Sierra Club v. Wagner

581 F. Supp. 2d 246, 2008 DNH 113, 2008 U.S. Dist. LEXIS 45454, 2008 WL 4560669
CourtDistrict Court, D. New Hampshire
DecidedJune 6, 2008
Docket1:07-cr-00257
StatusPublished
Cited by5 cases

This text of 581 F. Supp. 2d 246 (Sierra Club v. Wagner) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. Wagner, 581 F. Supp. 2d 246, 2008 DNH 113, 2008 U.S. Dist. LEXIS 45454, 2008 WL 4560669 (D.N.H. 2008).

Opinion

ORDER

STEVEN J. McAULIFFE, Chief Judge.

Plaintiffs, the Sierra Club, Forest Watch, and The Wilderness Society (collectively, the “Sierra Club”), bring this action under the Administrative Procedure Act seeking declaratory and injunctive relief. Specifically, they seek a judicial declaration that defendants (collectively, the “Forest Service”) violated the National Environmental Policy Act and the National Forest Management Act when they approved two forest resource management projects in the White Mountain National Forest: the Than Forest Resource Management Project (the “Than Project”) and the Batchelder Brook Vegetation Management Project (the “Batchelder Brook Project”).

Appearing as amici curiae and urging the court to deny the Sierra Club the relief it seeks and to uphold defendants’ approval of the Than and Batchelder projects, are the following entities: The State of New Hampshire; The Society for the Protection of New Hampshire Forests; the Appalachian Mountain Club; the New Hampshire Timberland Owners Association; the North Country Council; and the Audubon Society of New Hampshire. 1

Plaintiffs do not challenge the White Mountain National Forest Land and Resource Management Plan, which was implemented in 2005. Nor do they directly challenge the merits of the two forest resource management projects at issue in this case (though they plainly do not approve of them). Instead, plaintiffs assert that defendants failed to apply the proper statutory and regulatory standards when deciding whether to approve those projects. Accordingly, the court is not called upon to consider either the wisdom or the propriety of the forest resource management projects at issue in this case. Rather, the narrow legal question presented is whether defendants followed the correct procedures and applied the correct statutory and regulatory standards in approving those projects. For the reasons discussed below, the court concludes that they did.

*251 Background

I. The White Mountain National Forest.

The White Mountain National Forest (“WMNF”) was established under the Weeks Law of 1911, which authorized the Secretary of Agriculture to purchase land for the National Forest System. The first land purchase for the WMNF occurred in 1914 and, since then, the forest has grown to encompass nearly 800,000 acres in northern New Hampshire and western Maine. Among other things, the WMNF contains 48 summits of 4,000 feet and higher, both softwood and northern hardwood trees, and a wide variety of plants, birds, fish, and other species.

The WMNF is administered by the Forest Service in accordance with, and to achieve the objectives established in, the comprehensive White Mountain National Forest Land and Resource Management Plan (the “Forest Plan”). The Forest Plan is the product of nine years of research and planning, as well as an extraordinary level of public involvement. The current Forest Plan was adopted in September of 2005. Among other things, it designates 34,500 acres as Recommended Wilderness and 358,000 acres as “General Forest Management Lands.” Within the General Forest Management Lands, approximately 281,000 acres are considered suitable for timber harvesting and, of that total, 97,400 acres (approximately one-third) are located within areas inventoried as “roadless” (discussed below). The Forest Plan allows timber harvesting on approximately 3,400 acres annually, which is less than one-half of one percent of the overall acreage within the WMNF. See Forest Plan, Appendix B, page B-4.

The WMNF is divided into 15 management areas. Id. at page 3-2. As to each, the Forest Plan identifies a purpose, the desired condition of the land, and the standards and guidelines for managing that land. The Forest Plan is, then, somewhat analagous to a city’s zoning ordinance. The objectives of the Forest Plan and the goals established with respect to each of the 15 management areas are achieved by, among other things, implementation of site-level projects. See generally Forest Plan, Preface at page v (“Relationship of the Forest Plan to Site-level Projects”). All forest management, including site-level projects, must comply with the provisions of the Forest Plan. Under the Forest Plan, a site-level project’s environmental analysis “tiers” to the Forest Plan’s Final Environmental Impact Statement (“FEIS”). In other words, a specific project’s environmental analysis may incorporate, by reference, the information in the FEIS, without the need to reiterate it.

Shortly after the current Forest Plan was adopted in 2005, the Forest Service began an on-the-ground evaluation to determine what management actions were necessary to achieve the goals established in the Forest Plan. In the areas covered by the Than and Batchelder Brook projects, the Forest Service identified a need for a wider array of habitats, as represented by vegetation of differing age-classes, including those in the youngest category, known as early-successional stages.

II. Inventoried Roadless Areas (“IRAs”).

Areas within a national forest that are designated as “roadless” meet certain minimum criteria and have characteristics related to natural and wilderness values. To meet the criteria for roadless areas in the eastern United States, land must, among other things, have the following characteristics: it has or is regaining a natural, untrammeled appearance; improvements in the area are being affected by the forces of nature (rather than humans) and are disappearing or muted; the location of the area is conducive to the perpetuation of wilderness values; the area contains no *252 more than one-half mile of improved road for each 1,000 acres; and twenty percent or less of the area has been the subject of timber harvesting within the past 10 years.

As part of the recently-completed revision of the Forest Plan, all land within the national forest was inventoried and assessed to determine which of it qualified as “roadless” (also known as “Inventoried Roadless Areas” or “IRAs”). That inventory resulted in the recognition of 27 road-less areas within the WMNF, totaling more than 403,000 acres (roughly one-half of the entire national forest). All of those IRAs also meet the criteria for designation as Wilderness Areas. See WMNF FEIS, page 2-7. See generally Forest Plan, pages 3-9 through 3-18.

Once an area has qualified as an inventoried roadless area, it is evaluated to determine if it has characteristics consistent with Wilderness. Here, the Forest Plan recommended to Congress that 34,500 acres within the WMNF be designated as Wilderness and placed those lands into Management Area 9.1 (“Recommended Wilderness”) until their recent designation to the Wilderness Preservation System. The remaining roadless areas were assigned to other management areas, based primarily on ecological classification and management history. See, e.g., Batchelder Brook Environmental Assessment at 3-93.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pam Squared at Texarkana, LLC v. Azar
District of Columbia, 2020
United States v. Southern Union Co.
643 F. Supp. 2d 201 (D. Rhode Island, 2009)
Sierra Club v. Wagner
555 F.3d 21 (First Circuit, 2009)
Sierra Club v. Wagner, et al.
2008 DNH 113 (D. New Hampshire, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
581 F. Supp. 2d 246, 2008 DNH 113, 2008 U.S. Dist. LEXIS 45454, 2008 WL 4560669, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-wagner-nhd-2008.