Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 1
FILED UNITED STATES COURT OF APPEALS United States Court of Appeals Tenth Circuit FOR THE TENTH CIRCUIT _________________________________ May 29, 2026
Christopher M. Wolpert SJH 11 LLC, a Delaware limited liability Clerk of Court company,
Plaintiff - Appellee,
v. No. 25-8037 (D.C. No. 1:25-CV-00018-SWS) DOWBUILT, INC., a Washington (D. Wyo.) corporation and John Does 1-10,
Defendants - Appellants. _________________________________
ORDER AND JUDGMENT * _________________________________
Before MORITZ and FEDERICO, Circuit Judges, and ALLEN, District Judge **. _________________________________
During an arbitration between plaintiff SJH 11 LLC and nonparty SDI LLC—
which is ostensibly owned by defendant Dowbuilt, Inc.—the arbitrator ruled that SJH
was not required to arbitrate certain of its claims against Dowbuilt and instead could
file those claims in a court of competent jurisdiction. After SJH filed this action,
Dowbuilt moved to compel arbitration. The district court denied the motion and
Dowbuilt appeals.
* This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. But it may be cited for its persuasive value. See Fed. R. App. P. 32.1(a); 10th Cir. R. 32.1(A). ** The Honorable Ann Marie McIff Allen, United States District Judge for the District of Utah, sitting by designation. Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 2
We affirm. Contrary to Dowbuilt’s strained interpretation of the arbitrator’s
order, the arbitrator did in fact determine that SJH is not required to arbitrate the
claims at issue. Since the parties do not dispute that questions of arbitrability were
delegated to the arbitrator, we are bound by that arbitrability ruling.
Background
In 2021, SJH and SDI entered into two identical contracts related to the
development of two properties in Jackson, Wyoming. Although the contracts were
solely between SJH and SDI, SDI included a statement in each that it was doing
business as Dowbuilt. The contracts required all disputes to be first mediated and
then, if unresolved, arbitrated by the American Arbitration Association (AAA) in
accordance with its Construction Industry Arbitration Rules.
SJH terminated the contracts in September 2022. 1 It refused to pay SDI’s final
invoices, and SDI filed for arbitration in November 2023. Referring to itself in its
filings as either doing business as Dowbuilt or simply as Dowbuilt, SDI asserted
claims for breach of contract and unjust enrichment. In February 2024, SJH answered
and filed counterclaims against SDI for breach of contract, breach of the implied
covenant of good faith and fair dealing, and conversion.
On December 6, 2024, SJH filed a motion under Construction Industry
Arbitration Rule 9(a), which provides that “[t]he arbitrator shall have the power to
1 SJH’s complaint alleges that it did so because of what it viewed as SDI’s suspicious billing practices. But its actual termination was for convenience based on a contract provision permitting SJH to “at any time, terminate the [c]ontract for [its] convenience and without cause.” App. vol. 1, 93; see also id. at 129 (same). 2 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 3
rule on his or her own jurisdiction.” App. vol. 2, 333. As relevant here, SJH’s Rule 9
motion asked the arbitrator to make two findings: “(1) that the arbitration is limited
to claims between the parties to the construction contracts (SDI . . . and SJH); [and]
(2) [that] claims against Dowbuilt[,] . . . or any counterclaims or defenses in response
to such claims, are outside the scope of this action.” Id. at 373.
On December 18, the arbitrator conducted a telephone conference on SJH’s
motion. This conversation was not recorded or transcribed. According to Dowbuilt,
“[t]he parties and the arbitrator agreed during the hearing that Dowbuilt would be
joined to the [a]rbitration.” App. vol. 1, 64. Dowbuilt emailed the arbitrator later the
same day confirming its consent to join the arbitration. But SJH asserts that it never
consented to Dowbuilt joining the arbitration with regard to every possible claim it
might have against Dowbuilt; it merely acknowledged during the conference that
some of its February 2024 counterclaims involved Dowbuilt’s conduct. Indeed, SDI’s
counsel stated in a declaration that SJH did not share during the December 18 phone
conference that it planned to assert new claims against Dowbuilt.
The next day, December 19, the arbitrator issued an order denying SJH’s Rule
9 motion not on the merits but as “untimely under the provisions of the AAA
Construction Industry Arbitration Rule 9[(c)],” id. at 150, which requires such
motions to be submitted “no later than the filing of the answering statement,” App.
vol. 2, 333. The order noted SJH’s statement “that some of its counterclaims were
against Dowbuilt . . . , an entity distinct from [SDI]”; said that “the parties have
treated SDI . . . and Dowbuilt interchangeably” throughout the arbitration; and noted
3 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 4
Dowbuilt’s consent “to be a party in this arbitration for purposes of defending any
claims that [SJH] has against it.” App. vol. 1, 150.
