SILO POINT II LLC v. Suffolk Const. Co., Inc.

578 F. Supp. 2d 807, 2008 U.S. Dist. LEXIS 76018, 2008 WL 4366382
CourtDistrict Court, D. Maryland
DecidedSeptember 25, 2008
Docket1:08-cv-00999
StatusPublished
Cited by17 cases

This text of 578 F. Supp. 2d 807 (SILO POINT II LLC v. Suffolk Const. Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SILO POINT II LLC v. Suffolk Const. Co., Inc., 578 F. Supp. 2d 807, 2008 U.S. Dist. LEXIS 76018, 2008 WL 4366382 (D. Md. 2008).

Opinion

MEMORANDUM OPINION

RICHARD D. BENNETT, District Judge.

Plaintiff Silo Point II, LLC, (“Silo Point”), a Maryland Limited Liability Company engaged in the business of real estate development, has filed a two-count Complaint in this Court against Defendant Suffolk Construction Company, Inc. (“Suffolk”), a general contractor incorporated in Massachusetts. At issue is the Guaranteed Maximum Price contract (the “Contract”) the parties entered into that sets forth the terms and risks attendant to the construction of a condominium project in Baltimore City (the “Project”). The crux of the dispute relates to the calculation of the Guaranteed Maximum Price (“GMP”), which largely determines liability for cost overruns on the Project. After the parties failed to negotiate a resolution, Silo Point brought this action seeking declaratory relief and specific performance.

Now pending before this Court is Defendant Suffolk’s Motion to Dismiss (Paper No. 4). Suffolk argues that the forum selection clause governing the Contract requires all disputes to be filed in a Mary- _ land state court. This matter has been briefed fully and no hearing is necessary. See Local Rule 105.6 (D.Md.2008). For the reasons set forth below, Suffolk’s Motion to Dismiss is GRANTED.

BACKGROUND

This action arises out of a dispute related to the construction of an approximately $100 million condominium project along Baltimore’s Inner Harbor. (Compl. ¶ 5.) On November 8, 2005, Silo Point issued its intent to award a prime contract to Suffolk for the construction of the Project that involved the conversion of a 1920s-era grain elevator and silo into a high end condominium building. (Id. ¶¶ 5, 8.) In late 2005 and early 2006, the parties engaged in Pre-Construction, wherein they identified the scope and intent of the work, determined construction feasibility, developed a construction schedule, and calculated a GMP. (Id. ¶ 9.) At the close of Pre-Construction, on April 20, 2006, the parties entered into the Contract that specified a GMP of $92,690,000 and a substantial completion date within twenty months from the commencement of construction. (Id. ¶¶ 10, 11; Def.’s Ex. 1A, Art. 4, § 4.3) The Contract provided that any costs exceeding the GMP would be borne by Suffolk without reimbursement by Silo Point. (Def.’s Ex. 1A, Art. 4 § 4.3) Finally, the Contract contains a forum selection clause which reads:

§ 4.4.3 Governing Law and Venue The substantive and procedural laws of Maryland shall apply in all respects to any and all disputes arising from or relating to interpretation of performance of this Contract, except as otherwise specifically provided herein. Any dispute between the parties shall be exclusively brought in the courts of the State of Maryland.

(Def.’s Ex. IB, Art. 4, § 4.4.3.)

During the construction process, several unforeseen conditions and difficulties developed. As a result, Suffolk began to incur costs well above the GMP and the Project’s projected completion date was extended. Suffolk thereupon petitioned Silo Point for both an upward adjustment *809 to the GMP to compensate for its cost overruns and for a time extension on the Project’s completion date. (Compl. ¶ 19.) A protracted dispute arose between the parties over the scope and nature of any adjustments to the Contract and the determination of the GMP and construction schedule.

