Simons Brick Co. v. Eagle Indemnity Co.

294 P. 1075, 110 Cal. App. 676, 1930 Cal. App. LEXIS 194
CourtCalifornia Court of Appeal
DecidedDecember 27, 1930
DocketDocket No. 6113.
StatusPublished

This text of 294 P. 1075 (Simons Brick Co. v. Eagle Indemnity Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simons Brick Co. v. Eagle Indemnity Co., 294 P. 1075, 110 Cal. App. 676, 1930 Cal. App. LEXIS 194 (Cal. Ct. App. 1930).

Opinion

HOLLZER, J., pro tem.

The above-entitled actions were tried together and the appeals taken from the respective judgments entered therein are presented upon one and the same record. There is no real dispute as to the facts out of which the suits arose.

In March, 1925, one Callahan, as contractor, entered into an agreement with the Los Angeles city school district for the construction of two school buildings, and in connection therewith furnished a bond executed by the defendant, as surety, conditioned for the payment by the said contractor of all materials, etc., used upon said buildings. Said bond recited in part: “If said principal as contractor . . . fails to pay for any material . . . said surety will pay the sum . . . provided that a verified claim or claims shall be filed as required by an act of the Legislature of the State of California entitled, ‘An Act to secure the payment of the claims of persons employed by contractors upon public works, . . . ’ approved May 10, 1919.”

At the time said bond was executed, the act (Stats. 1919, p. 487), referred to therein required that, before an action could be commenced on the bond, the claimant, within the period allowed by law to file claims of mechanics’ liens, must file with the official body by whom the contract had been awarded, a verified statement of his claim showing that the sum due had not been paid.

*678 After the execution of said bond, said act was amended so as to provide that the filing of such a claim should no longer be a condition precedent to commencing an action on the bond, said act becoming effective July 23, 1925 (Stats. 1925, p. 539, sec. 2).

Between April 22 and July 14, 1925, Simons Brick Company, one of the appellants herein, furnished brick which was used on one of the school buildings, and between May 1 and July 21, 1925, furnished brick which was used on the other building, on account of which material a balance of $2,392.33 still remains owing to said company.

On August 26, 1925, R. G. Blessing, the other appellant herein, completed his subcontract for the construction of a tile roof on one of said buildings, on account of which a balance of $375 still remains owing to him.

On October 14, 1925, notice of completion respecting one of said buildings was recorded, and on October 30, 1925, notice of completion of the other building was recorded.

Neither of the appellants herein filed a statement of its or his respective claim with the Los Angeles city school district.

It is conceded that if the amendment which became effective July 23, 1925, is applicable to the claims upon which these actions are being prosecuted, the appellants are entitled to judgments for the respective amounts above mentioned. The trial court, however, held that said amendment was not retroactive and rendered judgment in favor of the defendant.

Appellants contend that the amendment of July 23, 1925, in no way impaired the obligation which defendant assumed under the bond, but merely changed the procedure whereby those entitled to the remedy afforded by the act requiring such bond, might obtain such remedy. Accordingly, it is argued, since the amendment became effective before the expiration of the period within which, under the prior law, they might have been required to file a claim with the official body which had awarded the contract—indeed, the time for filing such claim had not commenced to run as to appellant Blessing on the date the amendment went into effect—the provision under the prior law requiring the filing of such claims did not apply to the claims of the appellants, and hence, they are entitled to recover on the bond.

*679 The respondent, on the other hand, insists that the law, as it stood at the time the bond was executed, including the provision requiring the filing of the claim with the public body which awarded the contract, constituted a part of the obligation of such bond; that legislation relieving a claimant from such requirement with respect to any bond given prior to the enactment of such legislation would result in impairing the obligation of the bond, and hence, would be unconstitutional. Respondent, therefore, contends that the failure of the appellants to file a verified statement of claim, as required by the statute at the time the bond was given, bars any right of recovery herein.

An examination of the authorities convinces us that the contention of the appellant must be upheld.

In Asbestos Mfg. & Supply Co. v. American Bonding Co., 25 Cal. App. 641 [145 Pac. 107], a bond was given pursuant to a statute enacted in 1897 (Stats. 1897, p. 202), requiring that the person seeking relief under the bond shall file with the board of'public works a verified statement of his claim within thirty days from the- time such work is completed, and providing further that suit may be filed by such claimant within ninety days after the filing of such claim. The work involved in that suit had been completed prior to February 26, 1912, but the claim was not filed until April 12, 1912, and the action was commenced July 18, 1912. However, the statute in force at the time of the execution of the bond was subsequently, to wit, in 1911, amended so as to extend the respective periods for the filing of claims and the commencement of suit thereon, and it was conceded that, if the act of 1911 was operative in that case, the claim was filed and likewise the suit was commenced within the proper time.

In the cited case, the bonding company, as here, insisted that the amendatory act should not be construed as being retroactive, and that the provisions of the act in force when the bond was executed should be considered the sole criterion.

The court, however, overruled the contention of the bonding company, upon the theory that a change in remedy, or the time within which it must be sought, does not impair the obligation of a contract, provided an adequate and available remedy be left, and that the amendment in question *680 involved merely a change of that character, citing in support of its conclusion, the cases of National Surety Co. v. Architectural Decorating Co., 226 U. S. 276 [57 L. Ed. 221, 33 Sup. Ct. Rep. 17, see, also, Rose’s U. S. Notes] , Bear Lake v. Garland, 164 U. S. 1 [41 L. Ed. 327, 17 Sup. Ct. Rep. 7], and Kerckhoff-Cuzner Mill Co. v. Olmstead, 85 Cal. 80 [24 Pac. 648],

The first case cited was an action upon a bond given to a school district of Minnesota, conditioned that the general contractor would pay all claims for work, etc., furnished for the completion of a certain school building. On the date when the bond was executed, the law of Minnesota (Rev. Laws 1905, sec. 4539) provided that “No action shall be maintained upon any such bond unless within 90 days after performing the last item of work, or furnishing the last item of . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ogden v. Saunders
25 U.S. 213 (Supreme Court, 1827)
National Surety Co. v. Architectural Decorating Co.
226 U.S. 276 (Supreme Court, 1912)
Oshkosh Waterworks Co. v. Oshkosh
187 U.S. 437 (Supreme Court, 1903)
Colma Vegetable Assn. v. Bonetti
267 P. 172 (California Court of Appeal, 1928)
City of Los Angeles v. Oliver
283 P. 298 (California Court of Appeal, 1929)
Trebilcox v. City of Sacramento
266 P. 1015 (California Court of Appeal, 1928)
Asbestos Manufacturing & Supply Co. v. American Bonding Co.
145 P. 107 (California Court of Appeal, 1914)
Aikins v. Kingsbury
151 P. 145 (California Supreme Court, 1915)
Kerckhoff-Cuzner Mill & Lumber Co. v. Olmstead
24 P. 648 (California Supreme Court, 1890)
People ex rel. Foote v. Clark
119 N.E. 329 (Illinois Supreme Court, 1918)
Grant v. Berrisford
101 N.W. 940 (Supreme Court of Minnesota, 1904)
Architectural Decorating Co. v. National Surety Co.
132 N.W. 289 (Supreme Court of Minnesota, 1911)
Brown v. Staple Cotton Co-operative Ass'n
96 So. 849 (Mississippi Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
294 P. 1075, 110 Cal. App. 676, 1930 Cal. App. LEXIS 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simons-brick-co-v-eagle-indemnity-co-calctapp-1930.