Shotwell v. United States

163 F. Supp. 907, 1 Fed. R. Serv. 2d 835, 1958 U.S. Dist. LEXIS 4062
CourtDistrict Court, E.D. Washington
DecidedJuly 7, 1958
Docket1127
StatusPublished
Cited by6 cases

This text of 163 F. Supp. 907 (Shotwell v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shotwell v. United States, 163 F. Supp. 907, 1 Fed. R. Serv. 2d 835, 1958 U.S. Dist. LEXIS 4062 (E.D. Wash. 1958).

Opinion

DRIVER, District Judge.

Defendant, United States, has moved for summary judgment. The facts on which the motion must be decided are set out in the amended complaint, two affidavits in support of the motion, and two affidavits in opposition thereto.

Amended Complaint

Plaintiff’s amended complaint may be summarized as follows:

On April 3, 1951, defendant, through its Bureau of Reclamation (hereinafter called the Bureau), Department of the Interior, entered into a contract with J. A. Terteling & Sons, Inc. (hereinafter called Terteling), for the construction of a canal and wasteway in connection with the Columbia Basin Project. The contract provided that in the performance of the work the contractor could obtain sand and gravel without charge from the Potholes pit acquired by defendant for use in the construction of the project. On June 19, 1951, Terteling entered into a subcontract with plaintiff whereby the latter was to furnish 25,000 cubic yards of concrete aggregates at a price based on production from the Potholes pit. In the performance of the subcontract the plaintiff, as he had a right to do, entered upon the Potholes pit premises and erected his aggregate processing plant with the approval or acquiescence of the Bureau “personnel” who designated the place where the plant should be erected. The aggregates produced at the plant by plaintiff were inspected by Bureau “inspectors”, in accordance with the specifications of the prime contract.

During and after the time the plaintiff was performing the subcontract, the Bureau had other contracts for construction of various features of the Columbia Basin Project. The other contractors, as well as Terteling, were permitted to obtain concrete aggregates for performance of their contracts free of charge from the Potholes pit.

Bureau “personnel” encouraged plaintiff to extract and process additional concrete aggregates from the Potholes pit to supply the other contractors with concrete aggregates and gave plaintiff permission to sell the same to such other contractors. Plaintiff did then process such additional aggregates, which were inspected by Bureau “inspectors” at the plaintiff’s plant and were sold to the other contractors.

Bureau “personnel” cooperated with the plaintiff in estimating the requirements of concrete aggregates for the other contractors, and plaintiff produced aggregates in accordance with such estimates. In May, 1953, plaintiff had in stockpiles on the Potholes pit approximately 9,000 cubic yards of aggregates produced as part of the estimated requirements for the other contractors of the Bureau.

An Act of Congress authorized the Secretary of the Interior, in his discretion, to permit removal from government lands such as the Potholes pit of sand and gravel, with or without competitive bidding, and the authority was delegated and redelegated so as to vest the same in P. R. Nalder, District Manager of the Columbia Basin Project. The District Manager had knowledge of plaintiff’s operations in producing aggregates and selling the same to contractors other than Terteling, and specifically of the stockpiling of the 9,000 cubic yards of aggregates on hand in May, 1953. Plaintiff’s operations were encouraged by “personnel” of the Bureau who were under the supervision of the District Manager. The plaintiff was permitted to operate just as though he had a formal permit, and, in effect, did have a permit to extract free of charge and to process concrete aggregates from the Potholes pit exclusively for sale to Bureau contractors with contracts which contained provisions similar to those in Terteling’s prime contract (i. e., permission to obtain concrete aggregates from the Potholes pit free of charge). The plaintiff at his own substantial expense produced and stockpiled the 9,000 cubic yards of *910 aggregates on hand in May, 1953, in reliance upon such permit and the course of conduct of “defendant’s officers and employees.”

On May 19, 1953, the District Manager directed plaintiff to vacate the Potholes pit and the defendant converted the aggregates to its own use and sold the same to plaintiff’s damage in the sum of $13,-950.

Affidavits in Support of Motion For Summary Judgment

The affidavit of P. R. Nalder recites: On and subsequent to December 21, 1952, P. R. Nalder was the District Manager of the Columbia Basin Project. One of his duties was the granting or refusing to grant permits for the removal of aggregates from project lands. Attached to Nalder’s affidavit as exhibits are documents with notations of publication in the Federal Register, showing the delegation of authority to grant permits from the Secretary through subordinates to the officer in charge, who was the Project Manager. As shown by such documents, permits were required to be in writing, and unless a permit was issued on competitive bids, after advertising, a charge was to be made for the aggregates, based on local prevailing rates. The land known and described as the Potholes pit at all times involved in the present action was owned by the United States, and was being administered by the Bureau for the purposes of the Columbia Basin Project. No permit was granted to the plaintiff to remove aggregates from the Potholes pit, or to extract the same therefrom and stockpile it for purposes of sale. Nalder had no knowledge of the removal and sale, or of the stockpiling of aggregate from the Potholes pit by the plaintiff until on or about May 19', 1953, when he promptly by letter informed plaintiff that he had no title to such aggregate, and requested that he immediately vacate the premises.

The affidavit of H. A. Parker states: At all times pertinent to the present action prior to December 21, 1952, H. A. Parker was the District Manager of the Columbia Basin Project, and as such had the same authority as his successor, P. R. Nalder, with reference to permits for the removal of aggregates from project lands, including the Potholes pit. No employee of the Bureau subordinate to Parker had any authority to grant such permits, and no one, including Parker, had authority to grant oral permits. No permit was ever granted to the plaintiff. Parker had no knowledge of the removal and sale or the stockpiling of aggregate from the Potholes pit while he was in charge of the Columbia Basin Project, by the plaintiff.

Affidavits In Opposition to Motion for Summary Judgment

A summary of the affidavit of plaintiff is as follows: The plaintiff knows all of the allegations of fact in the amended complaint to be true of his own personal knowledge, “or on information and belief” believes “them to be true.” In the summer or fall of 1951, accompanied by his superintendent, William McConnell, plaintiff called on Marvin Hawkins “project materials engineer” for the Bureau, in his office in Ephrata, Washington. The conference was for the purpose of determining the quantity of concrete aggregates that would probably be needed by the various Bureau contractors within reasonable hauling distance of the Potholes pit in 1952-1953. The Bureau, and Hawkins in particular, encouraged plaintiff to sell concrete aggregates to various contractors in the summer and fall of 1951, and, in one instance, to sell to a supplier who was not a contractor. Hawkins also encouraged plaintiff to produce and stockpile estimated requirements of 10,000 cubic yards for such contractors in 1952 and 1953. Plaintiff accordingly

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sargeant v. Government of the Virgin Islands
10 V.I. 245 (Virgin Islands, 1973)
United States v. Georgia-Pacific Company
421 F.2d 92 (Ninth Circuit, 1970)
Bond Distributing Co. v. Carling Brewing Co.
32 F.R.D. 409 (D. Maryland, 1963)
Dovberg v. Dow Chemical Co.
195 F. Supp. 337 (E.D. Pennsylvania, 1961)
Dovberg v. Dow Chemical Company
195 F. Supp. 337 (E.D. Pennsylvania, 1961)
Fagan v. Pennsylvania Railroad Company
173 F. Supp. 465 (M.D. Pennsylvania, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
163 F. Supp. 907, 1 Fed. R. Serv. 2d 835, 1958 U.S. Dist. LEXIS 4062, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shotwell-v-united-states-waed-1958.