Siluria (Assignment for the Benefit of Creditors), LLC v. Lummus Technology LLC
This text of Siluria (Assignment for the Benefit of Creditors), LLC v. Lummus Technology LLC (Siluria (Assignment for the Benefit of Creditors), LLC v. Lummus Technology LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
In The
Court of Appeals
Ninth District of Texas at Beaumont
________________
NO. 09-23-00127-CV ________________
SILURIA (assignment for the benefit of creditors), LLC, Appellant
V.
LUMMUS TECHNOLOGY LLC, Appellee ________________________________________________________________________
On Appeal from the 284th District Court Montgomery County, Texas Trial Cause No. 21-03-03166-CV ________________________________________________________________________
MEMORANDUM OPINION
The underlying litigation arises from a dispute over which party is entitled to
a $1.5 million “holdback contingency” deposited in an escrow fund when Lummus
Technology LLC (“Lummus”) purchased Siluria (assignment for the benefit of
creditors), LLC’s (“Siluria ABC”) assets. Following a jury trial where the jury
answered the sole question in favor of Lummus, the trial court’s judgment awarded
Lummus: $1,495,493.10 to be paid from the court’s registry representing the
holdback contingency, past attorney’s fees of $467,144.50, conditional appellate
1 attorney’s fees, and post-judgment interest. In five issues, Siluria ABC appeals the
trial court’s judgment for Lummus. As discussed more fully below, we affirm the
trial court’s judgment.
I. BACKGROUND
The assets purchased by Lummus from Siluria ABC included a
“demonstration unit” set up under a lease agreement on Braskem America, Inc.’s
(“Braskem”) premises in La Porte, Texas.1 This demonstration unit employed a new
oxidative coupling technology (“OCM”) that allegedly could be used in
manufacturing plastics. Critical to this appeal’s resolution is what the
“demonstration unit” encompasses, and whether the parties’ Escrow Agreement was
ambiguous, which was executed at the same time as the parties’ Asset Purchase
Agreement (“APA”). Neither the APA nor the Escrow Agreement defined the
phrases “begun removing” or “demonstration unit.” Both agreements provided for a
“holdback contingency” related to the demonstration unit.
The parties’ agreed terms included Lummus paying $8.5 million for all Siluria
ABC’s assets, with $7 million paid at closing and $1.5 million in a “holdback
contingency” that Lummus paid into an escrow account. Under the Escrow
Agreement, the $1.5 million would be paid to Siluria ABC upon the earlier of: (1)
Lummus and Braskem entering a lease agreement and site services agreement in
1Braskem is not a party to the litigation.
2 accordance with Section 2.1 of the APA to be able to operate the demonstration unit
at Braskem’s facility; or (2) the sixth (6th) month anniversary of the Closing (as
defined in the APA), if by that time Lummus had not begun removing the
demonstration unit from Braskem’s facility. If neither of those events occurred,
Lummus would receive the $1.5 million escrow fund. In other words, if Lummus
failed to enter the described lease with Braskem or if it began removing the
demonstration unit by the six (6th) month anniversary of Closing, the $1.5 million
would be returned to Lummus that it had paid into escrow. It is undisputed that
Lummus failed to enter a lease with Braskem to operate the demonstration unit on
its premises.
A. Parties’ Relationship, Negotiations and Agreements
In May 2019, Siluria ABC sent Lummus a form APA, and the parties
exchanged red-lined versions of these agreements negotiating the terms. Per the
Escrow Agreement and APA, the total purchase price for the assets covered was $8.5
million with $7 million of that paid to Siluria ABC at closing and the remaining $1.5
million designated as a “Holdback Contingency” (“the Holdback”) paid by Lummus
into an escrow account at closing. Which party received the $1.5 million Holdback
from the escrow fund was conditioned on certain events as laid out in the parties’
agreements. The parties executed both agreements on July 15, 2019.
3 The APA provided:
2. PURCHASE PRICE; PAYMENTS.
2.1 Purchase Price. In consideration of the sale, transfer, conveyance and assignment of all of the Purchased Assets to Buyer at the Closing, Buyer shall, as of the Closing, assume only those liabilities, if any, expressly set forth as Assumed Liabilities in Section 3.1 of this Agreement and shall pay to Seller, in the manner stated below, the sum of Eight Million, Five Hundred Thousand U.S. Dollars (US $8,500,000) in cash (the “Purchase Price”), as follows: a. Seven Million U.S. Dollars ($7,000,000 Million U.S. Dollars) by wire trans[]fer at Closing; and b. One Million, Five Hundred Thousand U.S. Dollars (US $1,500,000) (the “Holdback”) shall be paid by Buyer at Closing to an escrow/trust account, such amounts to be released to Seller upon satisfaction of the Holdback Contingency. For the purposes of this Agreement, the “Holdback Contingency” shall mean that Buyer is able to conclude a lease and site services agreement with Braskem America Inc. (“Braskem”) to be able to operate the demonstration unit included in the Purchased Assets at Braskem’s LaPorte facility on material terms which are substantially the same as those granted to Assignor in its lease and site services with Braskem dated December 5, 2013 and also including that Braskem would provide in the Buyer’s lease a full immunity and hold harmless to Buyer and its affiliates for any environmental issues existing prior to Buyer entering into the lease with Braskem for the leased property, including any caused by Assignor. As a requirement for Buyer to enter into the lease with Braskem, a Phase II Environmental Assessment must be conducted on the leased property with such results to be reasonably satisfactory to Buyer. The Holdback shall be paid to Seller in its entirety upon the earlier to occur of the following events: a. The date on which Buyer and Braskem have entered into a lease agreement on the terms stated above to be able to operate the demonstration unit at Braskem’s Laporte facility; or
4 b. The sixth (6th) month anniversary of the Closing if, by such date, Buyer has not begun removing the demonstration unit from Braskem’s facility. If neither event occur[s], the entire amount of the Holdback shall be returned to Buyer.
Likewise, Section 3 of the Escrow Agreement provided:
3. Escrow Agent’s Duties and Authority to Act. The Escrow Agent is hereby authorized and directed to deliver the Escrow Fund in the amount of $1,500,000.00 by wire transfer of immediately available funds to an account designated in writing by Seller or Buyer, as applicable, to: a) Seller, upon the earlier to occur of the following events: ii. The date on which Buyer and Braskem America Inc. (“Braskem”) have entered into a lease agreement and the site services agreement in accordance with the requirements set forth in Section 2.1 of the Purchase Agreement to be able to operate the demonstration unit at Braskem’s LaPorte facility; or ii. The sixth (6th) month anniversary of the Closing (as defined in the Purchase Agreement) if, by such date, Buyer has not begun removing the demonstration unit from Braskem’s facility. b) Buyer, if neither event set forth in a) i. or ii. above occurs.
The sixth-month anniversary of closing fell on January 15, 2020.
B. Lawsuit and Procedural Posture
After the parties closed, Lummus was unable to secure a lease with Braskem
as described in the APA to operate the demonstration unit on its premises, and by
December 2019, Braskem would no longer allow Lummus on-site. However, after
the parties closed and while simultaneously attempting to negotiate a lease with
Free access — add to your briefcase to read the full text and ask questions with AI
In The
Court of Appeals
Ninth District of Texas at Beaumont
________________
NO. 09-23-00127-CV ________________
SILURIA (assignment for the benefit of creditors), LLC, Appellant
V.
LUMMUS TECHNOLOGY LLC, Appellee ________________________________________________________________________
On Appeal from the 284th District Court Montgomery County, Texas Trial Cause No. 21-03-03166-CV ________________________________________________________________________
MEMORANDUM OPINION
The underlying litigation arises from a dispute over which party is entitled to
a $1.5 million “holdback contingency” deposited in an escrow fund when Lummus
Technology LLC (“Lummus”) purchased Siluria (assignment for the benefit of
creditors), LLC’s (“Siluria ABC”) assets. Following a jury trial where the jury
answered the sole question in favor of Lummus, the trial court’s judgment awarded
Lummus: $1,495,493.10 to be paid from the court’s registry representing the
holdback contingency, past attorney’s fees of $467,144.50, conditional appellate
1 attorney’s fees, and post-judgment interest. In five issues, Siluria ABC appeals the
trial court’s judgment for Lummus. As discussed more fully below, we affirm the
trial court’s judgment.
