Sierra Club v. Environmental Protection Agency

294 F.3d 155, 352 U.S. App. D.C. 357, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20760, 2002 U.S. App. LEXIS 13141
Court of Appeals for the D.C. Circuit·Decided July 2, 2002·No. 01-1070 & 01-1158·Published·Cited by 55 cases

Opinion

Opinion for the Court filed by Chief Judge GINSBURG.

GINSBURG, Chief Judge:

The Sierra Club petitions for review of a decision by the Environmental Protection Agency approving revisions to the state implementation plans for ozone in the Washington, D.C. Metropolitan Area. The Club contends the EPA was without authority to approve revised SIPs that extend the Area’s deadline for attainment and do not provide for the States concerned to adopt reasonably available control measures, annual rates of progress in reducing emissions, and specific contingency measures to take effect should the Area fail to achieve scheduled reductions in emissions.

We hold that the EPA exceeded its authority and that its decision is otherwise arbitrary and capricious in the above respects. Therefore, we grant the petition and remand this matter to the EPA for further proceedings.

I. Background

Section 109 of the Clean Air Act directs the EPA to promulgate National Ambient Air Quality Standards (NAAQS) for ozone, see 42 U.S.C. § 7409, and Title V of the Act delegates to the states primary responsibility for implementing those standards, see id. §§ 7407, 7410. A state discharges this responsibility by developing and enacting a state implementation plan (SIP) that provides for “implementation, maintenance, and enforcement” of the standards in each “air quality control region” within its jurisdiction, subject to the EPA’s approval and supervision. Id. § 7410(a)(1).

If an area “does not meet the NAAQS or it contributes to ambient air quality in a nearby area that does not meet the NAAQS,” then the EPA designates the area as one of “nonattainment,” id. § 7407(d)(1)(A), and classifies the degree of nonattainment in the area as marginal, moderate, serious, severe, or extreme, see id. § 7511(a), (b)(2). This classification determines both the date by which the area must attain the NAAQS and the stringency of the measures that the area must implement in the meantime to reduce emissions of volatile organic compounds (VOCs) and oxides of nitrogen (NOx), both of which are the precursors of ozone. See id. § 7511(a).

All states were required to revise their SIPs to bring any areas of “serious” nonat-tainment into attainment “as expeditiously as practicable but not later than” November 15, 1999. Id. §§ 7511(a)(1), 7511a(c)(2)(A). The Act specifies that a revised SIP must contain certain elements, including: “the implementation of all reasonably available control measures [RACM],” id. § 7502(c)(1); annual demonstrations of “reasonable further progress,” id. § 7502(c)(2), defined — with an exception not here relevant — as a reduction in the emission of VOCs at a rate of “at least 3 percent of baseline emissions each year,” id. § 7511 a(c) (2) (B) (i); and contingency measures “to be undertaken if the area fails to make reasonable further progress, or to attain” the NAAQS by November 15, 1999, id. § 7502(c)(9). The states were *159 required to submit the revised SIPs to the EPA for approval, which the Agency was required to grant if the “revision [met] all the requirements ... [and] would be adequate to attain and maintain the [NAAQS] by the attainment date specified.” Id. § 76098(a)(1), (2).

An area of serious nonattainment that failed to reach attainment by the deadline was to be reclassified by operation of law to “severe” nonattainment status. See id. § 7511(b)(2)®. The deadline for attainment would then be extended until November 15, 2005, see id. § 7511(a)(1), but the area would be required again to revise its SIP to implement still more rigorous programs for monitoring and reducing emissions, see id. § 7511(b)(2)(A)®.

The Washington, D.C. Metropolitan Area comprises the District of Columbia and several counties each in Maryland and Virginia. In 1991 the EPA declared the Washington Area to be in “serious” nonat-tainment of the NAAQS for ozone. See Designation of Areas for Air Quality Planning Purposes, 56 Fed.Reg. 56,694, 56,738, 56,772, 56,841 (Nov. 6, 1991) (codified respectively at 40 C.F.R. §§ 81.309, .321, .347 (2002)). In response, the District of Columbia Department of Health, the Maryland Department of the Environment, and the Virginia Department of Environmental Quality (hereinafter referred to as “the States”) submitted nonattainment SIPs for the Washington Area, see Approval & Promulgation of Air Quality Implementation Plans, 66 Fed.Reg. 586 (Jan. 3, 2001) (Approval), pursuant to section 172(b) of the Act, 42 U.S.C. § 7502(b).

