Silicon International Ore, LLC v. Monsanto Co.

314 P.3d 593, 155 Idaho 538, 82 U.C.C. Rep. Serv. 2d (West) 152, 2013 WL 6190607, 2013 Ida. LEXIS 335
CourtIdaho Supreme Court
DecidedNovember 27, 2013
Docket39409
StatusPublished
Cited by28 cases

This text of 314 P.3d 593 (Silicon International Ore, LLC v. Monsanto Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silicon International Ore, LLC v. Monsanto Co., 314 P.3d 593, 155 Idaho 538, 82 U.C.C. Rep. Serv. 2d (West) 152, 2013 WL 6190607, 2013 Ida. LEXIS 335 (Idaho 2013).

Opinion

W. JONES, Justice.

I. Nature of the Case

Plaintiff, Silicon International Ore, LLC (“SIO”), appeals the district court’s entry of summary judgment in favor of defendants, Monsanto Company (“Monsanto”) and Washington Group International, Inc. (“WGI”), in a lawsuit brought by SIO against Monsanto and WGI for alleged breach of contract, intentional interference with SIO’s operations under said contract and breach of the implied covenant of good faith and fair dealing.

II. Factual and Procedural Background

Monsanto, through a wholly owned subsidiary, owns a quartzite mine near Soda Springs, Idaho. Monsanto and WGI contracted with each other for WGI to operate the quartzite mine. This agreement was memorialized in the Quarzite Agreement (“First Quarzite Agreement”), which expired at the end of 2002. A by-product of WGI’s operations at the quarry was silica sand, which was too small for Monsanto to use in its manufacturing.

In early 2000, SIO contacted Monsanto about acquiring the silica sand. Both Monsanto and WGI met with SIO to discuss SIO’s proposed business plan. SIO presented Monsanto with a proposed contract 1 , but the proposed contract was never executed. However, on November 29, 2000, Monsanto and WGI executed an Addendum to the First

Quarzite Agreement (“First Addendum”). The First Addendum authorized WGI to construct and operate a processing facility for silica sand at the quartzite mine and to pay Monsanto royalties of $13.00 per ton of processed silica sand that was sold by WGI to a third party. On December 1, 2000, SIO and WGI executed the Master Agreement, under which WGI agreed to provide “a portion of the silica sand within its control” to SIO; SIO agreed to pay for the construction of the processing facility for the silica sand; SIO agreed to pay WGI to dry, screen, and bag the silica sand; SIO agreed to pay WGI an additional $13.00 per ton for the processed silica sand; and WGI agreed to load the bagged silica sand onto SIO trucks. The Master Agreement was effective for five years, and it provided that title to the silica sand would pass to SIO upon delivery of the silica sand by WGI. Shortly thereafter, on December 19, 2000, Robert Sullivan, an officer of SIO who signed the Master Agreement, wrote a letter to Monsanto saying “we are pleased that the intent seems to be a long-term relationship.”

Shortly before the First Quarzite Agreement was set to expire in September of 2001, Monsanto and WGI executed a second Quarzite Agreement (“Second Quarzite Agreement”). Because the Second Quarzite Agreement by its terms terminated the First Quarzite Agreement, on March 1, 2002, Monsanto and WGI executed a new addendum to the Second Quarzite Agreement (“Second Addendum”). The Second Addendum was almost identical to the First Addendum but provided that WGI would pay Monsanto between $3.00 and $13.00 per ton of silica sand based on several considerations and that the “[tjitle to the silica sand sold by SIO shall pass directly from [Monsanto] to SIO upon processing ... subject to payment.” The Second Addendum also provided that Monsanto would make available enough silica sand to allow SIO to sell up to 25,000 tons of processed sand a year.

*543 The Master Agreement between WGI and SIO expired on December 1, 2005. WGI continued providing silica sand to SIO for two additional years. 2 On December 28, 2007, WGI notified SIO that it would no longer be providing SIO with silica sand after the end of the year. After discussions -with SIO, SIO was permitted to continue processing and bagging sand through April 29, 2008. SIO dismantled its operations in the quarry and removed its building and equipment.

