Martin v. Baird Hardware Co.

147 So. 2d 142
CourtDistrict Court of Appeal of Florida
DecidedNovember 29, 1962
DocketNo. D-397
StatusPublished
Cited by2 cases

This text of 147 So. 2d 142 (Martin v. Baird Hardware Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Baird Hardware Co., 147 So. 2d 142 (Fla. Ct. App. 1962).

Opinion

STURGIS, Judge.

This is an interlocutory appeal by property owners, defendants below, from an order in a suit to foreclose a lien under Chapter 84, Florida Statutes, F.S.A., which granted the plaintiff lienholders’ motion for partial summary decree, holding that plaintiffs were entitled to a lien for the full amount of their claims. Appellants , also seek review of an order denying their petition for rehearing of said order. As the issues on appeal are developed by the first order, it is not necessary to separately treat the latter.

In December 1960 the defendant owners of the subject property contracted with a person who is not a party to this proceeding to construct thereon a veterinary hospital for the contract price of $26,365.40. The contractor did not furnish the bond contemplated by the statute to insure payment of laborers, subcontractors, and ma-terialmen on the job. The contract provided for three progress payments of $8,-333.33 each to be made at stated intervals. [143]*143The first and second payments were made, totaling $16,666.66, but the owners did not withhold 20% thereof as required by Section 84.05(11) (a), Florida Statutes 1961, F.S.A.1 in those instances where, as in this case, the owner fails to exact the mentioned bond of the contractor.

After receiving the second progress payment and prior to completion of the improvement, the direct contractor abandoned the job. At that time the lienors had not furnished owners with the cautionary notice provided by F.S. § 84.04, F.S.A. and there remained in owners’ hands the sum of $9,689.73 on account of the contract price. Shortly thereafter the lienors filed their claims of lien and served copies on owners in accordance with F.S. §§ 84.14, 84.16, and 84.19, F.S.A. In the meantime the owners, without making any attempt to distribute said unpaid balance among the lienors, resumed work on the improvement. However, on May 27, 1961, which was less than 20 days after the contract was abandoned, owners offered to disburse to the lienors ratably in settlement of their claims the said unpaid balance of the contract price. The claims totaled more than that amount and the lienors rejected the offer. Three days later they brought this suit to foreclose their alleged liens in the full amount claimed.

We pause at this juncture to take note of the fact that if the owners had strictly complied with the statutory provision requiring “twenty per cent of each [progress] payment” to be withheld when it became “due under the direct contract,” the total amount that would have been available to the lienors is $3,333.33, representing 20% of the $16,666.66 advance payment; and further, that if the contract had been fully completed by the direct contractor and if the owners had strictly complied with the statutory provision prohibiting them from paying “more than eighty per cent of the contract price * * * until * * * the contractor has furnished the owner statement under oath required by § 84.04 (3),” etc., the total amount available to the lienors would have been $5,273.08, representing 20% of the $26,365.40 contract [144]*144price. See F.S. § 84.05(11) (a), F.S.A.; footnote 1. In either event the amount available for proration among the lienors would have been substantially less than the $9,689.73 balance of the contract price which the owners offered to prorate among them in settlement of their claims.

On the basis of the above recited essential facts, the plaintiff lienors (appellees) moved the trial court to enter a summary decree in their favor on the issue of whether the property which is the subject of this suit is impressed with a lien for the full amount due plaintiffs for work done and materials furnished by them.

In granting said motion the chancellor held, inter alia, and we agree, that on the authority of Lehman v. Snyder, 84 So.2d 312 (Fla.1956), and Sinclair Refining Co. v. J. H. Cobb, Inc., 112 So.2d 582 (Fla.App.1959), and in view of the fact that the sum remaining in the hands of the owners for the benefit of the lienors was in excess of 20% of the total contract price, the owners were not materially in violation of F.S. § 84.05(11) (a), F.S.A. for having failed to deduct and withhold from the direct contractor 20% of the progress payments at the time they were made.

The order appealed contains the following critical comment which forms the basis for the partial summary judgment in question :

“Plaintiffs further contend that after abandonment by the general contractor the Defendants MARTIN commenced completion of the improvement without disbursing the funds withheld by them, and that under the terms of the statute that the property improved should be subject to a lien in the full amount of any and all outstanding bills for labor, services or materials furnished for such improvement. This contention of Plaintiffs must be sustained. The statute is clear and unambiguous in its mandatory requirement that prior to commencing completion after an abandonment the funds withheld must be disbursed as required therein. This the Defendants MARTIN did not do. There appears to be no case construing this provision of the statute and in light of the clear mandate thereof the Court is compelled to grant Plaintiffs’ Motion. The Legislature originally enacted this statute in 1953 and reenacted the same within a very short time after the same was declared unconstitutional in Greenblatt v. Goldin, 94 So.2d 355 (Fla.1957), indicating a clear intention that this requirement become and remain a part of the Florida Mechanics’ Lien law. The law may appear to be harsh in this instance but the requirement is clear. The Legislature has twice enacted this provision. The passage from the opinion of Justice O’Connell in All State Pipe Supply Co. v. McNair, 89 So.2d 774, 775 (Fla.1956) as follows is appropriate :
‘There is nothing to be gained in condemning or applauding the Mechanics’ Lien Law for it is the law of this State. Admittedly, it is harsh in many respects, as applied to an owner, and no one improving property can ignore its provisions without coming to grief.’ ”

We do not interpret the quoted excerpt from All State Pipe Supply Co. as having the connotation accorded to it in application to this case. We are persuaded that the equitable considerations controlling the decisions in Lehman v. Snyder and Sinclair Refining Co. v. J. H. Cobb, Inc., supra, apply hereto with greater force.

A cursory examination of the statute (footnote 1) compels the conclusion that it is so vague and contradictory — in respect to those provisions which purport to state the procedure to be followed by the owner in the event the direct contractor abandons the work and consequent thereon fails to furnish the owner with the statement under oath required by F.S. § [145]*14584.04(3), F.S.A.2 or to furnish the owner with the money required to make up the amount needed to fully discharge lienors’ claims — as to afford no competent procedure which the owner can follow with reasonable certainty that in so doing he will avoid the liability, in the nature of a penalty, which the order appealed imposes for the sole reason stated by the above excerpt therefrom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westinghouse Electric Supply Co. v. 1800 North Federal Corp.
29 Fla. Supp. 136 (Broward County Circuit Court, 1967)
Bryan v. Owsley Lumber Company
201 So. 2d 246 (District Court of Appeal of Florida, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
147 So. 2d 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-baird-hardware-co-fladistctapp-1962.