On December 30, SJH filed amended counterclaims in the arbitration, seeking
to add new fraud and other tort claims against Dowbuilt. The next day, SDI and
Dowbuilt moved to strike the amended counterclaims as untimely. Later the same
day, SJH replied, arguing that its amended counterclaims were, as “a matter of due
process,” required by the denial of its Rule 9 motion. Id. at 252. SJH stated it “did
not agree to Dowbuilt . . . being a party, quite the contrary, and has not treated these
two parties as interchangeable,” despite SDI “taking the unusual approach of
admitting SDI and Dowbuilt . . . are alter egos of one another.” Id. SJH further
argued that its additional, “separate” claims against Dowbuilt were “outside of the
contract.” Id. Adding Dowbuilt to the arbitration, SJH stated, “gets Dowbuilt . . . the
benefit of not being pursued in . . . state or federal court.” Id.
On January 2, 2025, the arbitrator issued an order striking SJH’s amended
counterclaims as untimely under Construction Industry Arbitration Rule 6(b), which
provides that “[a]fter the arbitrator is appointed[,] no new or different claim or
counterclaim may be submitted without the arbitrator’s consent.” Id. at 258 (quoting
App. vol. 2, 332). The arbitrator described the December 19 order denying SJH’s
Rule 9 motion as an order “that [SJH’s] pending claims against Dowbuilt, . . . as
represented in [SJH’s] counterclaim dated February . . . 2024, be included in this
arbitration.” Id. So, the arbitrator explained, SJH could still pursue its February 2024
counterclaims against Dowbuilt; it just couldn’t assert any new claims in the
4 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 5
arbitration.
On January 7, SJH filed a motion for clarification, asking the arbitrator to
“confirm” that the January 2 order didn’t “prevent or otherwise preclude SJH from
pursuing any and all new claims set forth in the [a]mended . . . [c]ounterclaim[s]
Free access — add to your briefcase to read the full text and ask questions with AI
Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 1
FILED UNITED STATES COURT OF APPEALS United States Court of Appeals Tenth Circuit FOR THE TENTH CIRCUIT _________________________________ May 29, 2026
Christopher M. Wolpert SJH 11 LLC, a Delaware limited liability Clerk of Court company,
Plaintiff - Appellee,
v. No. 25-8037 (D.C. No. 1:25-CV-00018-SWS) DOWBUILT, INC., a Washington (D. Wyo.) corporation and John Does 1-10,
Defendants - Appellants. _________________________________
ORDER AND JUDGMENT * _________________________________
Before MORITZ and FEDERICO, Circuit Judges, and ALLEN, District Judge **. _________________________________
During an arbitration between plaintiff SJH 11 LLC and nonparty SDI LLC—
which is ostensibly owned by defendant Dowbuilt, Inc.—the arbitrator ruled that SJH
was not required to arbitrate certain of its claims against Dowbuilt and instead could
file those claims in a court of competent jurisdiction. After SJH filed this action,
Dowbuilt moved to compel arbitration. The district court denied the motion and
Dowbuilt appeals.
* This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. But it may be cited for its persuasive value. See Fed. R. App. P. 32.1(a); 10th Cir. R. 32.1(A). ** The Honorable Ann Marie McIff Allen, United States District Judge for the District of Utah, sitting by designation. Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 2
We affirm. Contrary to Dowbuilt’s strained interpretation of the arbitrator’s
order, the arbitrator did in fact determine that SJH is not required to arbitrate the
claims at issue. Since the parties do not dispute that questions of arbitrability were
delegated to the arbitrator, we are bound by that arbitrability ruling.
Background
In 2021, SJH and SDI entered into two identical contracts related to the
development of two properties in Jackson, Wyoming. Although the contracts were
solely between SJH and SDI, SDI included a statement in each that it was doing
business as Dowbuilt. The contracts required all disputes to be first mediated and
then, if unresolved, arbitrated by the American Arbitration Association (AAA) in
accordance with its Construction Industry Arbitration Rules.
SJH terminated the contracts in September 2022. 1 It refused to pay SDI’s final
invoices, and SDI filed for arbitration in November 2023. Referring to itself in its
filings as either doing business as Dowbuilt or simply as Dowbuilt, SDI asserted
claims for breach of contract and unjust enrichment. In February 2024, SJH answered
and filed counterclaims against SDI for breach of contract, breach of the implied
covenant of good faith and fair dealing, and conversion.