On December 31, 2009, SIO sued Monsanto and WGI for damages for violating and interfering with an alleged verbal agreement to continue processing silica sand. SIO alleged that it and Monsanto entered into a verbal agreement separate and apart from the Master Agreement for the sale of silica sand. SIO alleged that the terms of the verbal agreement were as follows: (1) Monsanto agreed to furnish SIO with certain agreed-upon quantities of silica sand if processed in a safe and environmentally friendly manner; (2) SIO could sell the processed sand to third parties, but Monsanto reserved the right to limit the markets in which SIO could sell the sand; (3) SIO could extract sand from the quarry; and (4) the agreement would remain in full force so long as mutually beneficial to both SIO and Monsanto. SIO further alleged that it and Monsanto understood the agreement to be mutually beneficial so long as (1) SIO conformed to Monsanto’s environmental, safety, and control regulations; (2) SIO paid Monsanto an agreed-upon royalty; and (3) SIO permitted Monsanto to control the markets in which SIO could sell the sand. So long as these requirements were met, SIO alleged the verbal agreement provided that Monsanto would continue to provide sand from the quarry.

Against Monsanto, SIO asserted breach of the alleged verbal agreement, breach of the implied covenant of good faith and fair dealing, equitable estoppel, and quasi-estoppel. Monsanto denied SIO’s claims and asserted the statute of frauds, I.C. § 28-2-201(1), as an affirmative defense. Against WGI, SIO claimed that WGI breached the covenant of good faith and fair dealing implied into the Master Agreement, and SIO alleged that WGI tortiously interfered with the alleged verbal agreement between SIO and Monsanto.

On January 25, 2011, Monsanto and WGI filed motions for summary judgment. Monsanto argued that the verbal agreement was too indefinite and uncertain to constitute a contract, that the verbal agreement was void under the statute of frauds, and that SIO could not prove damages. WGI argued that the verbal agreement was too indefinite and uncertain to constitute a contract, that SIO could not prove damages, and that the verbal agreement is contrary to the express terms of the Master Agreement.

In its opposition to the motions for summary judgment, SIO offered an email correspondence between its employee, Robert Sullivan, and Mitchell Hart, a former employee of Monsanto, from March 13, 2008, (“Hart email”). In that email, Hart, who was SIO’s contact at Monsanto at the time the alleged verbal agreement was formed but no longer works at Monsanto, affirmed that the following was a fair statement of the discussions between SIO and Monsanto: “we both concur that an agreement exists between Monsanto and [SIO] in that Monsanto represented to us that we would be allowed to continue to operate as long as it was mutually beneficial for us to do so.” Monsanto challenged the statement as inadmissible hearsay and sought to strike the email. SIO argued that the statement was not hearsay but was admissible under the residual exception to the hearsay rule provided by I.R.E. 803(24).

On September 21, 2011, the district court entered its Memorandum Decision and Order, which granted Monsanto’s motion to strike the Hart email as inadmissible hearsay. The district court also granted Monsanto summary judgment on the basis that the alleged verbal agreement was unenforceable under the statute of frauds and was vague, indefinite, or uncertain with respect to its essential terms. The district court granted WGI summary judgment on SIO’s claims *544

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Smith
561 P.3d 459 (Idaho Supreme Court, 2024)
Litster v. Litster Frost
Idaho Supreme Court, 2024
TCR, LLC v. Teton County
Idaho Supreme Court, 2024
Von Wandruszka v. City of Moscow
554 P.3d 603 (Idaho Supreme Court, 2024)
Oksman v. City of Idaho Falls
549 P.3d 1086 (Idaho Supreme Court, 2024)
Geringer Capital v. Taunton Properties, LLC
529 P.3d 760 (Idaho Supreme Court, 2023)
White Acres LLC v. Shur-Green Farms LLC
Michigan Court of Appeals, 2022
Merrill v. Smith
477 P.3d 230 (Idaho Supreme Court, 2020)
Berrett v. Clark County School District
454 P.3d 555 (Idaho Supreme Court, 2019)
Budget Truck Sales, LLC v. Tilley
419 P.3d 1139 (Idaho Supreme Court, 2018)
Brent Regan v. Jeff Owen
413 P.3d 759 (Idaho Supreme Court, 2018)
Steelhead Townhomes, L.L.C. v. Clearwater 2008 Note Program, LLC
537 S.W.3d 855 (Missouri Court of Appeals, 2017)
Regan v. Owen
Idaho Supreme Court, 2017

Cite This Page — Counsel Stack

Bluebook (online)
314 P.3d 593, 155 Idaho 538, 82 U.C.C. Rep. Serv. 2d (West) 152, 2013 WL 6190607, 2013 Ida. LEXIS 335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silicon-international-ore-llc-v-monsanto-co-idaho-2013.