I. BACKGROUND
The assets purchased by Lummus from Siluria ABC included a
“demonstration unit” set up under a lease agreement on Braskem America, Inc.’s
(“Braskem”) premises in La Porte, Texas.1 This demonstration unit employed a new
oxidative coupling technology (“OCM”) that allegedly could be used in
manufacturing plastics. Critical to this appeal’s resolution is what the
“demonstration unit” encompasses, and whether the parties’ Escrow Agreement was
ambiguous, which was executed at the same time as the parties’ Asset Purchase
Agreement (“APA”). Neither the APA nor the Escrow Agreement defined the
phrases “begun removing” or “demonstration unit.” Both agreements provided for a
“holdback contingency” related to the demonstration unit.
The parties’ agreed terms included Lummus paying $8.5 million for all Siluria
ABC’s assets, with $7 million paid at closing and $1.5 million in a “holdback
contingency” that Lummus paid into an escrow account. Under the Escrow
Agreement, the $1.5 million would be paid to Siluria ABC upon the earlier of: (1)
Lummus and Braskem entering a lease agreement and site services agreement in
1Braskem is not a party to the litigation.
2 accordance with Section 2.1 of the APA to be able to operate the demonstration unit
at Braskem’s facility; or (2) the sixth (6th) month anniversary of the Closing (as
defined in the APA), if by that time Lummus had not begun removing the
demonstration unit from Braskem’s facility. If neither of those events occurred,
Lummus would receive the $1.5 million escrow fund. In other words, if Lummus
failed to enter the described lease with Braskem or if it began removing the
demonstration unit by the six (6th) month anniversary of Closing, the $1.5 million
would be returned to Lummus that it had paid into escrow. It is undisputed that
Lummus failed to enter a lease with Braskem to operate the demonstration unit on
its premises.
A. Parties’ Relationship, Negotiations and Agreements
In May 2019, Siluria ABC sent Lummus a form APA, and the parties
exchanged red-lined versions of these agreements negotiating the terms. Per the
Escrow Agreement and APA, the total purchase price for the assets covered was $8.5
million with $7 million of that paid to Siluria ABC at closing and the remaining $1.5
million designated as a “Holdback Contingency” (“the Holdback”) paid by Lummus
into an escrow account at closing. Which party received the $1.5 million Holdback
from the escrow fund was conditioned on certain events as laid out in the parties’
agreements. The parties executed both agreements on July 15, 2019.
3 The APA provided:
2. PURCHASE PRICE; PAYMENTS.
2.1 Purchase Price. In consideration of the sale, transfer, conveyance and assignment of all of the Purchased Assets to Buyer at the Closing, Buyer shall, as of the Closing, assume only those liabilities, if any, expressly set forth as Assumed Liabilities in Section 3.1 of this Agreement and shall pay to Seller, in the manner stated below, the sum of Eight Million, Five Hundred Thousand U.S. Dollars (US $8,500,000) in cash (the “Purchase Price”), as follows: a. Seven Million U.S. Dollars ($7,000,000 Million U.S. Dollars) by wire trans[]fer at Closing; and b. One Million, Five Hundred Thousand U.S. Dollars (US $1,500,000) (the “Holdback”) shall be paid by Buyer at Closing to an escrow/trust account, such amounts to be released to Seller upon satisfaction of the Holdback Contingency. For the purposes of this Agreement, the “Holdback Contingency” shall mean that Buyer is able to conclude a lease and site services agreement with Braskem America Inc. (“Braskem”) to be able to operate the demonstration unit included in the Purchased Assets at Braskem’s LaPorte facility on material terms which are substantially the same as those granted to Assignor in its lease and site services with Braskem dated December 5, 2013 and also including that Braskem would provide in the Buyer’s lease a full immunity and hold harmless to Buyer and its affiliates for any environmental issues existing prior to Buyer entering into the lease with Braskem for the leased property, including any caused by Assignor. As a requirement for Buyer to enter into the lease with Braskem, a Phase II Environmental Assessment must be conducted on the leased property with such results to be reasonably satisfactory to Buyer. The Holdback shall be paid to Seller in its entirety upon the earlier to occur of the following events: a. The date on which Buyer and Braskem have entered into a lease agreement on the terms stated above to be able to operate the demonstration unit at Braskem’s Laporte facility; or
4 b. The sixth (6th) month anniversary of the Closing if, by such date, Buyer has not begun removing the demonstration unit from Braskem’s facility. If neither event occur[s], the entire amount of the Holdback shall be returned to Buyer.
Likewise, Section 3 of the Escrow Agreement provided:
3. Escrow Agent’s Duties and Authority to Act. The Escrow Agent is hereby authorized and directed to deliver the Escrow Fund in the amount of $1,500,000.00 by wire transfer of immediately available funds to an account designated in writing by Seller or Buyer, as applicable, to: a) Seller, upon the earlier to occur of the following events: ii. The date on which Buyer and Braskem America Inc. (“Braskem”) have entered into a lease agreement and the site services agreement in accordance with the requirements set forth in Section 2.1 of the Purchase Agreement to be able to operate the demonstration unit at Braskem’s LaPorte facility; or ii. The sixth (6th) month anniversary of the Closing (as defined in the Purchase Agreement) if, by such date, Buyer has not begun removing the demonstration unit from Braskem’s facility. b) Buyer, if neither event set forth in a) i. or ii. above occurs.
The sixth-month anniversary of closing fell on January 15, 2020.
B. Lawsuit and Procedural Posture
After the parties closed, Lummus was unable to secure a lease with Braskem
as described in the APA to operate the demonstration unit on its premises, and by
December 2019, Braskem would no longer allow Lummus on-site. However, after
the parties closed and while simultaneously attempting to negotiate a lease with
Braskem, Lummus entered Braskem’s facility on two occasions to remove some of
5 the purchased assets. On October 2, 2019, “Lummus removed documents,
computers, maintenance tools and spare parts[.]” On November 5, 2019, Lummus
removed “remaining documents, instruments, spare parts, safety equipment,
maintenance tools, test equipment, golf cart, catalyst samples, and computer
hardware.”
On January 9, 2020, Lummus sent a letter to the Escrow Agent and Siluria
ABC demanding return of the Holdback, stating that given Braskem’s unwillingness
to enter a lease agreement, “Lummus was forced to begin the removal process for
assets related to the demonstration unit from Braskem’s Laporte facility in
preparation of a lease agreement not being reached.” On January 17, 2020, Siluria
ABC responded and disputed Lummus’s entitlement to the Holdback. Specifically,
Siluria ABC claimed that Lummus “did not by January 15, 2020, begin removing
the demonstration unit” and that “[a]ny actions that [Lummus] may have taken as
described in the January 9, 2020 letter to [begin the removal process for assets related
to the ‘demonstration unit’ were insufficient to meet the actual requirement under
Section 2.1 of the [APA].” Therefore, Siluria ABC claimed that the “Holdback
Contingency” in Section 3(a)(ii) of the Escrow Agreement was satisfied, and it was
entitled to the $1.5 million.
Having received competing demands for the escrow fund, on March 9, 2021,
the Escrow Agent filed its Original Petition for Interpleader seeking to deposit the
6 funds into the court’s registry. Lummus subsequently answered the interpleader
action and cross-claimed against Siluria ABC for breach of contract, declaratory
judgment, and attorney’s fees. Specifically, Lummus claimed that Siluria ABC
breached the Escrow Agreement and as relevant here, sought declarations that it
“began removing the demonstration unit from Braskem’s facility before January 15,
2020, as set out in Section 3(a)(ii) of the Escrow Agreement[,]” and that it is “entitled
to the full amount of the Escrow Fund because neither event in Section 3(a)(i) or (ii)
of the Escrow Agreement occurred.” Siluria ABC likewise answered the interpleader
and cross-claimed against Lummus for breach of contract, declaratory judgment, and
attorney’s fees. Siluria ABC claimed that Lummus breached the Escrow Agreement
and sought declarations that (1) “Lummus had not begun removing the
demonstration unit from Braskem’s facility” by the deadline as stated in the Escrow
Agreement, and (2) “Siluria ABC is entitled to the full amount of the Escrow Fund
because at least the event in Section 3(a)(ii) of the Escrow Agreement occurred.” In
May 2021, the parties filed an Agreed Motion to Interplead the Funds into the
Registry of the Court, Award Attorneys’ Fees, and to Dismiss Stibbs & Co., PC (the
“Escrow Agent”), which the trial court granted.