On December 6, 2024, SJH filed a motion under Construction Industry
Arbitration Rule 9(a), which provides that “[t]he arbitrator shall have the power to
1 SJH’s complaint alleges that it did so because of what it viewed as SDI’s suspicious billing practices. But its actual termination was for convenience based on a contract provision permitting SJH to “at any time, terminate the [c]ontract for [its] convenience and without cause.” App. vol. 1, 93; see also id. at 129 (same). 2 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 3
rule on his or her own jurisdiction.” App. vol. 2, 333. As relevant here, SJH’s Rule 9
motion asked the arbitrator to make two findings: “(1) that the arbitration is limited
to claims between the parties to the construction contracts (SDI . . . and SJH); [and]
(2) [that] claims against Dowbuilt[,] . . . or any counterclaims or defenses in response
to such claims, are outside the scope of this action.” Id. at 373.
On December 18, the arbitrator conducted a telephone conference on SJH’s
motion. This conversation was not recorded or transcribed. According to Dowbuilt,
“[t]he parties and the arbitrator agreed during the hearing that Dowbuilt would be
joined to the [a]rbitration.” App. vol. 1, 64. Dowbuilt emailed the arbitrator later the
same day confirming its consent to join the arbitration. But SJH asserts that it never
consented to Dowbuilt joining the arbitration with regard to every possible claim it
might have against Dowbuilt; it merely acknowledged during the conference that
some of its February 2024 counterclaims involved Dowbuilt’s conduct. Indeed, SDI’s
counsel stated in a declaration that SJH did not share during the December 18 phone
conference that it planned to assert new claims against Dowbuilt.
The next day, December 19, the arbitrator issued an order denying SJH’s Rule
9 motion not on the merits but as “untimely under the provisions of the AAA
Construction Industry Arbitration Rule 9[(c)],” id. at 150, which requires such
motions to be submitted “no later than the filing of the answering statement,” App.
vol. 2, 333. The order noted SJH’s statement “that some of its counterclaims were
against Dowbuilt . . . , an entity distinct from [SDI]”; said that “the parties have
treated SDI . . . and Dowbuilt interchangeably” throughout the arbitration; and noted
3 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 4
Dowbuilt’s consent “to be a party in this arbitration for purposes of defending any
claims that [SJH] has against it.” App. vol. 1, 150.
On December 30, SJH filed amended counterclaims in the arbitration, seeking
to add new fraud and other tort claims against Dowbuilt. The next day, SDI and
Dowbuilt moved to strike the amended counterclaims as untimely. Later the same
day, SJH replied, arguing that its amended counterclaims were, as “a matter of due
process,” required by the denial of its Rule 9 motion. Id. at 252. SJH stated it “did
not agree to Dowbuilt . . . being a party, quite the contrary, and has not treated these
two parties as interchangeable,” despite SDI “taking the unusual approach of
admitting SDI and Dowbuilt . . . are alter egos of one another.” Id. SJH further
argued that its additional, “separate” claims against Dowbuilt were “outside of the
contract.” Id. Adding Dowbuilt to the arbitration, SJH stated, “gets Dowbuilt . . . the
benefit of not being pursued in . . . state or federal court.” Id.
On January 2, 2025, the arbitrator issued an order striking SJH’s amended
counterclaims as untimely under Construction Industry Arbitration Rule 6(b), which
provides that “[a]fter the arbitrator is appointed[,] no new or different claim or
counterclaim may be submitted without the arbitrator’s consent.” Id. at 258 (quoting
App. vol. 2, 332). The arbitrator described the December 19 order denying SJH’s
Rule 9 motion as an order “that [SJH’s] pending claims against Dowbuilt, . . . as
represented in [SJH’s] counterclaim dated February . . . 2024, be included in this
arbitration.” Id. So, the arbitrator explained, SJH could still pursue its February 2024
counterclaims against Dowbuilt; it just couldn’t assert any new claims in the
4 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 5
arbitration.
On January 7, SJH filed a motion for clarification, asking the arbitrator to
“confirm” that the January 2 order didn’t “prevent or otherwise preclude SJH from
pursuing any and all new claims set forth in the [a]mended . . . [c]ounterclaim[s]
against Dowbuilt . . . in a separate proceeding.” Id. at 261. Dowbuilt opposed the
motion, arguing in part that SJH’s additional claims against it were “clearly within
the scope of the [c]ontracts’ arbitration provision[s]” and were therefore waived by
SJH’s failure to include them among the initial February 2024 counterclaims. App.
vol. 2, 468.
