SJH 11 v. Dowbuilt

Court of Appeals for the Tenth Circuit·Decided May 29, 2026·No. 25-8037·Unpublished

Opinion

FILED

UNITED STATES COURT OF APPEALS United States Court of Appeals Tenth Circuit

FOR THE TENTH CIRCUIT

_________________________________ May 29, 2026

Christopher M. Wolpert

SJH 11 LLC, a Delaware limited liability Clerk of Court company,

Plaintiff - Appellee,

v. No. 25-8037 (D.C. No. 1:25-CV-00018-SWS)

DOWBUILT, INC., a Washington (D. Wyo.) corporation and John Does 1-10,

Defendants - Appellants.

ORDER AND JUDGMENT *

Before MORITZ and FEDERICO, Circuit Judges, and ALLEN, District Judge **.

During an arbitration between plaintiff SJH 11 LLC and nonparty SDI LLC—

which is ostensibly owned by defendant Dowbuilt, Inc.—the arbitrator ruled that SJH was not required to arbitrate certain of its claims against Dowbuilt and instead could file those claims in a court of competent jurisdiction. After SJH filed this action, Dowbuilt moved to compel arbitration. The district court denied the motion and Dowbuilt appeals.

*

This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. But it may be cited for its persuasive value. See Fed. R. App. P. 32.1(a); 10th Cir. R. 32.1(A).

**

The Honorable Ann Marie McIff Allen, United States District Judge for the District of Utah, sitting by designation.

We affirm. Contrary to Dowbuilt’s strained interpretation of the arbitrator’s order, the arbitrator did in fact determine that SJH is not required to arbitrate the claims at issue. Since the parties do not dispute that questions of arbitrability were delegated to the arbitrator, we are bound by that arbitrability ruling.

Background

In 2021, SJH and SDI entered into two identical contracts related to the development of two properties in Jackson, Wyoming. Although the contracts were solely between SJH and SDI, SDI included a statement in each that it was doing business as Dowbuilt. The contracts required all disputes to be first mediated and then, if unresolved, arbitrated by the American Arbitration Association (AAA) in accordance with its Construction Industry Arbitration Rules.

SJH terminated the contracts in September 2022. 1 It refused to pay SDI’s final invoices, and SDI filed for arbitration in November 2023. Referring to itself in its filings as either doing business as Dowbuilt or simply as Dowbuilt, SDI asserted claims for breach of contract and unjust enrichment. In February 2024, SJH answered and filed counterclaims against SDI for breach of contract, breach of the implied covenant of good faith and fair dealing, and conversion.

On December 6, 2024, SJH filed a motion under Construction Industry Arbitration Rule 9(a), which provides that “[t]he arbitrator shall have the power to

1 SJH’s complaint alleges that it did so because of what it viewed as SDI’s suspicious billing practices. But its actual termination was for convenience based on a contract provision permitting SJH to “at any time, terminate the [c]ontract for [its] convenience and without cause.” App. vol. 1, 93; see also id. at 129 (same).

rule on his or her own jurisdiction.” App. vol. 2, 333. As relevant here, SJH’s Rule 9 motion asked the arbitrator to make two findings: “(1) that the arbitration is limited to claims between the parties to the construction contracts (SDI . . . and SJH); [and] (2) [that] claims against Dowbuilt[,] . . . or any counterclaims or defenses in response to such claims, are outside the scope of this action.” Id. at 373.

On December 18, the arbitrator conducted a telephone conference on SJH’s motion. This conversation was not recorded or transcribed. According to Dowbuilt, “[t]he parties and the arbitrator agreed during the hearing that Dowbuilt would be joined to the [a]rbitration.” App. vol. 1, 64. Dowbuilt emailed the arbitrator later the same day confirming its consent to join the arbitration. But SJH asserts that it never consented to Dowbuilt joining the arbitration with regard to every possible claim it might have against Dowbuilt; it merely acknowledged during the conference that some of its February 2024 counterclaims involved Dowbuilt’s conduct. Indeed, SDI’s counsel stated in a declaration that SJH did not share during the December 18 phone conference that it planned to assert new claims against Dowbuilt.

The next day, December 19, the arbitrator issued an order denying SJH’s Rule 9 motion not on the merits but as “untimely under the provisions of the AAA Construction Industry Arbitration Rule 9[(c)],” id. at 150, which requires such motions to be submitted “no later than the filing of the answering statement,” App. vol. 2, 333. The order noted SJH’s statement “that some of its counterclaims were against Dowbuilt . . . , an entity distinct from [SDI]”; said that “the parties have treated SDI . . . and Dowbuilt interchangeably” throughout the arbitration; and noted

Dowbuilt’s consent “to be a party in this arbitration for purposes of defending any claims that [SJH] has against it.” App. vol. 1, 150.

On December 30, SJH filed amended counterclaims in the arbitration, seeking to add new fraud and other tort claims against Dowbuilt. The next day, SDI and Dowbuilt moved to strike the amended counterclaims as untimely. Later the same day, SJH replied, arguing that its amended counterclaims were, as “a matter of due process,” required by the denial of its Rule 9 motion. Id. at 252. SJH stated it “did not agree to Dowbuilt . . . being a party, quite the contrary, and has not treated these two parties as interchangeable,” despite SDI “taking the unusual approach of admitting SDI and Dowbuilt . . . are alter egos of one another.” Id. SJH further argued that its additional, “separate” claims against Dowbuilt were “outside of the contract.” Id. Adding Dowbuilt to the arbitration, SJH stated, “gets Dowbuilt . . . the benefit of not being pursued in . . . state or federal court.” Id.

On January 2, 2025, the arbitrator issued an order striking SJH’s amended counterclaims as untimely under Construction Industry Arbitration Rule 6(b), which provides that “[a]fter the arbitrator is appointed[,] no new or different claim or counterclaim may be submitted without the arbitrator’s consent.” Id. at 258 (quoting App. vol. 2, 332). The arbitrator described the December 19 order denying SJH’s Rule 9 motion as an order “that [SJH’s] pending claims against Dowbuilt, . . . as represented in [SJH’s] counterclaim dated February . . . 2024, be included in this arbitration.” Id. So, the arbitrator explained, SJH could still pursue its February 2024 counterclaims against Dowbuilt; it just couldn’t assert any new claims in the

arbitration.

On January 7, SJH filed a motion for clarification, asking the arbitrator to “confirm” that the January 2 order didn’t “prevent or otherwise preclude SJH from pursuing any and all new claims set forth in the [a]mended . . . [c]ounterclaim[s] against Dowbuilt . . . in a separate proceeding.” Id. at 261. Dowbuilt opposed the motion, arguing in part that SJH’s additional claims against it were “clearly within the scope of the [c]ontracts’ arbitration provision[s]” and were therefore waived by SJH’s failure to include them among the initial February 2024 counterclaims. App. vol. 2, 468.

Free access — add to your briefcase to read the full text and ask questions with AI

SJH 11 v. Dowbuilt, (10th Cir. 2026).

SJH 11 v. Dowbuilt (SJH 11 v. Dowbuilt) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

U.S. Energy Corp. v. Nukem, Inc.
400 F.3d 822 (Tenth Circuit, 2005)
Henry Schein, Inc. v. Archer & White Sales, Inc.
586 U.S. 63 (Supreme Court, 2019)
Coinbase, Inc. v. Bielski
599 U.S. 736 (Supreme Court, 2023)