In April 2022, the parties filed competing motions for summary judgment
regarding the Escrow Agreement’s construction. In essence, Lummus asserted that
the “demonstration unit” encompassed “all the instruments, parts, and equipment
7 necessary to operate the unit[.]” In contrast, Siluria ABC contended the phrase
“demonstration unit” in the parties’ Escrow Agreement refers “only to the four-story
industrial [s]tructure at Braskem’s Facility.”
Lummus also argued that “begin” in the parties’ agreement is undefined and
should be given its plain, ordinary meaning, and that Siluria ABC took an
unreasonably narrow definition of “demonstration unit” in that it wanted to limit the
definition to only the four-story structure. Siluria ABC contended Lummus’s
definition of “demonstration unit” was overly broad.
In May 2022, the trial court granted Siluria ABC’s Motion for Summary
Judgment. In July 2022, Lummus filed its Motion for Reconsideration, Motion to
Vacate Portion of Summary Judgment Order, and Request for Oral Hearing on
Same. Lummus asserted that there were genuine issues of material fact about the
meaning of “demonstration unit.” Lummus contended that despite Siluria ABC’s
contention the agreement was unambiguous, Siluria ABC relied on “the external
testimony of Siluria ABC’s and Lummus’ corporate representatives, and other
external contracts, in seeking to establish its definition of ‘demonstration unit.’”
Lummus noted the parties’ contradictory summary-judgment evidence, Siluria
ABC’s limiting the definition to the “four-story structure[,]” and Lummus’s
definition that included all assets needed for the unit to operate. In August 2022, the
trial court granted Lummus’s Motion for Reconsideration and vacated its prior
8 summary judgment order in part. The trial court determined that the issues would be
tried to a jury. In January 2023, the trial court signed an “Order Clarifying ‘Order
Granting Lummus Technology LLC’s Motion for Reconsideration and Motion to
Vacate Portion of Summary Judgment Order.’” In the Order Clarifying, the trial
court explained that “no pleaded claims or affirmative defenses have been disposed
of in this case and all pleaded claims and affirmative defenses are live issues for
trial.” In vacating its prior summary-judgment order, the trial court reasoned that
“demonstration unit” was an undefined term in the agreement, “making an ambiguity
argument possible on appeal.”
Before trial, Lummus filed an Unopposed Motion to Designate it as Plaintiff
for Trial, which the trial court granted. The parties also agreed to try the issue of
attorney’s fees to the bench by submitting affidavits, after the jury’s verdict.
C. Trial Evidence of Negotiations and the Parties’ Intentions
Three witnesses testified at trial: Will Groten for Lummus; Ian Rubin from
Braskem via deposition; and William Trento for Siluria ABC. The documentary
evidence included the APA with its exhibits, Escrow Agreement, red-lined versions
of the APA, photographs, demand letters, and various emails from the parties and
Braskem.
9 Will Groten’s Testimony
Will Groten (“Groten”) is Lummus’s Chief Innovation Officer and negotiated
the purchase of assets from Siluria ABC. He described Lummus as a company that
helps develop technologies it could license to markets around the world, which they
do by acquiring partially developed intellectual property ideas. In 2018, Siluria
Technology, LLC (“Siluria Tech”) approached Lummus, because it needed
additional equity investors. At that time, Groten viewed the assets when he toured
the La Porte facility. Although Lummus decided not to invest in Siluria Tech,
Lummus thought they could eventually acquire the assets and intellectual property
“in a bankruptcy scenario.”
Groten explained that in 2019, instead of Lummus completing the deal
directly with Siluria Tech, Siluria Tech chose to enter the “ABC process.”2 Groten
testified that it made “sense for us to pursue acquiring the technology and its assets
. . . so we engaged with Siluria ABC to conclude an Asset Purchase Agreement.”
Groten viewed Siluria ABC’s sale of assets “as a fast-track liquidation sale[,]” and
explained that “Siluria wanted as much money as they could get, but speed was of
the essence as well.” Before purchase, Lummus accessed Siluria ABC’s “data
room,” which included information like a fixed asset sheet, patents, capital projects,
2The record shows that “ABC” referred to the “assignment for the benefit of
creditors” process, which was described as a similar alternative to bankruptcy available to California entities. 10 the Braskem lease agreement, the site services agreement, and the license agreement
for Braskem to use the OCM technology. Groten understood Lummus was buying
(1) the intellectual property represented in all the patents, (2) the physical assets that
included the lab equipment in California and all the catalysts, and (3) the
demonstration unit at La Porte, Texas.
Groten explained that when you do research and development in the chemical
engineering space, the purpose of a demonstration unit is the last step in developing
a new technology and is “a complex set of assets . . . that have to be operated in a
chemical plant environment to prove that the technology does what . . .it says it’s
supposed to do, but it’s also that it can be operated in a chemical plant environment.”
Groten testified that Lummus understood that the demonstration unit at La Porte was
integrated into Braskem’s chemical plant operations, as reflected in the site lease and
site services agreements between Braskem and Siluria Tech. Those documents were
referenced in the APA, and Groten testified the Braskem-Siluria Tech lease showed
it allowed Siluria Tech to bring assets and equipment to Braskem’s facility for the
purpose of demonstrating the OCM technology in “a real operating environment of
the Braskem chemical plant.”
Groten testified about the APA process with Siluria ABC, and the
requirements that the full $1.5 million would be given to the Seller if Lummus
entered a lease with Braskem on the same material terms as the Siluria Tech lease
11 plus Lummus would not assume any environmental liabilities. Groten also discussed
the APA’s holdback contingency and why it was included. He explained that the
events they negotiated determined whether the escrow fund would be returned to
Lummus or belonged to Siluria ABC. He said they “captured the essence of both
parties’ needs:” Lummus wanting a demonstration unit capable of operating at the
Braskem site and Siluria ABC’s need to bring the valuation determination to a
conclusion in a six-month period. Groten testified the instructions in the Escrow
Agreement match the holdback contingency in the APA, and if neither event
occurred, then the money is returned to the Buyer. Groten testified that the $1.5
million holdback was the value assigned for a demonstration unit capable of
operating rather than the cost to remove the unit. Groten testified that besides the
fixed asset value, the holdback contingency “valued the demonstration unit capable
of operating at Braskem at $1.5 million.”
The first event related to the contingency was whether Lummus could enter a
lease with Braskem under the same terms Siluria Tech had and to be able to operate
the demo unit at Braskem’s La Porte facility. Groten began negotiating a lease and
site services agreement with Ian Rubin from Braskem, but he learned in September
2019, it was unlikely that Lummus would get a lease on the same material terms as
the Siluria Tech lease. Even so, Lummus and Braskem were interested in continuing
negotiations. The parties did not dispute that Lummus was unable to enter such a
12 lease with Braskem, because, according to Groten, “Braskem made a business
decision that they did not want to continue to host the unit there.”
Groten testified the parties negotiated the second event in the holdback
contingency “because of the Siluria ABC desire for a timely resolution of the value
that Lummus would get from the demonstration unit[,]” which was written as
“whether or not we have begun removing the demonstration unit from Braskem’s
facility.” Groten testified the parties negotiated the “begun removing” language
because, although Siluria ABC initially wanted Lummus to complete removal within
six months, Groten knew “that threshold was impossible to achieve.” Therefore,
Groten said, “I negotiated a very, very low threshold of beginning to remove, as I
thought that was something that we could practically achieve in a six-month
window.” Groten also outlined the complexity of removing the demonstration unit
from an operating chemical plant that would make it impossible to complete in six
months, including environmental and safety issues. He described the removal
process, beginning with the decision to begin removal followed by sending staff
familiar with demonstration units in
to remove those items that you can easily remove and secure to make the unit inoperable. So you would remove computers and you would remove all documentation. You would remove the spare parts. You would remove the catalysts and anything else that was easily removed within the capabilities of our people and bring them to our site.