The arbitrator issued an order clarifying the January 2 order on January 17,
again characterizing the December 19 order on the Rule 9 motion as allowing SJH’s
February 2024 counterclaims to “proceed against both SDI . . . and Dowbuilt, . . .
based on the representation by SJH that it had been proceeding in its counterclaims
against both entities.” App. vol. 1, 267. But the arbitrator determined that allowing
the February 2024 counterclaims to proceed “d[id] not mandate that SJH is forced to
arbitrate its [other] claims against Dowbuilt . . . in this arbitration or be precluded
from ever asserting those claims.” Id. That was so, the arbitrator reasoned, because
“[t]here is no arbitration agreement between Dowbuilt . . . and SJH.” Id. Thus, the
arbitrator “ordered that SJH retains its right to pursue claims against Dowbuilt . . .
that were not brought in its February . . . 2024 counterclaim[] in a court of competent
5 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 6
jurisdiction.” 2 Id.
Two days later, SJH filed this action in federal district court against Dowbuilt,
asserting claims for fraud, negligent misrepresentation, conversion, and unjust
enrichment. Several months after that, Dowbuilt filed a motion to compel arbitration.
The district court denied the motion to compel, ruling that it was bound by the
arbitrator’s decision that SJH’s claims, to the extent they were not February 2024
counterclaims, weren’t arbitrable. It additionally ruled that SJH had not consented to
arbitration, that Dowbuilt’s consent was insufficient on its own, and that equitable
estoppel did not support compelling arbitration.
Dowbuilt appeals. 3 See 9 U.S.C. § 16(a)(1) (order denying motion to compel
arbitration is immediately appealable).
Analysis
“We review de novo the decision of the district court to grant or deny a motion
to compel arbitration.” Reeves v. Enter. Prods. Partners, LP, 17 F.4th 1008, 1011
(10th Cir. 2021). The parties agree on the applicable law. “Under the Federal
2 Within hours of the January 17 order, Dowbuilt and SDI backpedaled and sought to consent to SJH’s proposed amended counterclaims, which the arbitrator had previously struck as untimely at Dowbuilt and SDI’s urging in its January 2 order. SJH opposed that attempt, stating it planned to “proceed[] with its claims against Dowbuilt . . . in a court of competent jurisdiction.” App. vol. 2, 546. The arbitrator rejected Dowbuilt and SDI’s belated consent, responding that as things stood, the scheduled hearing would consider only “the claims brought by SDI against SJH and the counterclaims made by SJH in its February . . . 2024 pleading against SDI and Dowbuilt.” Id. at 542. 3 The district court, as it’s required to do, stayed proceedings below while this appeal is pending. See Coinbase, Inc. v. Bielski, 599 U.S. 736, 747 (2023). It appears that the underlying arbitration is stayed, as well. 6 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 7
Arbitration Act, parties to a contract may agree that an arbitrator rather than a court
will resolve disputes arising out of the contract.” Henry Schein, Inc. v. Archer &
White Sales, Inc., 586 U.S. 63, 65 (2019). “The Act allows parties to agree by
contract that an arbitrator, rather than a court, will resolve threshold arbitrability
questions[,] as well.” Id. And crucially, “[w]hen the parties’ contract delegates the
arbitrability question to an arbitrator, a court may not override the contract.” Id. at
68. That’s because “arbitration is a matter of contract, and courts must enforce
arbitration contracts according to their terms.” Id. at 67.
Here, Dowbuilt accepts that SJH’s contracts with SDI, by electing to apply
AAA arbitration rules, delegated arbitrability questions to the arbitrator. 4 Dowbuilt
also accepts that we would therefore be bound by the arbitrator’s decision on that
point. But according to Dowbuilt, the arbitrator never decided arbitrability. In
support, Dowbuilt focuses on the third paragraph of the January 17 order, which
states that SJH must continue arbitrating its February 2024 counterclaims against
Dowbuilt but will not be “forced to arbitrate its [new] claims against Dowbuilt . . . in
this arbitration or be precluded from ever asserting those claims.” App. vol. 1, 267
(emphasis added). Dowbuilt interprets this language as a ruling that SJH can’t bring
its new claims “in this arbitration,” id. (emphasis added), not a broader ruling about
4 Dowbuilt also affirmatively asked the arbitrator to decide arbitrability. It argued, in response to SJH’s clarification motion, that SJH’s claims against it were waived because they were “clearly within the scope of the [c]ontracts’ arbitration provision[s].” App. vol. 2, 468. In so doing, Dowbuilt asked the arbitrator to decide if SJH’s claims were arbitrable. 7 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 8
the arbitrability of those claims—for instance, whether they are arbitrable in a
separate arbitration proceeding.