In March of 2008, Suffolk indicated that it would file for a mechanic’s lien against the property and would sue for breach of contract in the Circuit Court for Baltimore City. 1 (Id. ¶ 28.) On April 21, 2008, after the failure of the parties’ subsequent attempts to resolve their dispute, Silo Point filed this action. Silo Point seeks a declaratory judgment that determines “the GMP based on the respective rights, risks, and obligations each party undertook pursuant to their negotiated Contract, including the appropriate contract completion date, and a declaration regarding Suffolk’s claims that have been submitted and rejected, as contrary to the terms of the Contract.” (Id. ¶ 50.) In addition, Silo Point seeks a grant of specific performance requiring Suffolk to produce certain books and records previously sought by Silo Point. (Id. ¶¶ 52-55.) Suffolk has moved to dismiss, claiming, inter alia, that the forum selection clause in the Contract forecloses either party from filing suit in this Court. 2

STANDARD OF REVIEW

The United States Court of Appeals for the Fourth Circuit has recently ruled that Fed.R.Civ.P. 12(b)(3) is the proper procedural vehicle for bringing a motion to dismiss based on improper venue when the issue turns on a forum selection clause. 3 Sucampo Pharms., Inc. v. Astellas Pharma, Inc., 471 F.3d 544, 550 (4th Cir.2006). Under Rule 12(b)(3) the court is allowed to freely consider evidence outside the pleadings, unlike under a 12(b)(6) motion. Id. In addition, when resolving a motion to dismiss under Rule 12(b)(3), “ ‘the pleadings are not accepted as true, as would be required under a Rule 12(b)(6) analysis.’ ” Id. at 549 (quoting Argueta v. Banco Mexicano, 87 F.3d 320, 324 (9th Cir.1996)). Nevertheless, “[i]n deciding a motion to dismiss, all inferences must be drawn in favor of the plaintiff, and ‘the facts must be viewed as the plaintiff most strongly can plead them.’ ” Sun Dun, Inc. of Washington v. Coca-Cola Co., 740 F.Supp. 381, 385 (D.Md.1990) (quoting Coakley & Williams, Inc. v. Shatterproof Glass Corp., 706 F.2d 456, 457 (4th Cir.1983)).

ANALYSIS

Because this is a diversity action, the substantive law of Maryland is applied in analyzing the forum selection clause. See Eisaman, et al. v. Cinema Grill Systems, Inc., et al., 87 F.Supp.2d 446, 448 (D.Md.1999) (“[I]n diversity cases ... the Fourth Circuit applies state law to determine enforceability” of forum selection *810 clauses.). Maryland has adopted the federal standards for evaluating forum selection clauses. Gilman v. Wheat, First Securities, Inc., 345 Md. 361, 692 A.2d 454, 459-63 (1997). In M/S Bremen v. Zapata Off-Shore Co., 407 U.S. 1, 92 S.Ct. 1907, 32 L.Ed.2d 513 (1972), the Supreme Court of the United States held that a forum selection clause is deemed to be enforceable if it is both mandatory and reasonable. Because the validity of the forum selection clause in the present case is not contested, and there is no showing that it is unreasonable, it will be enforced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Korman v. Princess Cruise Lines, Ltd.
California Court of Appeal, 2019
Korman v. Princess Cruise Lines, Ltd.
243 Cal. Rptr. 3d 668 (California Court of Appeals, 5th District, 2019)
Seidel v. Kirby
296 F. Supp. 3d 745 (D. Maryland, 2017)
Structural Preservation Systems, LLC v. Andrews
931 F. Supp. 2d 667 (D. Maryland, 2013)
Rihani v. Team Express Distributing, LLC
711 F. Supp. 2d 557 (D. Maryland, 2010)
Unistaff, Inc. v. Koosharem Corp.
667 F. Supp. 2d 616 (E.D. Virginia, 2009)
Nahigian v. Juno-Loudoun, LLC
661 F. Supp. 2d 563 (E.D. Virginia, 2009)
CoStar Realty Information, Inc. v. Field
612 F. Supp. 2d 660 (D. Maryland, 2009)
Tech USA, Inc. v. Evans
592 F. Supp. 2d 852 (D. Maryland, 2009)
The Hipage Co., Inc. v. Access2Go, Inc.
589 F. Supp. 2d 602 (E.D. Virginia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
578 F. Supp. 2d 807, 2008 U.S. Dist. LEXIS 76018, 2008 WL 4366382, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silo-point-ii-llc-v-suffolk-const-co-inc-mdd-2008.