13 Groten noted they would simultaneously make sure they understood Braskem’s
requirements for having third-party contractors on site, then have several contractors
to review what it would take to completely remove all the assets, including
disassembly of the four-story structure.
Groten testified that once Braskem verbally indicated Lummus would not get
the same terms, Lummus began running “parallel path type activities . . . to begin
the process of preparing to move the demonstration unit.” This included Groten’s
staff removing certain assets in early October. He explained Lummus’s intent in
removing the assets: first, they took things that they could remove easily; second,
they wanted to secure them, because they contained confidential technical
information; and third, they were aware of the criteria they had to begin removing
before the six-month date. Groten testified that on October 1, 2019, Lummus reached
out to Braskem, because they “were looking to begin removal of critical items . . .
that are integral to the demonstration unit, and that included these computers and
small critical items at . . . the La Porte facility.” When Lummus entered the APA
and Groten negotiated the term to begin removing, he had this whole process in
mind. The APA required Lummus to begin removing by the six-month anniversary
of closing, which they did when his staff went to Braskem on two occasions and
removed assets they acquired from the site, rendering the unit incapable of operating
safely, and brought them to Lummus’s facility. Along with removing those items,
14 before the January 15, 2020, deadline, Lummus contacted three third-party
contractors with the skill set to complete the removal and began asking Braskem for
permission to bring them on-site so they could get a quote on complete removal.
Groten explained that he chose three people to retrieve items from Braskem,
specifically “because they have a very clear understanding of what a demonstration
unit is and the complexities and . . . how demonstration units operate[]” and “were
very knowledgeable about the types of equipment that would be there, the safety
protocols to go into a plant like that, to assess what can be safely and easily
removed[.]” Groten described how the demonstration unit worked and specifically
that the unit was “integrated into the larger chemical plant[,]” meaning “it shared a
control room, and the control room is connected via wires to all of the instruments
and the pumps, the valves, everything that controls the temperatures, the pressures,
the flow rates of the chemical processes, including all emergency equipment[.]” He
testified the unit had emergency shutdown logic integrated into the software that
controls the unit for safety purposes. Groten explained that you needed the control
room to run the OCM process, which was “connected via electrical and signaling
wires to various components.” He testified the control room contained “sophisticated
computers” typically referred to as “DCS, digital control systems” which monitor
everything going on in the various pieces of equipment, like pressures, temperatures,
15 and flow rates; it also controls the valves, pumps, and motors and contains
“emergency shutdown logic.”
Groten said that chemical analyzers in the control room and in the structure
which were “important to understand what was happening inside the pipes in the
catalyst” and “it’s essential . . . to have a unit capable of operating.” Among other
things, Groten discussed photographs of items in the control room, including
computers, and catalysts adjacent to the “four-story structure.” He testified that the
computer taken from the control room analyzed data coming from DCS system
signals, and the unit could not operate safely without the computer. Groten also
testified that the catalysts were required for the OCM process.
Groten explained that in the APA, the language was meant to be
“comprehensive” given the demonstration of technology and was written “to be
almost a catchall because what you don’t want is something to disappear or to be
argued about that it wasn’t included in the . . . Asset Purchase Agreement.” Groten
testified that Bill Trento from Sherwood Partners was involved in the APA
negotiations. Groten led the APA negotiations for Lummus with assistance from
inside counsel. Per the APA, the total purchase price for the assets covered was $8.5
million with $7 million of that “upfront.” Groten testified that the $7 million covered
all the assets including the intellectual property “but it did not include . . . a
demonstration unit capable of operating at the Braskem La Porte facility.” Groten
16 said the value of that asset was contingent upon the terms under which Lummus
could continue to operate that demonstration unit at the Braskem La Porte facility.
That value is reflected in the APA as the $1.5 million paid by the Buyer at closing
to an escrow account, and those amounts would be released to the Seller upon
satisfaction of the holdback contingency. Groten testified that Lummus’s intent was
the $1.5 million “covered the value of having an operating demonstration plant at
Braskem La Porte without the environmental liabilities of prior occupants.” Also
included in the $1.5 million was technical documentation essential for operating the
demonstration unit, data associated with past operation of the demo unit, catalysts
that embodied the IP in a physical form, and all of those “constituted . . . a
demonstration unit capable of operating at Braskem La Porte.”
According to Groten, Lummus knew what was included in the demonstration
unit capable of operating at the Braskem facility “through a combination of on-site
inspection, plus information provided to us in a data room, . . . then subsequently the
same information . . . that was there for the Siluria ABC negotiations.” Groten
explained that under the APA, Lummus viewed it as holistic, and the only reason
anything from Siluria Tech was at Braskem was for demonstrating the technology;
thus, everything there “constituted an integral to [sic] and part of the demonstration
unit.” He explained that Lummus had “expertise in what pilot plants and
demonstration units should look like[.]” Groten listed what they expected to see in
17 the data room, including computers, analytical equipment, operating instructions,
startup, shutdown, emergency operating procedures, safety equipment, catalysts
“any parts of the physical components to the demonstration unit” were included in
an exhibit to the APA, which was “written in a way to be as comprehensive as
possible.” Groten testified that there was a “fixed asset detail” attached as an
appendix to the APA, and all the assets encompassed at that Braskem site fell under
the umbrella of the “demonstration unit.” Groten testified this was because those
items listed were “essential to make . . . a demonstration that’s capable of operating”
safely at the Braskem La Porte Chemical Plant. Groten testified that “demo plant
LPT” on the fixed asset detail spreadsheet attached to the APA refers to assets that
are subsets of the demonstration unit located at the Braskem La Porte facility and
felt if they removed any item within that asset class, they began removing the
demonstration unit.
Groten discussed Lummus’s letter to the Escrow Agent demanding return of
funds dated on January 9, 2020, because 1) they had begun to remove, and 2) they
were not going to enter a lease on the terms provided for in the Escrow Agreement
and APA with Braskem. Lummus was not getting the value assigned to the
demonstration unit, and by then, they knew Braskem would not enter a lease with
them under the terms embedded in the Escrow Agreement and APA, so they had
begun removing the demonstration unit. After Lummus sent its letter, Siluria ABC
18 challenged it with their own letter to the Escrow Agent, because according to Groten,
Siluria ABC “created an arbitrary threshold that they said [Lummus] had not met in
beginning to remove the demonstration unit.” Groten reasoned that the negotiated
language “to begin removal” was a low threshold, and Siluria ABC “suggested that
the activities that we had taken to make the unit not capable of operating and
removing what we could did not meet that threshold of beginning to remove[.]”
Groten testified the APA does not say that the demonstration unit is a four-story
structure; this was because “the structure is only a component of it, and it was not
identified as a separate asset on the balance sheet of Siluria Tech.” Lummus
eventually removed the entire demonstration unit from Braskem at a cost of
$502,000.
Ian Rubin’s Testimony
Ian Rubin (“Rubin”), Braskem’s director of business development strategic
growth projects, testified that Braskem hosted Siluria Tech as a tenant, and Siluria
Tech built a “demo plant” at their La Porte site. Rubin testified about a new lease
with Lummus and explained that Braskem’s lease with Siluria Tech was below
market and “was very unattractive to Braskem America, and we had no interest in
continuing on the same terms.” Rubin testified that in September 2019, Braskem had
a video conference with Lummus and made it clear that Braskem would not engage
in lease negotiations unless it was “on a market basis.”
19 Braskem believed it would take three months to remove the unit entirely, and
the process requires expertise. Rubin testified that when the demonstration unit was
operating, someone was always in the control room monitoring it to make sure it
operated safely. Rubin testified it would take heavy machinery to remove it and
would be a big, time-consuming job.
He said that Lummus could only come onto Braskem’s premises to get their
items with permission. Rubin testified that Lummus came to Braskem on October 2,
2019, to remove computers and tools and again on November 5, 2019, to retrieve
other items. In early December 2019, Lummus requested permission to have their
third-party contractor come onsite to inspect the demo plant. Rubin responded on
December 2, 2019, that per Braskem’s legal team, they could not interact with
Lummus because one of Siluria Tech’s shareholders had sued over the sale of the
assets, and Braskem wanted an indemnity agreement from Lummus before they
allowed them back on the premises, which they did not execute until April 2020.
