (Supreme Court of Virginia, 1900)
Graham v. McCoy
48 P. 780 (Washington Supreme Court, 1897)
Goldhammer v. Dyer
7 Colo. App. 29 (Colorado Court of Appeals, 1895)
Moorman v. Seattle & Montana Railway Co.
35 P. 596 (Washington Supreme Court, 1894)
Sears v. Seattle Consolidated Street Railway Co.
33 P. 389 (Washington Supreme Court, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
25 P. 1077, 2 Wash. 57, 1891 Wash. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skagit-railway-lumber-co-v-cole-wash-1891.