SJH 11 v. Dowbuilt

CourtCourt of Appeals for the Tenth Circuit
DecidedMay 29, 2026
Docket25-8037
StatusUnpublished

This text of SJH 11 v. Dowbuilt (SJH 11 v. Dowbuilt) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SJH 11 v. Dowbuilt, (10th Cir. 2026).

Opinion

Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 1

FILED UNITED STATES COURT OF APPEALS United States Court of Appeals Tenth Circuit FOR THE TENTH CIRCUIT _________________________________ May 29, 2026

Christopher M. Wolpert SJH 11 LLC, a Delaware limited liability Clerk of Court company,

Plaintiff - Appellee,

v. No. 25-8037 (D.C. No. 1:25-CV-00018-SWS) DOWBUILT, INC., a Washington (D. Wyo.) corporation and John Does 1-10,

Defendants - Appellants. _________________________________

ORDER AND JUDGMENT * _________________________________

Before MORITZ and FEDERICO, Circuit Judges, and ALLEN, District Judge **. _________________________________

During an arbitration between plaintiff SJH 11 LLC and nonparty SDI LLC—

which is ostensibly owned by defendant Dowbuilt, Inc.—the arbitrator ruled that SJH

was not required to arbitrate certain of its claims against Dowbuilt and instead could

file those claims in a court of competent jurisdiction. After SJH filed this action,

Dowbuilt moved to compel arbitration. The district court denied the motion and

Dowbuilt appeals.

* This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. But it may be cited for its persuasive value. See Fed. R. App. P. 32.1(a); 10th Cir. R. 32.1(A). ** The Honorable Ann Marie McIff Allen, United States District Judge for the District of Utah, sitting by designation. Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 2

We affirm. Contrary to Dowbuilt’s strained interpretation of the arbitrator’s

order, the arbitrator did in fact determine that SJH is not required to arbitrate the

claims at issue. Since the parties do not dispute that questions of arbitrability were

delegated to the arbitrator, we are bound by that arbitrability ruling.

Background

In 2021, SJH and SDI entered into two identical contracts related to the

development of two properties in Jackson, Wyoming. Although the contracts were

solely between SJH and SDI, SDI included a statement in each that it was doing

business as Dowbuilt. The contracts required all disputes to be first mediated and

then, if unresolved, arbitrated by the American Arbitration Association (AAA) in

accordance with its Construction Industry Arbitration Rules.

SJH terminated the contracts in September 2022. 1 It refused to pay SDI’s final

invoices, and SDI filed for arbitration in November 2023. Referring to itself in its

filings as either doing business as Dowbuilt or simply as Dowbuilt, SDI asserted

claims for breach of contract and unjust enrichment. In February 2024, SJH answered

and filed counterclaims against SDI for breach of contract, breach of the implied

covenant of good faith and fair dealing, and conversion.

On December 6, 2024, SJH filed a motion under Construction Industry

Arbitration Rule 9(a), which provides that “[t]he arbitrator shall have the power to

1 SJH’s complaint alleges that it did so because of what it viewed as SDI’s suspicious billing practices. But its actual termination was for convenience based on a contract provision permitting SJH to “at any time, terminate the [c]ontract for [its] convenience and without cause.” App. vol. 1, 93; see also id. at 129 (same). 2 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 3

rule on his or her own jurisdiction.” App. vol. 2, 333. As relevant here, SJH’s Rule 9

motion asked the arbitrator to make two findings: “(1) that the arbitration is limited

to claims between the parties to the construction contracts (SDI . . . and SJH); [and]

(2) [that] claims against Dowbuilt[,] . . . or any counterclaims or defenses in response

to such claims, are outside the scope of this action.” Id. at 373.

On December 18, the arbitrator conducted a telephone conference on SJH’s

motion. This conversation was not recorded or transcribed. According to Dowbuilt,

“[t]he parties and the arbitrator agreed during the hearing that Dowbuilt would be

joined to the [a]rbitration.” App. vol. 1, 64. Dowbuilt emailed the arbitrator later the

same day confirming its consent to join the arbitration. But SJH asserts that it never

consented to Dowbuilt joining the arbitration with regard to every possible claim it

might have against Dowbuilt; it merely acknowledged during the conference that

some of its February 2024 counterclaims involved Dowbuilt’s conduct. Indeed, SDI’s

counsel stated in a declaration that SJH did not share during the December 18 phone

conference that it planned to assert new claims against Dowbuilt.

The next day, December 19, the arbitrator issued an order denying SJH’s Rule

9 motion not on the merits but as “untimely under the provisions of the AAA

Construction Industry Arbitration Rule 9[(c)],” id. at 150, which requires such

motions to be submitted “no later than the filing of the answering statement,” App.

vol. 2, 333. The order noted SJH’s statement “that some of its counterclaims were

against Dowbuilt . . . , an entity distinct from [SDI]”; said that “the parties have

treated SDI . . . and Dowbuilt interchangeably” throughout the arbitration; and noted

3 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 4

Dowbuilt’s consent “to be a party in this arbitration for purposes of defending any

claims that [SJH] has against it.” App. vol. 1, 150.

On December 30, SJH filed amended counterclaims in the arbitration, seeking

to add new fraud and other tort claims against Dowbuilt. The next day, SDI and

Dowbuilt moved to strike the amended counterclaims as untimely. Later the same

day, SJH replied, arguing that its amended counterclaims were, as “a matter of due

process,” required by the denial of its Rule 9 motion. Id. at 252. SJH stated it “did

not agree to Dowbuilt . . . being a party, quite the contrary, and has not treated these

two parties as interchangeable,” despite SDI “taking the unusual approach of

admitting SDI and Dowbuilt . . . are alter egos of one another.” Id. SJH further

argued that its additional, “separate” claims against Dowbuilt were “outside of the

contract.” Id. Adding Dowbuilt to the arbitration, SJH stated, “gets Dowbuilt . . . the

benefit of not being pursued in . . . state or federal court.” Id.

On January 2, 2025, the arbitrator issued an order striking SJH’s amended

counterclaims as untimely under Construction Industry Arbitration Rule 6(b), which

provides that “[a]fter the arbitrator is appointed[,] no new or different claim or

counterclaim may be submitted without the arbitrator’s consent.” Id. at 258 (quoting

App. vol. 2, 332). The arbitrator described the December 19 order denying SJH’s

Rule 9 motion as an order “that [SJH’s] pending claims against Dowbuilt, . . . as

represented in [SJH’s] counterclaim dated February . . . 2024, be included in this

arbitration.” Id. So, the arbitrator explained, SJH could still pursue its February 2024

counterclaims against Dowbuilt; it just couldn’t assert any new claims in the

4 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 5

arbitration.

On January 7, SJH filed a motion for clarification, asking the arbitrator to

“confirm” that the January 2 order didn’t “prevent or otherwise preclude SJH from

pursuing any and all new claims set forth in the [a]mended . . . [c]ounterclaim[s]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Energy Corp. v. Nukem, Inc.
400 F.3d 822 (Tenth Circuit, 2005)
Henry Schein, Inc. v. Archer & White Sales, Inc.
586 U.S. 63 (Supreme Court, 2019)
Coinbase, Inc. v. Bielski
599 U.S. 736 (Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
SJH 11 v. Dowbuilt, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sjh-11-v-dowbuilt-ca10-2026.