William Trento’s Testimony
William Trento (“Trento”) is a senior vice president for Sherwood Partners,
which is a “small business advisory firm.” He explained that their work deals with
companies experiencing financial distress, and he takes insolvent companies through
some type of insolvency proceeding, “like an Assignment for the Benefit of
Creditors.” In May 2019, Siluria Tech engaged Sherwood Partners to act as a
20 fiduciary in the ABC process. Sherwood Partners formed a “special purpose
entity[,]” which was “Siluria (Assignment for the Benefit of Creditors) LLC.” Siluria
Tech then assigned all its assets to Siluria ABC, and Sherwood Partners’ job was “to
protect, manage, and ultimately liquidate those assets to generate as much as cash”
as possible and return it to the creditors. There is no mandated deadline for
completing the ABC process and usually, the process lasts more than six months,
but the sales process lasts thirty to sixty days.
Trento understood that Siluria Tech had developed new technology to convert
natural gas to other more valuable products, like ethylene, through chemical
catalysts, but he did not have a detailed understanding about how the process
worked. He testified that the ABC process did not require him to have a detailed
understanding of an insolvent company’s business. Their goal is always to maximize
the assets’ value, and they hire back former employees from various aspects of the
business, in this case technical people who knew the most about the intellectual
property. In this case, Siluria ABC hired former Siluria Tech employees including
finance people, CEO and COO Erik Scher, and Chief Technology Officer Guido
Radaelli. The finance team from Siluria Tech told them generally that the assets
included intellectual property, fixed assets in California, and a facility in Texas,
which they had to liquidate. In May 2019, those assets were assigned to Siluria ABC,
which began marketing them by developing a target list of potential buyers.
21 The sales memo described “a first-of-its-kind commercial demonstration plant
co-located with the Braskem operating polypropylene plant in La Porte, Texas,” and
Trento said he believed the phrase “commercial demonstration plant” to be “the lease
facility in Texas where the Siluria assets were located.” Trento testified the assets
located in the demonstration plant included “that large four-story structure, the
demonstration unit that we have seen so many pictures of, and then other
miscellaneous assets that were located in the remote office: the employees’
computers and papers and spare parts and such.” He testified that the four-story
structure was the largest asset at Braskem’s facility and identified that as the
“demonstration unit.” He testified that it was partially self-contained, but “it’s
certainly connected to the Braskem plant through Braskem’s piping, and it’s
connected to Braskem’s control room through wires and piping and such.”
Trento testified that during the asset marketing process, he did not really
understand how the demonstration unit worked or know what items were necessary
to operate it. He had never seen the demonstration unit or control room in person
and had not been to the Braskem site. Trento testified he did not know if the spare
catalyst was a critical component required to make the demonstration unit work or
how often they had to be changed. Trento testified that although he did not know
everything needed to operate the demonstration unit, “I know you need the control
room, . . . the pieces.” He understood that in the control rooms, computers and
22 programs run the physical demonstration unit, but here, it was Braskem’s control
room. Even so, Trento did not know what the computers, tools, and parts Lummus
removed were used for.
Trento was the one primarily handling the negotiations for Siluria ABC, and
his main contact was Groten, but he also spoke with an attorney from Lummus. In
late May 2019, he had a conference call with Groten and discussed the demonstration
unit, who later sent over notes summarizing the call. Trento believed that when
Groten’s notes mentioned “demo plant La Porte[,]” he was referring “to the lease
facility in Texas where the Siluria assets were located.” He then differentiated
between that and the “demo unit asset,” explaining that he believed Groten meant
“the large four-story structure.” Nevertheless, Trento testified they did not discuss
which items were critical to the demonstration unit’s operation nor did anyone from
Lummus tell Trento they defined “demonstration unit” to include all Siluria ABC’s
assets at the La Porte facility. Trento testified that Groten’s notes from the
conference call also referenced a post-close price adjustment. He explained that
Groten was concerned if they could not get a lease with Braskem, it would cost $1.5
million to remove the large structure from Braskem. Trento testified that he initially
thought Groten’s estimate seemed high but ultimately determined it was reasonable
based on the need for heavy equipment and that it was “a large structure” and “a big
process” to remove. Trento denied that Groten told him during the conference call
23 that Lummus believed the $1.5 million represented the value of an operable
demonstration unit. Trento testified that in a petrochemical plant the removal process
includes contemplating removal through physical removal of the assets. Even so,
Siluria ABC believed that “begin removal meant getting cranes out there and torches
or wrenches or whatever to begin dismantling this big unit[;]” that was their
intention.
Trento told the jury that after the May 2019 conference call, Lummus
submitted its offer, and Sherwood sent a standard APA to them, which Lummus
marked up. According to Trento, before Siluria ABC entered the agreements with
Lummus, they did not perform any due diligence on Lummus and cared only about
maximizing return to creditors, so they went with whoever was willing and capable
of buying the assets. The parties ultimately agreed to a final APA.
Consistent with Groten’s testimony, Trento understood that the $1.5 million
escrow fund referenced the holdback in the APA, and the two events identified in
the Escrow Agreement sections 3(a) and (b) are the same as the conditions outlined
in the APA section 2.1. Trento said Siluria ABC agreed to the holdback because if
Lummus could not get a new lease with Braskem and had to remove the
demonstration unit, it would be expensive. So, they felt it was reasonable if it cost
that much to move it.
24 Trento said that Section 3 of the Escrow Agreement addressed the events
related to the holdback contingency. He testified that the first event required for
Siluria ABC to get the money was that Lummus and Braskem enter a lease
agreement and site services agreement “to be able to operate the demonstration unit
at Braskem’s La Porte facility” in accordance with the requirements set forth in
Section 2.1 of the APA. Trento testified that to meet the first condition for Siluria
ABC to get the holdback, the demonstration unit must be able to operate, which was
written in the Escrow Agreement. He added that the second condition for Siluria
ABC to get the money was that “Buyer has not begun removing the demonstration
unit from Braskem’s facility.” He agreed that neither the Escrow Agreement nor
APA used the language “four-story structure” and that the contract did not say the
$1.5 million was for removal costs.
Trento testified that the phrase “demonstration unit” is undefined in the
agreements, which he regrets, although he conceded that the contract should be
interpreted according to industry custom and practice. He explained the parties did
not define it because it was understood to be the four-story structure, and Siluria
ABC intended the phrase “demonstration unit” as used in the agreements to mean
“this large four-story structure” that would be “difficult” and “expensive to remove.”
Siluria ABC’s intent when they used the phrase “begun removing the demonstration
unit” was that Lummus would attempt to negotiate a lease with Braskem over a
25 matter of weeks or “a month or two” and if not, they would bring in a company with
cranes and start removing it. He said they agreed to the six-month timeline, because
ABCs always want the money as quickly as possible; here they were willing to wait
six months but did not want to go beyond that so they could maximize value and get
the money to the creditors as soon as possible. Trento testified that at first, Siluria
ABC wanted Lummus to be required to complete the demonstration unit’s removal
to receive the escrow fund, but Groten resisted. Groten suggested removing the
demonstration unit was a big process and while they might move most of it in six
months, he thought it was possible they would have a “little left,” which made sense
to Siluria ABC. Trento testified that the Escrow Agreement did not require Lummus
to complete the removal of the demonstration unit by January 15, 2020, although
Siluria ABC had every opportunity to put that in the contract, rather Lummus only
had to begin removal.
Once the parties signed the agreements, Siluria ABC immediately transferred
the assets to Lummus and then waited for the $1.5 million holdback. Trento testified
that Lummus did not notify them in October or November 2019 it had begun
removing the demonstration unit. He said they finally heard from Lummus about the
holdback in January 2020, when Lummus sent a letter to their firm and the Escrow
Agent. When Trento read Lummus’s letter, he did not believe that Lummus satisfied
the conditions and was entitled to the escrow fund. He specifically pointed to the
26 following language in Lummus’s letter: “Because of Braskem’s unwillingness and
delay to enter into any lease agreement with respect to the demonstration unit,
Lummus was forced to . . . begin the removal process for assets related to the
demonstration unit from Braskem’s La Porte facility.” Trento explained that
language shows Lummus began “the removal process for assets related to the
demonstration unit, but not the demonstration unit itself.” Trento testified that Siluria
ABC believed that Lummus had not begun removing the demonstration unit by
January 15, 2020, based solely on Groten’s letter.
