Simonson Cashway Co. v. Merickel Construction Co.

391 N.W.2d 903, 1986 Minn. App. LEXIS 4611
CourtCourt of Appeals of Minnesota
DecidedAugust 12, 1986
DocketC6-86-64
StatusPublished
Cited by4 cases

This text of 391 N.W.2d 903 (Simonson Cashway Co. v. Merickel Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simonson Cashway Co. v. Merickel Construction Co., 391 N.W.2d 903, 1986 Minn. App. LEXIS 4611 (Mich. Ct. App. 1986).

Opinion

OPINION

RANDALL, Judge.

This is a mechanics’ lien foreclosure action by Boutin Plumbing & Heating (Bout-in) and Richard Kampa Construction (Kam-pa) involving real estate owned initially by Merickel Construction Company (Merickel) but purchased during the litigation by respondent Simonson Cashway Company (Si-monson), itself a contractor with a mechanic’s lien foreclosure action. That purchase merged the interests of Simonson and Mer-ickel. The trial court granted summary judgment in favor of Simonson, thereby preventing enforcement of appellants’ mechanics’ liens. We reverse and remand.

FACTS

Merickel contracted to sell Sundance Construction Company (Sundance) twelve lots that Merickel owned. Sundance signed a purchase agreement to sell one of those lots to Lloyd Ballman. Sundance agreed to build a house on that lot and contracted with various subcontractors to do the work. Sundance could not deliver marketable title to Ballman and the Sundance/Ballman purchase agreement, by its terms, became null and void. 1 However, before the purchase agreement fell through, the “Ballman house” was erected and included materials supplied by Simonson, Boutin, Kampa, and other suppliers.

Simonson, which supplied materials to the home, began a mechanics lien foreclosure against Merickel, then the fee owner of the subject property; Ballman, “purchaser” of the subject property; and Sun-dance, the general contractor for construction of the Ballman home on the subject property. In that action, Boutin, Kampa, and others timely intervened and that intervention is not at issue on appeal.

At a pre-trial hearing, Sundance’s attorney failed to appear. Pursuant to Simon-son’s motion, Sundance’s answer was stricken and summary judgment entered against Sundance. The trial court also dismissed Sundance’s cross claim against Mer-ickel. During the pendency of this litigation, Simonson purchased Merickel’s interest in the subject property and became the real party in interest.

Simonson settled with Ballman. The trial court dismissed that action with prejudice. Simonson also settled with some of the contractors but not with Boutin and Kampa. Simonson moved by summary judgment for dismissal of the mechanics lien claims of Boutin and Kampa on the grounds that, although Boutin and Kampa had filed mechanics liens, they did not comply with the pre-lien notice statute, Minn. Stat. § 514.011 (1984). Simonson claimed that it owned the property free of the mechanics’ liens. Boutin and Kampa took the position that, as a matter of law, no pre-lien notices were required. The trial court granted Simonson’s motion for summary *905 judgment and Boutin and Kampa appeal. See Minn.R.Civ.App.P. 103.03(a).

ISSUE

Did the trial court properly grant Simon-son’s summary judgment motion against Boutin and Kampa? At the various stages of the proceeding, were Sundance, Ball-man, and Merickel “owners” of the subject property and thus entitled to pre-lien notice, under Minn.Stat. § 514.011, subd. 2, before subcontractors such as Boutin and Kampa could properly maintain a mechanics lien foreclosure action?

ANALYSIS

Summary judgment

shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that either party is entitled to judgment as a matter of law.

Minn.R.Civ.P. 56.03. The moving party has the burden of proof and the non-moving party has the benefit of that view of the evidence most favorable to him. Nord v. Herreid, 305 N.W.2d 337, 339 (Minn.1981). All doubts and inferences must be made in favor of the non-moving party. The court’s function is not to decide issues of fact, but to determine whether there are issues to be tried. Id. at 339.

Without any findings or memorandum, the trial court granted summary judgment in favor of Simonson, in effect finding that the mechanics lien claims of Boutin and Kampa were fatally defective under Minn. Stat. § 514.011, subd. 2. Boutin and Kam-pa argue that summary judgment was improper. Appellants claim that, based on the facts, neither Merickel, Sundance or Ballman were entitled to pre-lien notice, or at least substantial and genuine issues of fact exist as to who is an owner.

First of all, we note that Simonson takes no position as to whether Sundance was ever owed pre-lien notice. Simonson claims that even if Sundance was not owed a pre-lien notice, Ballman and Merickel (Si-monson’s predecessor in interest) were. The dispute arises over interpreting the definition of “owner” in Minn.Stat. § 514.-011, subd. 5 (1984).

Subcontractors must give pre-lien notice to “owners” of property. Minn.Stat. § 514.011, subd. 2. The statute excepts from the notice requirement only subcontractors under direct contract with the “owner.” Id. The pertinent parts of Minn. Stat. § 514.011 are:

Every person who contributes to the improvement of real property so as to be entitled to a lien pursuant to section 514.-01, except a party under direct contract with the owner must, as a necessary prerequisite to the validity of any claim or lien, cause to be given to the owner or his authorized agent, either by personal delivery or by certified mail, not later than 45 days after the lien claimant has first furnished labor, skill or materials for the improvement, a written notice in at least 10-point bold type, if printed, or in capital letters, if typewritten, which shall state:
“Please take notice that persons or companies furnishing labor or materials for the improvement of real property may enforce a lien upon the improved land if they are not paid for their contributions, even if the parties have no direct contractual relationship with the owner. * * ”.

Minn.Stat. § 514.011, subd. 2 (1982).

For the purposes of this section, “owner” means the owner of any legal or equitable interest in real property whose interest in the property (1) is known to one who contributes to the improvement of the real property, or (2) has been recorded or filed for record if registered land, and who enters into a contract for the improvement of the real property.

Id., subd. 5 (emphasis added).

First of all, as to Ballman, the lack of pre-lien notice is irrelevant. Prior to the summary judgment dismissing Boutin and Kampa’s claim, Ballman had backed out of an unrecorded purchase agreement with *906 Sundance because Sundance could not provide marketable title. That agreement became null and void. The trial court accordingly dismissed Sundance’s cross-claim against Ballman. At the time of litigation, Ballman claimed no interest in the property- .

Sundance was not entitled to pre-lien notice for several reasons. First, there is a specific exception for owners who are also contractors like Sundance. See Minn. Stat. § 514.011, subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Wholesale Lumber, Inc. v. Citadel Co.
457 N.W.2d 244 (Court of Appeals of Minnesota, 1990)
PJ Acquisition Corp. v. Skoglund
453 N.W.2d 1 (Supreme Court of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
391 N.W.2d 903, 1986 Minn. App. LEXIS 4611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simonson-cashway-co-v-merickel-construction-co-minnctapp-1986.