Northwest Wholesale Lumber, Inc. v. Citadel Co.

415 N.W.2d 399, 1987 Minn. App. LEXIS 5029
CourtCourt of Appeals of Minnesota
DecidedNovember 24, 1987
DocketC2-87-525
StatusPublished
Cited by3 cases

This text of 415 N.W.2d 399 (Northwest Wholesale Lumber, Inc. v. Citadel Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Wholesale Lumber, Inc. v. Citadel Co., 415 N.W.2d 399, 1987 Minn. App. LEXIS 5029 (Mich. Ct. App. 1987).

Opinion

OPINION

RANDALL, Judge.

In mechanics’ lienholder’s action, the trial court entered judgment in favor of Northwest Wholesale Lumber, Inc. (NWL), Darlis Gray, (doing business as Interiors & Walls' by DAR) (DAR), and Genz-Ryan Plumbing & Heating Co. (Genz-Ryan), all of whom claimed mechanics’ liens against property upon which appellant Builders Finance, Inc. (BFI) held a mortgage. Appellant moved for amended or additional findings of fact and conclusions of law, or for a new trial. The motion was denied. NWL moved for amended findings of fact. The trial 'court granted the motion. BFI appeals the denial of its new trial motion, and the judgment. We reverse and remand.

FACTS

On February 24, 1984, The Citadel Company (Citadel) purchased a parcel of land containing lot 7, the property at issue here.

On February 24, 1984, appellant BFI filed a mortgage, which was executed and delivered on that day by Citadel. Citadel subsequently commenced development of the property. David Nichols, a self-em *401 ployed excavator, testified he commenced “exploratory work,” including digging and removal of trees around February 18, 1984.

Early in 1984, NWL entered into an understanding with Citadel that materials would be shipped as Citadel ordered them, and an invoice sent out for the amount received. NWL did not have a written contract with Citadel. NWL began delivering materials to lot 7 on April 18, 1984. The last shipment was made May 29, 1984.

DAR agreed to wallpaper the dining room and kitchen of the house constructed on lot 7. The work was done on June 24 and 25, 1984. Genz-Ryan began to install heating and plumbing in the house on lot 7 on June 1, 1984. The last date on which Genz-Ryan rendered services on lot 7 was August 28, 1984.

On December 11, 1984, Citadel filed a petition for relief in bankruptcy court. On March 8, 1985, the bankruptcy court entered an order lifting the automatic stay with respect to appellant’s claim on its mortgage. On June 11, 1985, appellant foreclosed on the mortgage. At the foreclosure sale appellant was the purchaser. The property was not redeemed during the redemption period.

In April 1985, NWL commenced a mechanics’ lien action. Genz-Ryan and DAR asserted liens in their crosselaims. Citadel did not appear at trial. The trial court entered judgment for NWL, DAR, and Genz-Ryan against Citadel, and found the rights of these three lienholders to be prior and superior to the interests of all other defendants, including appellant, the mortgagee. The trial court ordered the foreclosure of the liens and the sale of the property to satisfy them.

Appellant moved for amended or additional findings or a new trial. The motion was denied. NWL moved for amended findings, including a finding that NWL’s filing of its lien statement 121 days after the last day of contribution constituted excusable neglect under Minn.R.Civ.P. 6.02, and therefore constituted timely filing. The trial court granted NWL’s motion. BFI appeals the entry of judgment and the denial of its post-trial motions.

ISSUES

1. Did the trial court err by concluding NWL had a valid mechanics’ lien, although the lien statement was filed 121 days after NWL had provided the last service?

2. Was the trial court’s finding that respondents gave the required pre-lien notice clearly erroneous?

ANALYSIS

I.

Late filing of lien statement

Mechanics’ lien laws did not exist under common law, but are created by statute. Armco Steel Corp., Metal Products Division, v. Chicago & North Western Railway Co., 276 Minn. 133, 149 N.W.2d 23 (1967). There must be substantial statutory compliance before liens can be perfected. However, if a construction is permissible that will sustain a lien, it is preferred to one that will invalidate it. Id.

Proof of timeliness of filing is an essential part of the mechanics’ lien claim. Bloomington Electric Co. v. Freeman’s, Inc., 394 N.W.2d 605, 607 (Minn.1986), pet. for rev. denied (Minn. Dec. 17, 1986).

The lien ceases at the end of 120 days after doing the last of the work, or furnishing the last item of skill, material, or machinery, unless within this period,
(1) a statement of claim is filed * * *; and
(2) a copy of the statement is served * * * on the owner or his authorized agent or the person who entered into the contract with the contractor.

Minn.Stat. § 514.08, subd. 1 (Supp.1983).

Appellant contends NWL was not entitled to recover because its mechanics’ lien ceased to exist when its lien statement was not filed within 120 days of the last day on which materials were delivered to lot 7.

NWL contends appellant raised the late notice issue for the first time in its post-trial motion for amended findings, and is therefore precluded from asserting the is *402 sue now. In its complaint, NWL asserted the following:

28. That on the 27th day of September, 1984, within 120 days after furnishing the last time of materials for the improvement of Lot 7, Block 1, Briar Creek Addition, the plaintiff filed * * * its verified Lien Statement * * *.

Appellant contends its answer, which contained an express denial of allegations 14 through 30 of NWL’s complaint, and an affirmative allegation that NWL failed to comply with the provisions of Minn.Stat. §§ 514.01-514.17 (1982 and Supp.1983), sufficiently raised the issue. We agree.

Mechanics’ lien laws are to be liberally construed so as to protect the rights of workers and those who furnish labor and material for the improvement of real estate. Minnesota Wood Specialties v. Mattson, 274 N.W.2d 116, 119 (Minn.1978). However, they must be strictly followed with reference to all requirements upon which the right to a lien depends. Dolder v. Griffin, 323 N.W.2d 773, 780 (Minn. 1982). Timeliness of filing is an essential element the lienholder must prove to establish its claim. Bloomington Electric Co., 394 N.W.2d at 607.

Here, the trial court found NWL made its last contribution on May 29, 1984, and filed its mechanics’ lien statement September 27, 1984. Under Minn.Stat. § 514.08, subd. 1, Northwest Lumber’s lien ceased to exist after September 26, 1984. Lesmeister v. Dilly, 330 N.W.2d 95, 101 (Minn.1983); Hayle Floor Covering, Inc., v. First Minnesota Construction Co., 253 N.W.2d 809

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eischen Cabinet Co. v. Hildebrandt
671 N.W.2d 609 (Court of Appeals of Minnesota, 2003)
Northwest Wholesale Lumber, Inc. v. Citadel Co.
457 N.W.2d 244 (Court of Appeals of Minnesota, 1990)
Klingelhutz v. Woodsmen Construction, Inc.
455 N.W.2d 98 (Court of Appeals of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
415 N.W.2d 399, 1987 Minn. App. LEXIS 5029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-wholesale-lumber-inc-v-citadel-co-minnctapp-1987.