The three proposed SIPs did not provide for attainment by November 15,1999. See Proposed Rule, Approval & Promulgation of Air Quality Implementation Plans, 64 Fed.Reg. 70,460, 70,476-77 (Dec. 16, 1999) (Proposed Approval). Instead, the States requested that the EPA extend the attainment deadline for the Washington Area until November 15, 2005 without reclassifying as “severe” the nonattainment status of the Area. See id. The EPA previously had recognized that for certain “downwind areas, transport [of ozone] from upwind areas ha[d] interfered with their ability to demonstrate attainment” by the deadlines established in the Act. Extension of Attainment Dates for Downwind Transport Areas, 64 Fed.Reg. 14,441,14,442 (Mar. 25, 1999). As a result, according to the EPA, many downwind areas “fac[ed] the prospect of being reclassified ... to a higher nonattainment classification in spite of the fact that pollution that is beyond their control contributes to the levels of ozone they experience.” Id. With this in mind, the Agency granted the States’ request for an extension, see Approval, 66 Fed.Reg. at 630-31, determining that the transport of ozone and its precursors into the Washington Area could delay the date by which the Area would reach attainment, id.

The States did not propose in their revised SIPs to adopt any RACM, and the EPA concluded that none was warranted because “additional emission control measures would not advance the attainment date.” Id. at 608/1. Nor did the revised SIPs provide for annual rates of progress (ROP) in reducing emissions for the years after 1999, see id. at 603; or for any contingency measures “to make up for any emission reduction shortfall, either in achievement of ROP milestones or for failure to attain” the NAAQS, see id. at 615/2. The EPA determined that these omissions, too, were warranted. It deemed the ROP requirement “unreasonable” in light of the transport of ozone into the Washington Area, id. at 603/2, and it held that contingency measures are not mandatory elements of a SIP revision that establishes the attainment deadline and ROP for an *160 area, see id. at 615/3.

Free access — add to your briefcase to read the full text and ask questions with AI

Sierra Club v. Environmental Protection Agency, 294 F.3d 155, 352 U.S. App. D.C. 357, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20760, 2002 U.S. App. LEXIS 13141 (D.C. Cir. 2002).

294 F.3d 155 (Sierra Club v. Environmental Protection Agency) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vuegen Technologies Inc v. Cissna
District of Columbia, 2020
American Hospital Association v. Azar
District of Columbia, 2019
State of Wisconsin v. EPA
938 F.3d 303 (D.C. Circuit, 2019)
State of Connecticut v. Zinke
District of Columbia, 2018
Connecticut v. U.S. Dep't of the Interior
344 F. Supp. 3d 279 (D.C. Circuit, 2018)
Air Transp. Ass'n of Am., Inc. v. U.S. Dep't of Agric.
303 F. Supp. 3d 28 (D.C. Circuit, 2018)
State of North Dakota v. Regina McCarthy
868 F.3d 1062 (Ninth Circuit, 2017)
Fox Television Stations, Inc. v. Aereokiller
115 F. Supp. 3d 1152 (C.D. California, 2015)
Prevor v. United States Food & Drug Administration
67 F. Supp. 3d 125 (District of Columbia, 2014)
Jacqueline Halbig v. Sylvia Mathews Burwell
758 F.3d 390 (D.C. Circuit, 2014)
Detroit International Bridge Company v. Government of Canada
53 F. Supp. 3d 1 (District of Columbia, 2014)
['ADIRONDACK MEDICAL CENTER v. SEBELIUS']
29 F. Supp. 3d 25 (District of Columbia, 2014)
Sierra Club v. Environmental Protection Agency
705 F.3d 458 (D.C. Circuit, 2013)
Nat Resrc Def Cncl v. EPA
489 F.3d 1364 (D.C. Circuit, 2007)
Natl Resrc Def Cncl v. EPA
D.C. Circuit, 2007