Trento said Siluria ABC responded with their own letter in January 2020 and
requested the holdback. Trento testified that Siluria ABC would never agree to the
$1.5 million if it knew the demonstration unit included every asset belonging to
Siluria ABC at the La Porte facility, and it would be unreasonable to grab a computer
and get that money; the $1.5 million was specifically for “removal of the
demonstration unit.” The parties discussed that the demonstration unit as a large
structure that would require cranes, otherwise, it would be “so one-sided” and not
something they would do, as it is “not maximizing value for the creditors.” Only
after Siluria ABC disputed Lummus’s right to the holdback, did Trento begin
emailing Braskem to determine whether Lummus removed anything from the
demonstration unit and emailing Scher to determine whether Siluria Tech documents
27 defined the demonstration unit and whether the items Lummus removed were
included in it.
In March 2020, Groten sent a letter to Trento regarding the holdback and
detailed the property they removed, along with describing that Lummus had tried to
hire contractors. Trento did not dispute the letter’s accuracy or that the items
described were removed.
E. Jury Charge, Verdict, Attorney’s Fees, Post-Verdict Motions, and Final Judgment
During the charge conference, Lummus objected to an instruction that Siluria
ABC proposed regarding a bona fide attempt to complete an action as commenting
on the weight of the evidence. Siluria ABC agreed to withdraw that proposed
instruction. Thereafter, neither party objected to Question 1, which incorporated the
trial court’s ambiguity instruction.3, 4 The sole question submitted to the jury and
its response was:
Did Lummus Technology, LLC begin removing the demonstration unit from Braskem America, Inc.’s facility by January 15, 2020?
3The trial court granted Siluria ABC’s motion for directed verdict on Lummus’s affirmative defense of impossibility based on Braskem’s refusal to let them onsite. Lummus requested a submission of a second question on its affirmative defense of impossibility, which the trial court denied. 4It should be noted that in pretrial filings Siluria ABC submitted a proposed
“ambiguity instruction,” which was similar or substantially the same as contained in the sole question submitted to the jury.
28 In determining the meaning of the Escrow Agreement, you must determine the intent of the parties at the time of the agreement. Consider all of the facts and circumstance surrounding the making of the agreement, the interpretation of the agreement by the parties, and the conduct of the parties.
Answer “Yes” or “No.”
ANSWER: YES
Consistent with the parties’ Rule 11 Agreement, Lummus submitted evidence
of attorney’s fees to the trial court by affidavit after the trial. Lummus argued it was
entitled to attorney’s fees under Texas Civil Practice and Remedies Code section
37.009 governing declaratory judgments, and claimed it was unnecessary to
segregate since the breach-of-contract work and declaratory judgment claims were
“inextricably intertwined.” Lummus’s evidence supporting its attorney’s fees
included affidavits from attorneys and billing invoices. Lummus sought to recover
attorney’s fees through trial of $672,571.35 and attorney’s fees if Siluria ABC
appealed. Siluria ABC filed its Objection to Lummus’s Failure to Segregate
Attorneys’ Fees and Response to Lummus’s Motion to Determine Amount of
Prevailing Party’s Attorneys’ Fees. It objects to Lummus’s failure to segregate,
complains that Lummus’s fees were unreasonably high, asserts that Lummus’s fees
and expenses should not exceed $547,622.00, and argues Lummus is not entitled to
conditional appellate attorney’s fees. Siluria ABC supported its Response with
counsel’s affidavit. Lummus filed a Reply in Support of Motion to Determine
29 Amount of [Its] Attorneys’ Fees again asserting that it need not segregate its fees
and that its fees were reasonable.
The trial court’s Final Judgment incorporated the jury’s findings and declared
that Lummus was entitled to recover the full amount of the escrow fund because it
met the conditions required for recovery of such funds under the Escrow Agreement.
The trial court awarded Lummus: $1,495,543.10 from the court’s registry;5
attorney’s fees of $467,144.50 through trial; conditional appellate attorney’s fees of
$40,000.00 if Lummus prevails in the intermediate court of appeals; conditional
appellate attorney’s fees of $15,000.00 if a petition is filed with the Texas Supreme
Court and Lummus prevails; and conditional attorney’s fees of $35,000.00 if the
Texas Supreme Court grants a petition or full briefing is required and Lummus
prevails. The trial court also awarded post-judgment interest.
Siluria ABC filed its Motion to Disregard Jury Finding and for Judgment
Notwithstanding the Verdict, arguing that the Escrow Agreement was unambiguous
and should be construed as a matter of law, thus the jury’s finding is immaterial. It
also contends that Lummus’s interpretation was unreasonable. Siluria ABC also
filed a Motion for New Trial arguing the jury’s answer was against the great weight
5This reflects the net amount after the Escrow Agent’s fees were deducted
before the funds were deposited into the trial court’s registry. 30 and preponderance of the evidence. The trial court denied both motions. Siluria ABC
timely appealed.
II. ISSUES ONE, TWO AND THREE: CONTRACT INTERPRETATION
In issues one through three, Siluria ABC complains that the trial court should
have interpreted and determined that the Escrow Agreement was unambiguous as a
matter of law, and thus the trial court erred by submitting a question of law to the
jury, which was harmful. Lummus responds that Siluria ABC failed to object to the
jury charge and has waived its complaints about any submission to the jury. Siluria
ABC counters in its reply that as a question of law, the submission was immaterial,
thus it was not required to object.
A. Standard of Review and General Principles of Contract Law
“Whether a particular provision or the interaction among multiple provisions
creates an ambiguity is a question of law.” State Farm Lloyds v. Page, 315 S.W.3d
525, 527 (Tex. 2010) (citation omitted); see also Mosaic Baybrook One, L.P. v.
Simien, 674 S.W.3d 234, 257 (Tex. 2023) (citation omitted). We review issues of
contract construction under a de novo standard. See Barrow-Shaver Res. Co. v.
Carrizo Oil & Gas, Inc., 590 S.W.3d 471, 479 (Tex. 2019). When discerning the
parties’ intent, we examine the entire agreement, giving effect to each provision so
that none is rendered meaningless in the context in which they were written. See Bd.
31 of Regents of Tex. Univ. Sys. v. IDEXX Laboratories, Inc., 691 S.W.3d 438, 444–45
(Tex. 2024).
“We must give effect to the parties’ intentions, as expressed in their
agreement,” and “[w]e will give a contract language its plain, grammatical meaning
unless it would clearly defeat the parties’ intentions.” Barrow-Shaver Res. Co., 590
S.W.3d at 479 (citations omitted). “Whenever possible, courts must assess adverse
arguments and resolve a text’s meaning as a matter of law.” U.S. Polyco v. Tex. Cent.
Bus. Lines Corp., 681 S.W.3d 383, 389 (Tex. 2023). The Texas Supreme Court has
cautioned us against considering parties’ subjective intent when resolving a
contract’s meaning. See id. Usually, the instrument alone will be deemed to express
the parties’ intent, since it is objective, not subjective, intent that controls. See id. at
387 (citing City of Pinehurst v. Spooner Addition Water Co., 432 S.W.2d 515, 518
(Tex. 1968)). Thus, an unambiguous contract will “be enforced as written without
considering extrinsic evidence bearing on the parties’ subjective intent.” Devon
Energy Prod. Co. v. Sheppard, 668 S.W.3d 332, 343 (Tex. 2023) (citation omitted)
(stating same in context of oil and gas leases). The objective intent as expressed in
the agreement controls the construction of an unambiguous contract, “not a party’s
after-the-fact conduct.” In re Dillard Dept. Stores, Inc., 186 S.W.3d 514, 515 (Tex.
2006) (orig. proceeding) (citing Lopez v. Munoz, Hockema & Reed, L.L.P., 22
S.W.3d 857, 861 (Tex. 2000)).
32 Just because the parties disagree over a meaning does not make a contract
ambiguous. See IDEXX Laboratories, Inc., 691 S.W.3d at 443. “If the contract is
subject to two or more reasonable interpretations after applying the pertinent rules
of construction, however, the contract is ambiguous, creating a fact issue on the
parties’ intent.” ConocoPhillips Co. v. Koopmann, 547 S.W.3d 858, 874 (Tex. 2018)
(citation omitted) (emphasis added); see also IDEXX Labs., Inc., 691 S.W.3d at 445
(“A limited examination may yield reasonable, conflicting interpretations, but only
when one interpretation does not clearly emerge as correct after a full examination
is a contract ambiguous and the determination of its meaning left to a jury.”).
