Simacek v. York County Rural Public Power District

370 N.W.2d 709, 220 Neb. 484, 1985 Neb. LEXIS 1124
CourtNebraska Supreme Court
DecidedJuly 19, 1985
Docket84-207
StatusPublished
Cited by9 cases

This text of 370 N.W.2d 709 (Simacek v. York County Rural Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simacek v. York County Rural Public Power District, 370 N.W.2d 709, 220 Neb. 484, 1985 Neb. LEXIS 1124 (Neb. 1985).

Opinions

Boslaugh, J.

The plaintiffs, Albert Simacek, Patty Simacek, and Blanche J. Simacek, are the owners of a quarter section of farmland in Fillmore County, Nebraska. In 1887 Hiram L. Smith, a predecessor in title, conveyed to the Fremont, Elkhorn and Missouri Valley Railroad Company “for the purpose of constructing a Railroad thereon, and for all uses and purposes connected with the construction and use of said Railroad, a strip of land One Hundred feet in width” over and across the land owned by the plaintiffs. The deed provided that in the event the railroad right-of-way was abandoned, it would revert to the grantor, his heirs or assigns.

On April 27, 1967, the Chicago and North Western Railway Company, successor to the Fremont, Elkhorn and Missouri [485]*485Valley Railroad Company, issued a written license to the defendant, York County Rural Public Power District, to construct, maintain, and use an electric power transmission line along the right-of-way. The defendant constructed a powerline on the railroad right-of-way in 1967, which is a part of the transmission system of the defendant. The defendant did not obtain the consent of the plaintiffs to construct and operate the line, and the plaintiffs made no protest or objection to such construction and commenced no litigation concerning the line until this lawsuit was filed.

Subsequently, the Chicago and North Western Railway Company conveyed the right-of-way to the Great Plains Railway Company, which abandoned the right-of-way and removed its trackage in May 1976. The defendant has continued to maintain and operate the power line.

On March 2,1983, the plaintiffs commenced this action for a declaratory judgment as to the parties’ rights with respect to the property, to recover possession of the property, and for an injunction to compel the defendant to remove its transmission line and poles from the property. The defendant cross-petitioned, claiming a prescriptive easement. The trial court found generally for the defendant. The plaintiffs have appealed.

This being an equitable action, we review the record de novo and reach an independent conclusion without reference to the findings of the trial court. Steinfeldt v. Klusmire, 218 Neb. 736, 359 N.W.2d 81 (1984).

The issue before the court is whether the defendant acquired a prescriptive easement to maintain the powerline on plaintiffs’ property.

The law treats a claim of prescriptive right with disfavor, and, accordingly, such a claim requires that the elements of such adverse user be clearly, convincingly, and satisfactorily established. Grint v. Hart, 216 Neb. 406, 343 N.W.2d 921 (1984); Gerberding v. Schnakenberg, 216 Neb. 200, 343 N.W.2d 62 (1984). A party claiming a prescriptive easement must show that his user was exclusive, adverse, under a claim of right, continuous and uninterrupted, and open and notorious for the full 10-year prescriptive period. In order for the [486]*486defendant to succeed in its claim, the necessary elements must have been clearly, convincingly, and satisfactorily established since March of 1973. The record shows this was not accomplished.

It is well established that a permissive use is not adverse and cannot ripen into an easement. Fischer v. Grinsbergs, 198 Neb. 329, 252 N.W.2d 619 (1977). The general rule is that if a use begins as a permissive one, it retains that character until notice that the use is claimed as a matter of right is communicated to the owner of the servient estate. Gerberding, supra.

In Svoboda v. Johnson, 204 Neb. 57, 64-65, 281 N.W.2d 892, 898 (1979), it was explained:

The fourth element required to prove a prescriptive easement is that the claimant’s use was under a claim of right, such that there is no recognition of the right of the owner of the servient tenement to stop the use. In Barnes v. Milligan, 196 Neb. 50, 241 N.W.2d 508 (1976), we quoted from 3 Am. Jur. 2d, Adverse Possession, § 96, p. 177, with reference to the meaning of “claim of right,” as follows: “ ‘Terms such as “claim of right,” “claim of title,” and “claim of ownership,” when used in this connection, mean nothing more than the intention of the disseisor to appropriate and use the land as his own to the exclusion of all others, irrespective of any semblance or shadow of actual title or right. * * * Thus, “claim of right” means no more than “hostile” and if possession is hostile it is “under a claim of right.” ’ ”

See, also, Weiss v. Meyer, 208 Neb. 429, 303 N.W.2d 765 (1981).

The record shows that the defendant went into possession with the permission of the railroad company, which had the right to possession of the right-of-way, and did not maintain or use its electric transmission line under a claim of right prior to the railroad’s abandonment of the right-of-way. In its answer and cross-petition the defendant alleged:

That said defendant constructed an electric transmission line in 1967 along and upon approximately seven miles of railroad right of way including the railroad right of way across the Northeast Quarter (NEV4) of Section 20, Township 7 North, Range 2 West, in Fillmore [487]*487County, Nebraska, after first complying with all provisions of Nebraska law, and after entering into an agreement with the Chicago and North Western Railway Company dated April 27, 1967, which authorized the defendant to construct and maintain an electric transmission line upon said railroad right of way ....
That the defendant in constructing said electric transmission line relied upon the representations of the Chicago and Northwestern [sic] Railway Co. that it had full legal authority to permit the defendant to construct said electric transmission line; the defendant paid the sum of $10,000.00 to the said Chicago and Northwestern [sic] Railway Co. as consideration for its granting authority and permission to construct and maintain the electric transmission line upon the railroad right of way.

The defendant’s use of the property was permissive and not under a claim of right until at least May 1976, when the railroad abandoned the right-of-way.

The defendant argues that the railroad could not grant permission for the construction, maintenance, and use of an electric transmission line upon the right-of-way because such use was not consistent with its easement. Therefore, the defendant concludes, its use of the right-of-way was adverse to the plaintiffs from its inception. The argument ignores the fact that from April of 1967 to May of 1976 the defendant made no claim other than it was upon the right-of-way with permission. As has been stated repeatedly by this court,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fyfe v. Tabor Turnpost
Nebraska Court of Appeals, 2015
Sjuts v. GRANVILLE CEMETARY ASS'N
719 N.W.2d 236 (Nebraska Supreme Court, 2006)
Whipps Land & Cattle Co. v. Level 3 Communications, LLC
658 N.W.2d 258 (Nebraska Supreme Court, 2003)
Lake Arrowhead, Inc. v. Jolliffe
639 N.W.2d 905 (Nebraska Supreme Court, 2002)
Dowd v. City of Omaha, Douglas County
520 N.W.2d 549 (Nebraska Court of Appeals, 1994)
Western Fertilizer & Cordage Co. v. City of Alliance
504 N.W.2d 808 (Nebraska Supreme Court, 1993)
State v. Union Pacific Railroad
490 N.W.2d 461 (Nebraska Supreme Court, 1992)
Werner v. Schardt
382 N.W.2d 357 (Nebraska Supreme Court, 1986)
Simacek v. York County Rural Public Power District
370 N.W.2d 709 (Nebraska Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
370 N.W.2d 709, 220 Neb. 484, 1985 Neb. LEXIS 1124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simacek-v-york-county-rural-public-power-district-neb-1985.