Siemens Government Technologies, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedJune 2, 2026
Docket26-282
StatusPublished

This text of Siemens Government Technologies, Inc. v. United States (Siemens Government Technologies, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siemens Government Technologies, Inc. v. United States, (uscfc 2026).

Opinion

In the United States Court of Federal Claims No. 26-282C Filed: June 2, 2026 FOR PUBLICATION

SIEMENS GOVERNMENT TECHNOLOGIES, INC.,

Plaintiff,

v.

UNITED STATES,

Defendant.

Michael Bhargava and Logan Kemp, Nichols Law LLP, Washington, DC, for the plaintiff.

Matthew Roche, Civil Division, U.S. Department of Justice, Washington, DC, for the defendant.

MEMORANDUM OPINION

HERTLING, Judge

The plaintiff, Siemens Government Technologies, Inc. (“Siemens”), filed this breach-of- contract case against the defendant, acting through the U.S. Army Corps of Engineers (“the Corps”). Siemens alleges that the Corps violated its contractual obligations regarding the award of an energy savings performance contract (“ESPC”) at Army bases in Wiesbaden, Germany.

ESPCs are performance-based contracts between a federal agency and an Energy Service Company (“ESCO”) to conserve energy at government facilities. ESPCs allow federal agencies to enter multi-year contracts with ESCOs to achieve savings on the cost of energy; these savings on energy costs are then used to offset the payments due to the ESCOs under the ESPCs.

Siemens brings two claims: first, that the Corps violated its obligations under an implied- in-fact contract to consider bids “fairly and honestly”; second, that the Corps violated provisions of the Federal Acquisition Regulations (“FAR”) requiring agencies to conduct business with integrity, fairness, and openness, and to provide offerors a fair opportunity to compete. Siemens claims that it unnecessarily incurred $2,179,177 in bid-preparation costs for an ESPC task order that became nonviable and was therefore not issued due to a failure of the Corps to coordinate internally. Siemens alleges that the Corps’ internal lack of coordination breached the obligations identified above. For relief, Siemens seeks to recover its bid-preparation costs.

The defendant moves to dismiss under Rule 12(b)(1) of the Rules of the United States Court of Federal Claims (“RCFC”), arguing that Siemens’s claims are barred by the provision of the Federal Acquisition Streamlining Act of 1994 (“FASA”) that bars protests in this court in connection with the award of task orders. The defendant also argues that, even if FASA does not bar the claims, the complaint fails to state a claim and must be dismissed under RCFC 12(b)(6) because: (1) the ESPC contract at issue forecloses any implied-in-fact contract on the same subject; (2) the ESPC contract bars recovery of bid-protest costs; (3) the Corps did not owe Siemens a duty to “coordinate internally”; and (4) the alleged regulatory violations do not create an enforceable right of action.

To be barred by FASA, a claim must be “in connection with the issuance or proposed issuance of a task or delivery order.” 10 U.S.C. § 3406(f)(1). As FASA’s task-order bar has been interpreted by the Federal Circuit and other judges of this court, Siemens’s claims are not directly or causally connected to the issuance or non-issuance of a task order. Siemens would need to challenge either the task order’s terms or the Corps’ decision not to award Siemens the task order to draw such a connection. Instead, Siemens seeks reimbursement for its bid- preparation costs. As a result, FASA does not bar Siemens’s claims.

Siemens fails, however, to state a viable claim. The complaint alleges no dishonest or misleading conduct by the Corps and, at most, describes routine procurement decisions that cannot form the basis for liability under the facts as alleged. Siemens’s claim under the FAR also fails, as the Corps did not violate any duty imposed by the FAR. Accordingly, the complaint is dismissed under RCFC 12(b)(6).

I. FACTUAL BACKGROUND

A. The ESPC Program Section 8287 of title 42 of the U.S. Code authorizes federal agencies to use ESPCs as an alternative-financing mechanism to pay for energy-conservation measures. The statute spells out in detail an iterative process under which agencies may develop and issue task orders to ESCOs to implement ESPCs. Prospective contractors must follow this process. To obtain an ESPC task order, a contractor must “conduct a site survey, investigation, feasibility design and study, or similar assessment for the purpose of allowing the contractor to submit a firm, fixed-price proposal to implement specific energy conservation methods.” 42 U.S.C. § 8287(c)(1)(D)(ii).

The statute establishes a two-step procurement process for ESPCs. First, an agency awards an umbrella Indefinite-Delivery Indefinite-Quantity (“IDIQ”) contract to qualified ESCOs. The IDIQ contract makes the participating ESCOs eligible to bid on ESPCs. See 42 U.S.C. § 8287(b). Next, when agencies have identified potential energy-saving projects, they may solicit bids from among the ESCOs that have been awarded the IDIQ contract and award task orders for energy-conservation projects at federal facilities. 42 U.S.C. § 8287(c). ESPC task orders require no up-front capital costs from the agency. Instead, the ESCO awarded any ESPC task order must cover the initial capital costs and are then compensated based on the agency’s energy-cost savings. 42 U.S.C. § 8287(a)(1).

The Department of Energy (“DOE”) has promulgated a rule implementing the statute and establishing the administrative framework and contract structure for ESPCs. 10 C.F.R. pt. 436, subpt. B (2025). During an ESPC task-order procurement, a federal agency issues a solicitation detailing its proposed ESPC project and the projects parameters. The procedures for awarding

2 task orders, as well as the evaluation factors and their relative importance, are also set out in the solicitation for the contract at issue. This summary will refer to the specific elements of this procurement; these elements are consistent with the DOE regulations and reflect the standard process for issuing an ESPC task order.

The performance work statement for this procurement sets out the proposed energy- conservation measures (“ECMs”) that Siemens’s “proposal must discuss.” (ECF 8-1 at 150.) Once Siemens submitted its proposal, the Corps would invite Siemens to move forward to the next phase of the task-order procurement. At this stage in the procurement, Siemens has not been awarded the task order. Rather, Siemens has only been invited to conduct a Preliminary Assessment (“PA”), which is a comprehensive energy audit to identify additional potential ECMs.

A PA culminates in a Preliminary Assessment Report (“PAR”), submitted to the contracting officer. The PAR includes the results of the energy audit, as well as the ESCO’s recommendation about whether a detailed feasibility study (“DFS”) is warranted. A DFS uses information, data, and feedback from the Corps to design and propose ECMs with “a guarantee that the improvements will generate savings sufficient to pay for the project over the term of the contract.” (Id. at 50, 53, 83.) Following the submission of the PAR, the Corps would decide whether to invite Siemens to conduct a DFS. (Id. at 52, 82.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savantage Financial Services, Inc. v. United States
595 F.3d 1282 (Federal Circuit, 2010)
Hercules, Inc. v. United States
516 U.S. 417 (Supreme Court, 1996)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
Sommers Oil Company v. United States
241 F.3d 1375 (Federal Circuit, 2001)
Daniel A. Lindsay v. United States
295 F.3d 1252 (Federal Circuit, 2002)
William O. Schism and Robert Reinlie v. United States
316 F.3d 1259 (Federal Circuit, 2002)
Heyer Products Company v. United States
140 F. Supp. 409 (Court of Claims, 1956)
Sra International, Inc. v. United States
766 F.3d 1409 (Federal Circuit, 2014)
percipient.ai, Inc. v. United States
104 F.4th 839 (Federal Circuit, 2024)
percipient.ai, Inc. v. United States
121 F.4th 1311 (Federal Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Siemens Government Technologies, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siemens-government-technologies-inc-v-united-states-uscfc-2026.