Sioux City Foundry Co. v. City of South Sioux City

968 F.2d 777, 1992 U.S. App. LEXIS 15709, 1992 WL 158574
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 10, 1992
DocketNo. 91-2268
StatusPublished
Cited by2 cases

This text of 968 F.2d 777 (Sioux City Foundry Co. v. City of South Sioux City) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sioux City Foundry Co. v. City of South Sioux City, 968 F.2d 777, 1992 U.S. App. LEXIS 15709, 1992 WL 158574 (8th Cir. 1992).

Opinion

LOKEN, Circuit Judge.

In 1968, Sioux City Foundry Company (“SCF”) contracted with South Sioux City, Nebraska, to purchase electricity from the City-owned utility at a special rate. In April 1989, after determining that the. special rate was failing to cover its wholesale power costs, the City declared the contract null and void and began billing SCF at a significantly higher rate. SCF, a citizen of Iowa, brought this diversity suit to enforce the contract and appeals the district court’s determination that the contract is ultra vires and unenforceable. Concluding that the contract was within the City’s delegated powers, we reverse.

I.

In 1968, SCF wanted to build a new plant for its casting division, and South Sioux City was anxious to attract new industry. The City urged SCF to build the plant in South Sioux City and offered to provide electricity from its municipally owned distribution system at a favorable rate. Because it had no other power customer of comparable size, the City devised an appropriate large-user rate with the help of its wholesale supplier, Consumers Public Power District (CPPD).

At a meeting on Christmas Eve 1968, the City Council approved by resolution a contract under which the City would provide electricity to SCF’s new plant at a Special Foundry Power Rate (the Foundry Rate). The contract term was twenty-three years, the length of CPPD’s franchise to supply power to the City. The contract included rate-escalation provisions permitting the City to pass on increases in its wholesale electricity costs. Following City Council approval, SCF announced that it would build the million-dollar plant in South Sioux City. The parties signed a written contract and SCF completed the plant in 1969.

The contract was substantially modified in 1977, reflecting the City’s determination that the rate-adjustment provisions were inadequate. SCF agreed to increase the base rate and to amend the rate-escalation provisions, and the City agreed to extend the term of the contract until September 16, 2002. The Foundry Rate was adjusted annually in accordance with this 1977 addendum until 1989.

By the late 1980s, the Foundry Rate had become less favorable to the City because the demand charges it was paying to its supplier, now the Nebraska Public Power District, had escalated dramatically, while the City’s demand charges to SCF were fixed for the length of the contract in the 1977 addendum.1 Moreover, when more sophisticated meters were installed, the City determined that SCF’s peak demand periods largely coincided with the City’s, which increased the City’s cost of power.2

In March 1989,' City Attorney Wayne Boyd opined that the contract would be invalid if the City’s consultant concluded that the Foundry Rate was “not fair, reasonable and adequate to return the cost of service to the City, with a reasonable return for capital, construction and payment of indebtedness.” That same month, the City’s consultant reported that, “For fiscal year 1988, the cost of service [under the contract] was $537,004 compared to revenues received of $337,301.” At a meeting on April 4, 1989, the City Council passed a motion declaring the SCF contract “null [779]*779and void.” The City then began billing SCF at the “Large Light and Power” rate contained in the City’s 1982 general rate ordinance. SCF’s electricity charges have been, on average, about $20,000 per month higher under this rate than under the Foundry Rate.

In response, SCF protested and commenced this action. SCF’s amended complaint seeks declaratory and injunctive relief and damages, alleging that the contract is valid, that the City breached the contract by declaring it null and void and by unilaterally implementing the Large Light and Power rate, and that the City is estopped to deny the contract’s validity. Following an evidentiary hearing, the district court preliminarily enjoined the City from attempting to collect the higher rates. Applying the preliminary injunction factors from Dataphase Systems, Inc. v. CL Systems, Inc., 640 F.2d 109 (8th Cir.1981), the court tentatively concluded, among other things, that SCF would probably prevail on the merits because the contract was a valid exercise of the City’s proprietary powers.

SCF then moved for summary judgment. Reversing its previous position, the district court denied this motion and dissolved the preliminary injunction, concluding that there was no specific statutory authority for the contract, that a municipality may not contract away its legislative rate-setting power absent clear statutory authority, and therefore that the contract was ultra vires and void. SCF appeals the district court’s dissolution of the preliminary injunction, an appealable order under 28 U.S.C. § 1292(a)(1).

Although the decision to grant or deny a preliminary injunction is generally subject to appellate review only for abuse of discretion, the parties argue legal rather than discretionary equitable issues on this appeal.3 Both parties ask us to take up the district court’s ruling that the 1968 contract is invalid, a question of law that we review de novo. See Bell v. Sellevold, 713 F.2d 1396, 1399 (8th Cir.1983), cert. denied, 464 U.S. 1070, 104 S.Ct. 978, 79 L.Ed.2d 215 (1984).

II.

The parties present us with a narrow issue, whether the City in 1968 had the power to enter into a binding long-term contract specifying the rates SCF would pay for electricity purchased from the municipal distribution system. The parties agree that Nebraska law governs. South Sioux City, as a municipal corporation, has only those powers delegated to it by the State; these include powers “granted in express words; ... those necessarily or fairly implied in or incident to the powers expressly granted; [and] those essential to the declared objects and purposes of the corporation.” Jacobs v. City of Omaha, 181 Neb. 101, 147 N.W.2d 160, 163 (1966).

In general, municipal powers are either legislative or proprietary. See 2 Charles Keating and Stephen Flanagan, McQuillin’s Law of Municipal Corporations § 10.05 (3d ed. 1988). The distinction is important for two reasons. First, the grant of proprietary powers to act in the city’s corporate capacity for the benefit of its residents “necessarily implies all the incidental powers to do anything that any business man or corporation ought to do in operating a successful business enterprise.” Nelson-Johnston & Doudna v. Metropolitan Util. Dist., 137 Neb. 871, 291 N.W. 558, 560-61 (1940) (power to operate municipal electric utility includes power to sell appliances at retail). On the other hand, legislative powers are the acts of the sovereign and may only be exercised when expressly delegated by the state legislature. See Wabaska Elec. Co. v. City of Wymore, 60 Neb. 199, 82 N.W. 626, 627 (1900) (municipality has no power to regulate private utility’s rates absent statutory authority).

[780]*780Second, and more germane to this case, while long-term contracts are a readily accepted method of exercising a municipality’s proprietary powers, they are highly suspect in the legislative arena.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
968 F.2d 777, 1992 U.S. App. LEXIS 15709, 1992 WL 158574, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sioux-city-foundry-co-v-city-of-south-sioux-city-ca8-1992.