One rule of contract construction is that when terms are undefined, we give
them their plain meaning. See Simien, 674 S.W.3d at 257 (quoting Perthuis v. Baylor
Miraca Genetics Labs., LLC, 645 S.W.2d 228, 236 (Tex. 2022)). “To determine the
common, ordinary meaning of undefined terms used in agreements, ‘we typically
look first to their dictionary definitions and then consider the term’s usage in other
statutes, court decisions, and similar authorities.’” OHAH, Ltd. v. LNG Builders,
LLC, No. 09-20-00292-CV, 2022 WL 16986573, at *10 (Tex. App.—Beaumont
Nov. 17, 2022, pet. denied) (mem. op.) (quoting Tex. State Bd. of Examiners of
Marriage & Fam. Therapists v. Tex. Med. Ass’n, 511 S.W.3d 28, 35 (Tex. 2017)).
33 B. Analysis
Although the Escrow Agreement contained two contingencies, the parties do
not dispute that Lummus was unable to obtain a lease with Braskem to be able to
operate the demonstration unit at its La Porte facility. So, the first contingency is not
at issue. The only condition at issue here is over Section 3(a)(ii) of the Escrow
Agreement which provides that Seller is entitled to the 1.5 million if by:
The sixth (6th) month anniversary of the Closing (as defined in the Purchase Agreement) if, by such date, Buyer has not begun removing the demonstration unit from Braskem’s facility.
Otherwise, Buyer is entitled to the holdback. January 15, 2020 is the six month
anniversary. By January 15, 2020, had Lummus “begun” removing the
“demonstration unit” from Braskem’s facility. That is the sole issue.
For there to be an ambiguity, both parties’ advocated interpretations would
need to be reasonable, after we apply principles of contract construction. See IDEXX
Labs., Inc., 691 S.W.3d at 445; Koopmann, 547 S.W.3d at 874. Siluria ABC
contends its desired interpretation of “demonstration unit” is reasonable but that
Lummus’s suggested interpretation is unreasonable. Therefore, Siluria ABC argues
there is no ambiguity. Siluria ABC’s corporate representative, Trento, testified at
trial that “demonstration unit” was undefined in the contracts, which he regrets.
Likewise, the term “begun” is undefined. Since the terms are undefined in the
contract, we give them their plain meaning, looking first to their dictionary
34 definitions. See Simien, 674 S.W.3d at 257; Perthuis, 645 S.W.3d at 236; OHAH,
Ltd., 2022 WL 16986573, at *10.
“Begun” is the past tense of the verb “begin,” which is defined as “to do the
first part of action” or “go into the first part of a process.” https://merriam-
webster.com/dictionary/begun (last visited Mar. 3, 2025). “Demonstration” is
defined as “an act, process, or means of demonstrating to the intelligence,” or “a
showing of the merits of a product or service to a prospective customer.”
https://merriam-webster.com/dictionary/demonstration (last visited Mar. 3, 2025).
“Unit” is defined as “a single thing, person, or group that is a constituent of a whole”
or “a piece or complex of apparatus serving to perform one particular function.”
https://merriam-webster.com/dictionary/unit (last visited Mar. 3, 2025). Giving
these words their plain meaning, the “demonstration unit” is a single thing or group
that is a constituent of a whole, or a piece or complex of apparatus serving to perform
(1) an act, process or means of demonstrating, or (2) show the merits of a product or
service to a prospective customer. Using the plain language to define “demonstration
unit” references that the unit demonstrates or shows the merits of a process, product
or service. To show the OCM process or to demonstrate the OCM process would
require the demonstration unit to operate or be operable and it cannot operate without
its computers and materials. The other contingency in the Escrow Agreement, as
stated in section 3(a)(i), was that if Lummus failed to enter a lease and site services
35 agreement, in accordance with the APA, with Braskem “to be able to operate the
demonstration unit at Braskem’s LaPorte facility.” This is informative, as the
express purpose of the lease with Braskem was “to be able to operate the
demonstration unit” there, which supports the parties’ intent that the unit be
operable. Nothing in the language of the Escrow Agreement or the APA limits the
definition of the demonstration unit to the “four-story structure” or to only the bolted
attachments that Siluria ABC advocates. Rather, the language supports the parties’
intent that the demonstration unit be operable, and that Lummus was required to
begin to take the first steps in the process to remove it.
Applying principles of contract construction by giving undefined terms their
plain, ordinary meaning as read in context shows a single reasonable interpretation
emerges, and it is the definition Lummus advocates. See IDEXX Labs., Inc., 691
S.W.3d at 443–44. Therefore, we conclude the agreement is unambiguous. Cf.
Koopmann, 547 S.W.3d at 874 (explaining that if a contract is subject to two or more
reasonable interpretations after applying rules of construction, it is ambiguous).
These were sophisticated parties in an arm’s-length transaction. See Barrow-Shaver
Res. Co., 590 S.W.3d at 484 (explaining provision at issue was “a bargained-for
exchange” between sophisticated party). Trento and Groten, both engineers and with
the assistance of counsel, exchanged and edited drafts of the agreement, which
included adding the “begun removal” language that made it into the final agreement.
36 Thus, the surrounding circumstances establish that the “begun removal” provision
“was a bargained-for exchange between the parties.” Id. (citation omitted). “But
those are the only facts and circumstances we can consider without delving into the
parties’ intent beyond what their agreement plainly yields.” Id. (citation omitted).
The unambiguous provision controls, thus we do not consider extrinsic evidence that
varies the agreement. See id. By removing components such as computers and
catalysts that would have rendered the demonstration unit inoperable, Lummus had
“begun removal.” If the parties felt a higher or specific threshold was required, they
were free to negotiate that and include it in the Escrow Agreement.
Again, Siluria ABC contends that it did not need to object to the court’s
charge, because the question submitted to the jury was immaterial. Implicit in the
trial court’s decision to submit the question to the jury was its determination that the
contract was ambiguous. See Sifuentes v. Carrillo, 982 S.W.2d 500, 505 (Tex.
App.—San Antonio 1998, pet. denied); see also Exxon Corp. v. West Tex. Gathering
Co., 868 S.W.2d 299, 302 (Tex. 1993). As discussed above, we agree that the
contract at issue was unambiguous. Since the trial court failed to construe that the
contract was unambiguous as a matter of law, it erred in submitting the question to
the jury. See Barrow-Shaver Res. Co., 590 S.W.3d at 480; Grohman v. Kahlig, 318
S.W.3d 382, 887 (Tex. 2010). “A question is immaterial when it should not have
been submitted,” and a question “beyond the province of the jury, such as a question
37 of law, may be deemed immaterial.” Spencer v. Eagle Star Ins. Co. of Am., 876
S.W.2d 154, 157 (Tex. 1994). Siluria ABC correctly argues that the trial court’s
question submitted to the jury was immaterial. See id.
Siluria ABC did not object to the jury charge. Even so, “a complaint that a
jury’s answer is immaterial is not a jury charge complaint.” Musallam v. Ali, 560
S.W.3d 636, 640 (Tex. 2018) (citing BP Am. Prod. Co. v. Red Deer Res., LLC, 526
S.W.3d 389, 402 (Tex. 2017)). Thus, a party need not object to a jury question to
later argue it is immaterial. Id.; Red Deer Res., 526 S.W.3d at 402. Siluria ABC
preserved error on the immateriality issue by raising this concern in a post-verdict
motion for judgment notwithstanding the verdict. See Musallam, 560 S.W.3d at 640;
Red Deer Res., 526 S.W.3d at 402. That said, the erroneous submission of an
unambiguous contract to the jury is harmless if the jury found as the trial court should
have found. See Tex. R. App. P. 44.1 (outlining standard for reversible error);
Barrow-Shaver Res. Co., 590 S.W.3d at 480; Grohman, 318 S.W.3d at 887 (citation
omitted); Spencer, 876 S.W.2d at 157. Since the jury here determined that Lummus
had begun removing the demonstration unit by January 15, 2020, which is what the
trial court should have determined when construing this unambiguous agreement,
any error in submitting Question 1 to the jury was harmless. See Tex. R. App. P.
