Simonson v. "U" District Office Building Corp.

422 P.2d 1, 70 Wash. 2d 35, 1966 Wash. LEXIS 885
Washington Supreme Court·Decided December 22, 1966·No. No. 38499·Published·Cited by 6 cases

Opinion

Langenbach, J.

Plaintiffs are architects suing to recover for services performed for defendant corporation. (The Metropolitan Life Insurance Company was a nominal defendant and will not be further mentioned.) Since both parties are appealing they will be referred to by their original designations; plaintiffs will be referred to as Simonson.

The trial was to the court and over a period of days some 117 exhibits were received. We have examined those exhibits and have digested the nearly 800 page statement of facts. There was testimony and proof from which the trial court could have found the following facts and circumstances.

The officers of defendant are Potter, Zabel, and Coppage. Prior to 1957, Potter, Zabel, and one Schmid were the officers of Schmid Construction Company which had constructed a hospital at Burien, near Seattle. In 1958, they incorporated Pioneer Development and Investment Corporation1 which built a hospital at Lakewood, near Tacoma. The contracts between the hospital associations (which owned the hospitals after construction) and the construction companies, required the construction companies to obtain financing and to construct the hospitals. Potter and Zabel handled the financing details and Schmid, an experienced contractor, arranged all phases of construction.

Simonson had been employed to furnish architectural services for both hospitals. He drew such plans and specifications as the general contractor, Schmid, required. Zabel, [37] an attorney, prepared the necessary contracts and performed legal services.

In 1959, Potter and Zabel met Coppage, a realtor, who interested them in building a structure in the University District of Seattle on property upon which he held an option. They agreed to form the defendant corporation and also, in 1959, entered into a construction contract with Pioneer Associates, another corporation owned by Potter and Zabel. (Pioneer Associates seems to have been formed in order to get rid of Schmid’s interests in the various projects. It was not formally incorporated until 1961, and all of the assets of Pioneer Development Corporation were transferred to it.)

In July 1960, Potter, Zabel, Coppage, and Schmid met with Simonson relative to his employment as architect for defendant. On August 3, Simonson delivered a proposed contract of employment, on a standard form, to Zabel. Potter, Zabel, and Schmid were not satisfied with its terms. They wanted to cut Simonson’s fees to 4 per cent of construction costs because he was not expected to perform all of the normal architectural services as had been done on the two prior hospital contracts.

After further discussion the contract was redrafted. There would be no competitive bidding; Schmid would not need detailed plans and specifications as he would be doing the work himself. He would also supervise the work himself. Deletions were accordingly made in paragraphs C(l), (2), and (3) and the contract was finally executed.

Following the execution of the contract, Potter and Zabel had a disagreement with Schmid and the latter had nothing further to do with the construction of defendant’s building. Without Schmid, defendant had no one capable of performing his job as general contractor. Potter then, as representative of his associates and of defendant, informed Simonson that he would have to perform additional functions and provide additional services. Those services were generally, those set forth in paragraphs C(l), and (3) of the contract, which paragraphs had previously been stricken.

[38] Simonson then made extra plans and specifications for competitive bidding from subcontractors. Potter, Zabel, and Coppage were kept informed of progress. Plans and specifications were delivered to them in January 1961. They approved of the plans and instructed Simonson to get subcontractors and bids, and to proceed with the building of the structure.

In May 1961, the Lakewood Hospital had its formal opening and Potter and Zabel terminated their relations with Schmid. (He was finally paid off in July 1961.) John Shelman had been job superintendent under Schmid on the Lakewood Hospital and after Schmid’s disappearance, became construction superintendent of defendant’s building. As such he kept in close touch with Simonson during the construction of the building. He admitted he was not a contractor.

The defendant’s building was to be built as a “loft construction” in which no partitions would be placed until the tenants had been procured and had requested specific partitions. In June 1962, the building was substantially completed with the exception of the partitions. Final costs were computed. (Simonson had been paid certain amounts during the course of construction.) Later a dispute arose between the parties concerning extra services. Simonson filed a lien in June 1963.

Defendant asserted a counterclaim based upon an assignment from the Lakewood Hospital for some $110,000 damages alleged to have been sustained by that hospital because Simonson had not properly procured approval from the State Department of Health, with the result that a portion of that building had to be replaced.

At the conclusion of the trial, the court allowed Simon-son a recovery for certain extras, denied his claim of lien, and dismissed the counterclaim. Both parties have appealed from the resultant judgment.

Defendant alleged 29 assignments of error grounded primarily upon the findings of fact and conclusions of law entered by the trial court. Many of the issues are factual. An examination of the voluminous record disclosed to our [39] satisfaction that there was substantial proof, both oral and documentary, which the trial court was entitled to believe and which sustains the findings of that court.

What was said in Brooks v. Warner, 50 Wn.2d 99, 102, 309 P.2d 757 (1957), is determinative of this phase of the appeal:

The trial court, which had the opportunity to observe the witnesses, chose to believe respondent’s evidence and found that the parties had agreed to share losses as well as profits. We are governed on appeal by the rule that the trial court is better qualified to judge the weight to be given to conflicting testimony than this court. Consequently, the trial court’s findings of fact, entered upon conflicting testimony, will be accepted as the facts of the case, unless we can say that the evidence preponderates against such findings. [Citing cases.] In the case at bar, we cannot say that the evidence preponderates against the trial court’s finding as to the nature of the agreement intended by the parties.

We will now consider the legal arguments brought here by the defendant. Those arguments have been built primarily upon the defendant’s view of the facts, notwithstanding the trial court’s findings. Our decision that there was substantial evidence to support the trial court’s findings confirms those findings as the facts of this case. It is upon the facts as found by the trial court, and not as claimed by defendant, that the law will be applied.

Free access — add to your briefcase to read the full text and ask questions with AI

Simonson v. "U" District Office Building Corp., 422 P.2d 1, 70 Wash. 2d 35, 1966 Wash. LEXIS 885 (Wash. 1966).

422 P.2d 1 (Simonson v. "U" District Office Building Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hoffman v. Reinke Manufacturing Co.
416 N.W.2d 216 (Nebraska Supreme Court, 1987)
Orsi v. AETNA INSURANCE
703 P.2d 1053 (Court of Appeals of Washington, 1985)
Continental Insurance v. Paccar, Inc.
614 P.2d 675 (Court of Appeals of Washington, 1980)
Southwest Washington Production Credit Ass'n v. Seattle-First National Bank
577 P.2d 589 (Court of Appeals of Washington, 1978)
Kreger v. Hall
425 P.2d 638 (Washington Supreme Court, 1967)