But Dowbuilt’s myopic focus on the third paragraph overlooks the remainder
of the arbitrator’s order. The second paragraph states that “[t]here is no arbitration
agreement between Dowbuilt . . . and SJH.” Id. And there would be no need to
mention that fact if the arbitrator was not deciding arbitrability. And more
importantly, the fourth and final paragraph of the January 17 order explicitly states
“that SJH retains its right to pursue claims against Dowbuilt . . . that were not
brought in its February . . . 2024 counterclaim[] in a court of competent jurisdiction.”
Id. (emphasis added). This is more than a conclusion that SJH’s new claims against
Dowbuilt can’t be brought in this particular arbitration; it’s a conclusion that SJH is
not required to arbitrate its new claims against Dowbuilt.
The broader procedural context preceding the January 17 order corroborates
that conclusion. SJH’s initial Rule 9 motion sought to confirm that it could bring
claims against Dowbuilt outside the arbitration. But at that time, SJH did not tip its
hand that it planned to assert a new batch of noncontractual tort claims against
Dowbuilt. In Dowbuilt’s words, “SJH did not mention during the conference that it
intended to assert new causes of action or to increase its damages claim against either
SDI or Dowbuilt.” Id. at 64. Thus, the discussion between the parties and the
arbitrator at that time was limited to deciding whether SJH’s existing February 2024
counterclaims could proceed against Dowbuilt in the arbitration. And the only
question addressed in the December 19 order was whether “any claims” then pending
8 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 9
against Dowbuilt were properly within the scope of the arbitration. Id. at 150. The
arbitrator answered that question in the affirmative, based on the parties, and
especially SDI, treating Dowbuilt and SDI as alter egos.
Reading the December 19 order as limited to the February 2024 counterclaims
likewise clarifies the untimeliness rationale of the January 2 order: preventing SJH
from asserting new claims against Dowbuilt so close to the scheduled arbitration
hearing. The January 17 order in turn confirms that the December 19 order was
limited to SJH’s February 2024 counterclaims. It describes that order as authorizing
the “unusual situation” “that the counterclaims brought by [SJH] . . . would proceed
against both SDI . . . and Dowbuilt.” Id. at 267.
With this context, the January 17 order provided the requested clarification on
the arbitrability of all SJH’s proposed claims against Dowbuilt: the February 2024
counterclaims against Dowbuilt would remain in the arbitration, but the new claims
were not required to be there. Despite Dowbuilt’s protestations, that’s an arbitrability
ruling—SJH is not required to arbitrate its new tort claims against Dowbuilt. We
therefore reject Dowbuilt’s argument that the arbitrator didn’t decide the arbitrability
of SJH’s claims against Dowbuilt. 5
That is the end of the matter, given that Dowbuilt concedes both the factual
5 Dowbuilt alternatively argues that the January 17 order is ambiguous regarding arbitrability, so we should remand to the arbitrator for clarity. For authority, it cites a case holding that remand to the arbitrator may be appropriate to clarify an ambiguous award. See U.S. Energy Corp. v. Nukem, Inc., 400 F.3d 822, 830 (10th Cir. 2005). But not only is the arbitrator’s January 17 order not an award— it’s also not ambiguous, as the discussion above illustrates. 9 Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 10
proposition that the parties agreed to submit arbitrability questions to the arbitrator
and the legal proposition that we lack the authority to override that agreement. To be
sure, Dowbuilt additionally argues that SJH should be compelled to arbitrate its
claims because it consented to do so and as a matter of equitable estoppel. But
because these are arbitrability arguments, we decline to consider them. The arbitrator
determined the arbitrability of the new claims, and we “may not decide an
arbitrability question that the parties have delegated to an arbitrator.” Henry Schein,
Inc., 586 U.S. at 69.
Conclusion
Because the parties delegated arbitrability to the arbitrator and the arbitrator
decided that SJH was not required to arbitrate its claims against Dowbuilt—with the
limited, unusual exception of the February 2024 counterclaims already filed in the
arbitration—we affirm the district court’s order denying Dowbuilt’s motion to
compel and remand for further proceedings.
Entered for the Court
Nancy L. Moritz Circuit Judge