44.1; Barrow-Shaver Res. Co., 590 S.W.3d at 480; Grohman, 318 S.W.3d at 887
(citation omitted); Spencer, 876 S.W.2d at 157.
38 We overrule issues one through three.
III. ISSUE FOUR: FACTUAL SUFFICIENCY
In its fourth issue, Siluria ABC challenges the factual sufficiency of the
evidence by complaining that the jury’s verdict was against the great weight and
preponderance of the evidence. Even if the contract here required the jury to decide
a disputed fact issue, the evidence was factually sufficient to support the jury’s
verdict for the reasons discussed below.
A. Standard of Review and Applicable Law
In a legal sufficiency challenge of a jury’s verdict, we view all the evidence
in the light most favorable to the verdict. See Westwood Motorcars, LLC v.
Virtuolotry, LLC, 689 S.W.3d 879, 885 (Tex. 2024); City of Keller v. Wilson, 168
S.W.3d 802, 807, 810 (Tex. 2005). We reverse “only if there is a complete absence
of evidence proving a vital fact, the rules of law or evidence bar the court from
weighing the only evidence proving a vital fact, the evidence offered to prove a vital
fact is no more than a mere scintilla, or the evidence conclusively disproves the
existence of a vital fact.” Westwood Motorcars, 689 S.W.3d at 885–86 (citing City
of Keller, 168 S.W.3d at 807, 810). That said, on appeal, Siluria does not challenge
the legal sufficiency of the evidence supporting the jury’s verdict, but only the
factual sufficiency of the evidence. In a factual sufficiency review of a jury finding
on which the appellant does not have the burden of proof, we examine “all the
39 evidence and will set aside the verdict only if the evidence is so weak that it is clear
the verdict is wrong and unjust.” Cimarron Country Prop. Owners Ass’n v. Keen,
117 S.W.3d 509, 512 (Tex. App.—Beaumont 2003, no pet.) (citing Cain v. Bain, 709
S.W.2d 175, 176 (Tex.1986)). In a factual sufficiency review, we do not substitute
our judgment for the jury’s. See Golden Eagle Archery, Inc. v. Jackson, 116 S.W.3d
757, 761 (Tex. 2003). The jury is the sole judge of the witnesses’ credibility and
weight to be given their testimony. See id.
B. Analysis
Again, Groten testified that he intentionally negotiated the requirement that
they begin removal of the unit rather than complete it, which was a very low
threshold. Trento and Groten both testified that Siluria ABC sent the initial draft of
the APA, the parties exchanged redlines, including adding the “begun removal”
language, which Siluria ABC ultimately agreed to. Groten described the removal
process and testified that they began by removing easily “moveable” items like
computers, and the OCM catalysts that were necessary to the demonstration unit’s
operation. Groten also testified that before January 15, 2020, Lummus contacted
three third-party contractors with the skill set to complete removal and attempted to
get them on Braskem’s site.
Trento testified that he did not know how the catalysts or computers were
necessary to the demonstration unit and the OCM process. He did acknowledge that
40 the four-story structure was connected to the “control room through wires and piping
and such.” Trento testified that all Lummus had to do was begin removing the unit,
and he added that in a petrochemical process this includes when you contemplate
removal up through physical removal of the assets. Although he later testified that
Siluria ABC believed “begin removal meant getting cranes out there[,]” which was
their intent. Trento testified that he did not know everything needed to operate the
demo unit, but testified, “I know you need the control room, . . . the pieces.”
Additional evidence showed that on January 17, 2020, Trento and Siluria ABC
disputed Lummus “had begun” removing the demonstration unit; however, Trento
was still asking others whether Lummus had begun the removal process, which
seemed to show Siluria ABC disputed this without having knowledge of the removal
status.
Although the parties gave conflicting testimony about the meaning of
“demonstration unit” and “begun” or “begin removing” in the contract and their
intent, the jury was free to judge the witnesses’ credibility and decide the weight, if
any, to give the testimony. See id. For these reasons, we cannot say that the jury’s
verdict was against the great weight and preponderance of the evidence or clearly
wrong and manifestly unjust. See Cain, 709 S.W.2d at 176; Keen, 117 S.W.3d at
512.
We overrule issue four.
41 IV. ISSUE FIVE: ATTORNEY’S FEES
In issue five, Siluria ABC contends the trial court erred by awarding
Lummus’s attorney’s fees for failure to segregate and that Lummus was not entitled
to attorney’s fees for its breach of contract claim as an LLC.
“We review section 37.009 fee awards under an abuse-of-discretion
standard.” Transcor Astra Grp., S.A. v. Petrobras Am. Inc., 650 S.W.3d 462, 482
(Tex. 2022) (citing Bocquet v. Herring, 972 S.W.2d 19, 21 (Tex. 1998)). “It is an
abuse of discretion for a trial court to rule arbitrarily, unreasonably, or without regard
to guiding legal principles ... or to rule without supporting evidence.” Id. (citations
omitted).
In a declaratory judgment proceeding, “the court may award costs and
reasonable and necessary attorney’s fees as are equitable and just.” Tex. Civ. Prac.
& Rem. Code Ann. § 37.009. Generally, attorneys are required to segregate their
recoverable fees from fees that advance non-recoverable claims. See Tony Gullo
Motors I, L.P. v. Chapa, 212 S.W.3d 299, 311–12 (Tex. 2006). The exception is that
if “legal services advance both a recoverable and unrecoverable claim that . . . are so
intertwined they need not be segregated.” Kinsel v. Lindsey, 526 S.W.3d 411, 427
(2017); see also Chapa, 212 S.W.3d at 311–12.
42 B. Analysis
Here, the parties agreed to submit evidence of attorney’s fees to the trial court
via affidavit post-trial. Lummus submitted detailed affidavits outlining their work,
attaching fee invoices, and explaining why the declaratory judgment claims and
breach of contract claims were so intertwined they need not be segregated. Siluria
ABC challenges Lummus’s failure to segregate their fees. However, Siluria ABC’s
own attorney fee expert was also of the position that the declaratory judgment claims
and breach of contract claims were so intertwined they need not be segregated, which
corroborated Lummus’s position. Finally, the record establishes that the parties
sought competing declaratory judgments interpreting the contract and their rights
and duties under the contract, which is an allowable declaratory judgment claim. See
Tex. Civ. Prac. & Rem. Code Ann. § 37.004(a) (allowing for parties to seek a
declaration regarding a contract’s construction or their rights under a contract,
among other things).
The only fees arguably subject to segregation would have been work done in
response to the Escrow Agent’s interpleader action. Yet the record establishes that
the parties performed little work on the interpleader action, which included filing an
answer and the parties’ agreed motion to interplead the funds and dismiss the Escrow
Agent. The record reflects that the Escrow Agent initiated the lawsuit in March 2021
and by May 2021, the Escrow Agent had been dismissed from the case. Given the
43 brief period the parties dealt with the interpleader action, those fees would have been
comparatively small.
The evidence shows that Lummus sought $672,571.35 in fees, but Siluria
ABC claimed that Lummus’s fees and expenses should not exceed $547,622.00;
however, the trial court discounted Lummus’s fees to $467,144.50, reducing them
by 30.6%. Based on this discount and how intertwined the breach of contract and
declaratory judgment claims were, we cannot say the trial court abused its discretion
by not requiring further segregation. See Transcor Astra Grp., 650 S.W.3d at 482;
Bocquet, 972 S.W.2d at 21; see also Chapa, 212 S.W.3d at 311–12.
We overrule issue five.
V. CONCLUSION
Having overruled Siluria ABC’s issues necessary to the resolution of this
appeal, we affirm the trial court’s judgment.
AFFIRMED.
W. SCOTT GOLEMON Chief Justice
Submitted on February 27, 2025 Opinion Delivered March 20, 2025
Before Golemon, C.J., Johnson and Wright, JJ.
Related
Cite This Page — Counsel Stack
Siluria (Assignment for the Benefit of Creditors), LLC v. Lummus Technology LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siluria-assignment-for-the-benefit-of-creditors-llc-v-lummus-technology-texapp-2025.