Siemens Westinghouse Power Corp. v. Dick Corp.

293 F. Supp. 2d 336, 2003 U.S. Dist. LEXIS 18496, 2003 WL 22383284
CourtDistrict Court, S.D. New York
DecidedOctober 14, 2003
Docket03 Civ. 364(VM)
StatusPublished
Cited by6 cases

This text of 293 F. Supp. 2d 336 (Siemens Westinghouse Power Corp. v. Dick Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siemens Westinghouse Power Corp. v. Dick Corp., 293 F. Supp. 2d 336, 2003 U.S. Dist. LEXIS 18496, 2003 WL 22383284 (S.D.N.Y. 2003).

Opinion

*338 DECISION AND ORDER

MARRERO, District Judge.

Plaintiff Siemens Westinghouse Power Corporation (“SWPC”) and defendant Dick Corporation (“Dick”) formed a Consortium for the purpose of constructing a power plant in New Hampshire on behalf of global power company AES Corporation (“AES”). Because of delays in the project, SWPC has allegedly paid over $18 million in liquidated damages to AES. SWPC filed a complaint seeking reimbursement for those payments from Dick and from Dick’s sureties, defendants Continental Casualty Company and National Fire Insurance Company of Hartford (collectively, the “Sureties”). There are several parties, and numerous motions, still pending in this case. This Decision and Order addresses only SWPC’s motion for summary judgment against Dick and the Sureties, which was filed together with SWPC’s motion to dismiss Dick’s counterclaims. The motion for summary judgment is granted in part and denied in part.

I. BACKGROUND

In September 2000, Dick and SWPC entered into a Consortium Agreement (the “Consortium”) to build a power plant for AES in Londonderry, New Hampshire. (Comply 12.) The Consortium signed one contract with AES subsidiary AES Lon-donderry, LLC (“AES Londonderry”) and a second contract with AES subsidiary Sycamore Ridge Co., LLC (“Sycamore Ridge”) (collectively, the “Owner”). (Comply 13.) Under those contracts, the Owner assessed liquidated damages against the Consortium in the amount of $85,000 per day beginning June 1, 2002 because the project did not timely achieve what the contract termed “Provisional Acceptance.” (Complin 18, 20.) Dick made the initial liquidated damages payments, totaling around $3.6 million. (Affidavit of Howard F. Jenkins in Support of Plaintiff Siemens Westinghouse Power Corporation’s Motion for Summary Judgment, dated July 17, 2003 (“Jenkins Aff.”) ¶ 5; Statement of Material Facts in Dispute Submitted Pursuant to Local Rule 56.1 in Support of Dick’s and Dick’s Sureties Opposition to SWPC’s Motion for Summary Judgment (“Dick 56.1”) ¶ 7.) For reasons that are disputed, in October 2002 the Owner began drawing its liquidated damages from letters of credit SWPC had posted; those draws totaled about $12 million through March 2003. (Jenkins Aff. ¶ 7, Ex. C.) In April 2003, the Owner and the Consortium entered into two Provisional Acceptance Agreements (one with each Owner), which deemed the project as having achieved Provisional Acceptance and which required the Consortium to pay approximately $6 million in additional liquidated damages. (Id. at ¶ 8.) SWPC paid those damages as well, for a total sum in excess of $18 million. (Id. at ¶ 9.)

SWPC argues that, under the Consortium Agreement, Dick is responsible for paying all the liquidated damages in the first instance. (ComplA 30.) The ultimate apportionment of those damages, according to SWPC, is to be determined according to certain procedures set forth in the Consortium Agreement. (See Plaintiff Siemens Westinghouse Power Corporation’s Memorandum of Law in Support of Its Motions to Dismiss and for Summary Judgment (“SWPC Mem.”) 24.) The Sureties have posted a performance bond on behalf of Dick in connection with the project. (ComplJ 36.) SWPC alleges that the bond incorporates the Consortium Agreement by reference; accordingly, SWPC seeks to hold the Sureties jointly and severally liable for the liquidated damages. (Compl.lHI 35-39.)

Dick reads the Consortium Agreement to require Dick to pay the liquidated dam *339 ages only to the extent of Dick’s fault. (See Memorandum of Law In Support of Defendant/Counter-Plaintiff, Third-Party Plaintiff Dick Corporation’s and Defendants, Continental Casualty Company’s and National Fire Insurance Co. of Hartford’s Opposition to Siemens Westinghouse Power Corporation’s Motion to Dismiss and for Summary Judgment (“Def.Mem.”) 5-12). Dick claims there is at least a genuine issue of material fact as to this point. (Id.) In any event, Dick claims that SWPC made negligent misrepresentations and fraudulently induced Dick into the Consortium, thereby negating Dick’s obligation to pay liquidated damages. (Id. at 13-15.) Dick seeks, in the alternative, discovery under Federal Rule of Civil Procedure 56(f). (Id. at 18-20.) Finally, the Sureties argue that they are not obligated to pay on their bonds until SWPC performs its duties under the Consortium Agreement. (Id. at 20-21.)

II. SUMMARY JUDGMENT STANDARD

The Court may only grant summary judgment “if, the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). The Court must first look to the substantive law of the action to determine which facts are material; “[ojnly disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Even if the parties dispute material facts, summary judgment will be granted unless the dispute is “genuine,” ie., “there is sufficient evidence favoring the nonmoving party for a jury to return a verdict for that party.” Id. at 249, 106 S.Ct. 2505.

Summary judgment is appropriate in cases involving an unambiguous contract because the contract’s interpretation is a matter of law, not fact. Harris Trust and Sav. Bank v. John Hancock Mut. Life Ins. Co., 970 F.2d 1138, 1147-48 (2d Cir.1992), aff'd, 510 U.S. 86, 114 S.Ct. 517, 126 L.Ed.2d 524 (1993). That one party may offer a different interpretation of the contract’s unambiguous language will not defeat summary judgment. Id. Moreover, the mere presence of ambiguous contract language is not, by itself, enough to preclude summary judgment: “in order for the parties’ intent to become an issue of fact barring summary judgment, there must also exist relevant extrinsic evidence of the parties’ actual intent.” Mellon Bank, N.A. v. United Bank Corp. of New York, 31 F.3d 113, 116 (2d Cir.1994). In sum, “[wjhen the provisions of the contract are susceptible to conflicting constructions and when there is also relevant extrinsic evidence of the parties’ actual intent, the meaning of the provisions becomes an issue of fact barring summary judgment.” Williams and Sons Erectors, Inc. v. South Carolina Steel Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Siemens Westinghouse Power Corp. v. Dick Corp.
293 F. Supp. 2d 344 (S.D. New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
293 F. Supp. 2d 336, 2003 U.S. Dist. LEXIS 18496, 2003 WL 22383284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siemens-westinghouse-power-corp-v-dick-corp-nysd-2003.