Sinclair Refining Co. v. J. H. Cobb, Inc.

112 So. 2d 582, 1959 Fla. App. LEXIS 2948
CourtDistrict Court of Appeal of Florida
DecidedJune 5, 1959
DocketNo. 974
StatusPublished
Cited by2 cases

This text of 112 So. 2d 582 (Sinclair Refining Co. v. J. H. Cobb, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sinclair Refining Co. v. J. H. Cobb, Inc., 112 So. 2d 582, 1959 Fla. App. LEXIS 2948 (Fla. Ct. App. 1959).

Opinion

KANNER, Chief Judge.

This appeal, interlocutory in nature, inquires whether the filling station of appellant, Sinclair Refining Company, is subject to enforcement of a mechanic’s lien because of failure, under the trial court’s interpretation, to comply by its contract with the builder or otherwise with the statutory withholding provision.

Suit was brought under the contention that the requisite of section 84.05(11) (a), Florida Statutes, F.S.A., for the withholding by the owner of 20 per cent of each periodic payment due the building contractor had not been complied with. After the suit had been filed, appellant entered a cross-complaint, bringing into the suit other unpaid subcontractors and materialmen by permission of the court. This cross-complaint was dismissed by the court upon motion of one of the lien claimants thus brought into the suit, and it is from this determination that the appeal has been instituted. The trial court held that the direct contract here involved required progress payments of 80 per cent of the value of work completed at any particular time, that the statutory requirement necessitated the withholding of 20 per cent of these curtailed payments, and that appellant had not so performed.

The pertinent segment of section 84.05 (11) (a) reads as follows:

“If the owner fails to require or if for any reason the contractor fails to furnish the bond and notwithstanding the provisions of any other section of this chapter, the owner shall not pay any money on account of the direct contract prior to the visible commencement of operations and any amount so paid shall be held improperly paid, and the owner shall ¡with-. hold twenty per cent of each payment when it becomes due under the direct contract. In no event shall the owner pay more than eighty per cent of the contract price if the bond is not furnished until the contract has been ful[584]*584ly performed and final payment is due and the contractor has furnished the owner statement under oath required by § 84.04(3). If the statement recites any outstanding bills for labor, services or materials, or if the owner has knowledge of any, the owner shall pay such bills in full direct to the person or firm to whom they are due, if the balance due on the contract is sufficient, and deduct the amounts so paid from the balance due the contractor. If the balance due on the contract is not sufficient to pay all bills in full, the owner shall pay no money to anyone until such time as the contractor has furnished him with the difference. In the event the contractor fails to furnish the difference the owner shall determine the amount due each laborer, lienor, materialman or subcontractor and shall disburse to them the amounts due by him on the contract in accordance with the order of liens established herein. In the event the improvement is abandoned prior to completion, the owner shall follow the above procedure and disburse the funds withheld by him before commencing completion of the improvement. When the bond is not furnished nor the twenty per cent of each payment withheld and disbursed as required by this subsection, the property improved shall be subject to a lien in the full amount of any and all outstanding bills for labor, services, or materials furnished for such improvement; provided a claim of lien is filed of record within three months as required by § 84.16, and action to enforce it is commenced within one year from date of filing, in accordance with § 84.21, or the lienor has been made a party defendant in an action involving the real property described in the claim of lien within the same period of time and upon disposition of such action the lienor’s claim shall be discharged.”

A contract was entered into between the appellant and the Richard H. Smith Construction Company, Inc., for the building of a filling station for the sum of $23,180, later increased during construction to $23,-830. Under paragraph seventeen of the contract, it was provided that:

“17 Terms: Invoices shall be rendered on the final day of each month for 80% of the value of work performed, less amounts previously invoiced, payable net 10 days; balance due and payable net 30 days after acceptance of completed work by Sinclair.
“A list of correct names and addresses of all materialmen and subcontractors engaged by Contractor shall be submitted not later than 15 days prior to completion of work.”

Pursuant to this contract provision, progress payments of the amounts due were made by the appellant company on the basis of 80 per cent of the gross amount under each invoice as determined from the overall contract price and the percentage of work completed. This was done under four invoices presented periodically by the construction company, containing the following information:

Date Gross Amount 80% Thereof Less Previous Payment Amount Due
1. 9/20/57 $ 6,954.00 $ 5,563.20 $ $5,563.20
2. 9/30/57 14,298.00 11,438.40 5,563.20 5,875.20
3. 10/22/57 19,064.00 15,251.20 11,438,40 3,812.80
4. 11/20/57 22,638.50 18,110.80 15,251.20 2,859.60.

[585]*585Thus, appellant paid the amount of these invoices in the sum of $18,110.80, representing 80 per cent of the value of work done at the stage of completion shown by the fourth invoice.

Prior to time for final payment but after the work had been completed, appellant required and obtained pursuant to section 84.04(3), Florida Statutes, F.S.A., an affidavit from the construction company, and this document revealed a deficiency in payments of claims to subcontractors and ma-terialmen in the amount of $11,733.46, upon receipt of which information appellant declined to make further payment.

It may be noted that as against this deficiency of $11,733.46, appellant had retained the sum of $5,719.20, or 24 per cent of the total amount of the contract. This represented the 20 per cent remainder left after the 80 per cent payments had been made, plus the remaining amount due under the contract on completion of the work.

In considering the contention of the appellant that the 20 per cent withholding requirement of the statute had been incorporated into the contract and that the statute had been complied with, we find it necessary first to examine comparatively the pertinent provisions of the statute and of the contract in determining whether the trial court erroneously found to the contrary.

The owner, under the language of section 84.05(11) (a), is required to “withhold twenty per cent of each payment when it becomes due under the direct contract”; further, “In no event shall the owner pay more than eighty per cent of the contract price * * * until the contract has been fully performed and final payment is due and the contractor has furnished the owner statement' under oath required by § 84.04 (3).” It is observed that this provision requires no statement from the contractor enumerating unpaid lienors prior to the time that final payment becomes due; yet the statute contemplates progress payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Baird Hardware Co.
147 So. 2d 142 (District Court of Appeal of Florida, 1962)
Karwisch v. Midland Distributors
118 So. 2d 38 (District Court of Appeal of Florida, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
112 So. 2d 582, 1959 Fla. App. LEXIS 2948, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sinclair-refining-co-v-j-h-cobb-inc-fladistctapp-1959.