Simpson v. Board of Supervisors

180 Iowa 1330
CourtSupreme Court of Iowa
DecidedMay 22, 1917
StatusPublished
Cited by12 cases

This text of 180 Iowa 1330 (Simpson v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simpson v. Board of Supervisors, 180 Iowa 1330 (iowa 1917).

Opinion

Stevens, J.

1. Drains : establishment: jurisdiction: return of engineer: boundaries of appropriated land : irregularity only. Prior to June 17, 1914, a petition was filed in the auditor’s office of both Kossuth and Emmet Counties praying the establishment of a joint drainage district. After due notice to the parties entitled thereto, the boards met in joint session, and, on July 17, 1914, passed a resolution establishing the proposed district, designating it as the Emmet and Kossuth County Drainage District No. 2. The engineer appointed by the respective boards to make preliminary survey and report as to the feasibility and practicability of the proposed improvement, on March 3, 1914, submitted his report recommending the establishment of the proposed district, and filed plat and profile showing the land to be included within the district, and the location, route and terminus of the proposed ditch. The report of the engineer recommended a ditch 12 feet wide on the bottom, with side slopes of one to one, but neither the report of the engineer nor the resolution of the boards of supervisors fixed the width of the right of way sought to be taken for the use [1333]*1333of the public in the construction of the improvement. The appraisers appointed by the respective boards of supervisors to appraise damages estimated that the right of way required would be 85 feet, and computed the amount of damages to be awarded to each of the several property owners upon that basis. After the work of excavation began, it became apparent that the 85-foot right of way was not sufficient, and that the spoil bank had to be placed so near the ditch that the earth therefrom would wash into the ditch, causing it to fill. The report and plan -of the engineer provided that a berm should be left on each side of the ditch, 8 feet in width, but, on account of the peculiar character of the soil, it was found that the earth removed spread to such an extent as to require a right of way of from 100 to 120 feet in width. To meet this contingency, the boards of supervisors, acting jointly, without notice or other proceeding of any kind, on October 29, 1915, passed a resolution reciting in substance the fact that the engineer had recommended making the total width of the right of way 120 feet instead of 85 feet, and ordering that the landowners affected should be allowed additional damages, the amount of which being specified in said resolution. On April 11, 1916, appellant filed a petition in the office of the clerk of the district court, reciting, in substance, the matters above stated, and alleging that the proceedings of the respective boards in the matter of establishment of said drainage ditch had not been in conformity to the statutes, that defendants were attempting to deprive him of his property, in violation of the Constitution of Iowa and of the United States, without due process of law, that defendant Walb, who was the contractor doing the work, was about to enter upon his premises for the purpose of excavating the ditch, without authority to do so, and praying a temporary writ restraining the contractor and boards of super[1334]*1334visors from entering upon his premises for the purpose of constructing said ditch, and that upon final hearing the injunction be made permanent. Temporary writ was issued, but,, upon final' hearing, was dissolved, and judgment entered in favor of the defendants.

Plaintiff- appeals from the finding, order, and judgment of the district court dissolving the temporary injunction and rendering judgment in favor of the defendants.

I. Appellant’s principal contention is that an attempt is being made to deprive him of his property without due process of law. He rests this contention upon the claim that the respective boards of supervisors of Kossuth and Emmet Counties/acting jointly, proceeded in the matter of the establishment of the district and the appropriation of' a right'of way over his property without having first acquired jurisdiction to do so.

The report of the engineer appointed by the boards to make the preliminary survey estimated that 94 acres would be required for right of way. The plat filed by him indicated the commencement, route and terminus of the ditch, but neither the report nor the plat contained a statement or designation of the exact boundaries of the land sought to be condemned. Appellant filed a claim for damages in the sum of $15,000. The engineer who made the preliminary survey, with two other freeholders appointed to appraise damages, reported the amount of- damages sustained, including the value of the land taken, by each of the property owners in the district. Appellant was allowed $1,248. Damages were allowed for the value of the land taken at the rate of $140 per acre, from which it appears that something over'8 acres of the right of way were taken from the land of the appellant. The report of the survey made by the engineer and the appraisement of damages were each [1335]*1335approved by tlie boards of supervisors, in joint session, and the improvement finally established. Before the final order of establishment was entered, appellant filed objections thereto, upon the grounds, in substance, that the ditch was not a public necessity; that its establishment would amount to the taking of private property without adequate compensation; that sufficient drainage already existed; and that the boards of supervisors were without jurisdiction to establish the same: but said objections did not point out specifically the defects in the report of the engineer now complained of. The objections of appellant being denied and the improvement established, appellant, in due time, served notice of appeal from the order of establishment to the district court of Kossuth County, but failed to perfect his appeal by filing petition in the office of the clerk of the district court, as required by law. An appeal was also taken by him from the award of damages' and also from the classification of the lands for assessment and the assessment of benefits. Both of these appeals were pending in the court below at the time of the trial of this case.

After the work of excavation had begun, it appeared that, on account of the peculiar condition of the soil and other conditions prevailing, a strip of more than 85 feet in width would be required. The engineer thereupon recommended to the respective boards of supervisors that a further strip of 35 feet in width be appropriated, making the total width of the land proposed to be taken 120 feet. The boards of supervisors, without notice to the property owners or other preliminary action, by resolution approved the recommendation of the engineer, and awarded damages to appellant for the extra land proposed to be taken, at the same rate per> acre, apparently, as previously.

It appears to be conceded by appellant that the proper notice was given the property owners of the petition filed in the office of the county auditor and of the proceedings [1336]*1336for the proposed establishment of the improvement, so that no question of jurisdiction is urged on account of the failure to give the proper notice.

The real question presented is whether the matters complained of were mere irregularities or go directly to the question of jurisdiction. So far as material to the question presented, the drainage statutes provide as follows :

“Sec. 1989-a2. * * * He shall make return of his proceedings to the county auditor, which returns shall set forth the starting point, the route, the terminus or termini of the said ditch or ditches, drain or drains, or.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thorson v. BOARD OF SUPERVISORS OF HUMBOLDT COUNTY
90 N.W.2d 730 (Supreme Court of Iowa, 1958)
Thorson v. Board of Supervisors
90 N.W.2d 730 (Supreme Court of Iowa, 1958)
Mook v. Sioux City
60 N.W.2d 92 (Supreme Court of Iowa, 1953)
Harris v. BOARD OF TRUSTEES, ETC.
59 N.W.2d 234 (Supreme Court of Iowa, 1953)
Husson v. City of Oskaloosa
37 N.W.2d 310 (Supreme Court of Iowa, 1949)
Whisenand v. Van Clark
288 N.W. 915 (Supreme Court of Iowa, 1939)
Baldozier v. Mayberry
285 N.W. 140 (Supreme Court of Iowa, 1939)
Dashner v. Woods Bros. Construction
217 N.W. 464 (Supreme Court of Iowa, 1928)
Thompson v. Board of Supervisors
206 N.W. 624 (Supreme Court of Iowa, 1925)
Hoyt v. Board of Supervisors
202 N.W. 98 (Supreme Court of Iowa, 1925)
Bradley v. Appanoose County
200 N.W. 216 (Supreme Court of Iowa, 1924)
Incorporated Town of Carpenter v. Joint Drainage District No. 6
198 Iowa 182 (Supreme Court of Iowa, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
180 Iowa 1330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simpson-v-board-of-supervisors-iowa-1917.