Shore v. Haverson Architecture & Design, P.C.

886 A.2d 837, 92 Conn. App. 469, 2005 Conn. App. LEXIS 505
CourtConnecticut Appellate Court
DecidedDecember 6, 2005
DocketAC 25945
StatusPublished
Cited by21 cases

This text of 886 A.2d 837 (Shore v. Haverson Architecture & Design, P.C.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shore v. Haverson Architecture & Design, P.C., 886 A.2d 837, 92 Conn. App. 469, 2005 Conn. App. LEXIS 505 (Colo. Ct. App. 2005).

Opinion

Opinion

McLACHLAN, J.

In these consolidated cases involving an arbitration award, Haverson Architecture & Design, P.C. (Haverson) appeals from the judgment of the trial court, denying its application to vacate the award rendered in favor of Marc P. Shore and Debra Shore and granting the Shores’ application to confirm [471]*471the award.1 On appeal, Haverson claims that the court improperly (1) confirmed the arbitrator’s award, (2) refused to hear testimony from the arbitrator, (3) refused to grant Haverson’s motion for reconsideration and (4) granted the Shores’ application for a prejudgment remedy. We affirm the judgment of the trial court.

On June 26, 2001, the Shores hired Haverson to perform architectural services for their main house and carriage house. Pursuant to a written agreement, the parties agreed to submit claims or disputes to arbitration in accordance with the construction industry arbitration rules of the American Arbitration Association (association). On or about January 24, 2003, Haverson filed a demand for arbitration with the association, claiming that the Shores owed it money for various items. The Shores denied Haverson’s claims and submitted counterclaims for construction problems and for substantial underestimation of the construction costs.

Arbitration hearings were conducted on four days in July, 2003, and then again on two days in February, 2004. Posthearing briefs were submitted on March 15 and 16,2004. In a letter dated March 22,2004, the association notified the parties that (1) the posthearing briefs had been transmitted to the arbitrator on March 16, 2004, (2) the arbitrator had declared that the hearings would be closed as of March 29, 2004, and (3) the arbitrator would render the award within thirty days from the closing of the hearings, April 28, 2004.

On April 28, 2004, the association sent the parties a copy of the arbitrator’s written award by facsimile transmission. The award denied all of Haverson’s claims [472]*472and granted both of the Shores’ counterclaims, awarding the Shores $89,200. On April 30,2004, the association sent the parties, by facsimile transmission, a copy of the arbitrator’s modification of award, signed on April 29, 2004. The modification added two sentences that had been cut off at the bottom of the first page of the original award and did not change the substance of the original award.

On May 12, 2004, Haverson wrote to the association, requesting correction or vacation of the award. The association denied the request on June 2,2004. On June 16, 2004, the Shores filed an application in court to confirm the award. On July 20, 2004, Haverson filed an application in court to vacate the award on the grounds that (1) the award was not timely made, (2) the arbitrator failed to abide by the association’s rules and procedure and (3) the award was arbitrary, capricious and without support in the record. The actions were consolidated, and on September 7, 2004, the court granted the Shores’ application to confirm the award and denied Haverson’s application to vacate. On October 25, 2004, the court denied Haverson’s motion for reconsideration and granted the Shores’ application for a prejudgment remedy. This appeal followed. We address each claim in turn.

I

We first address Haverson’s claim that the court improperly confirmed the decision of the arbitrator. Specifically, Haverson claims that (1) the arbitrator failed to render an award within the time frame required by the association’s rules, as provided in the submission, (2) the award rendered by the arbitrator on April 28, 2004, was incomplete and (3) the arbitrator failed to respond to a request to correct the award.

In determining whether the court improperly upheld the arbitration award, we first set forth our standard [473]*473of review. “Judicial review of arbitral decisions is narrowly confined. . . . When the parties agree to arbitration and establish the authority of the arbitrator through the terms of their submission, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . . Because we favor arbitration as a means of settling private disputes, we undertake judicial review of arbitration awards in a manner designed to minimize interference with an efficient and economical system of alternative dispute resolution.” Industrial Risk Insurers v. Hartford Steam Boiler Inspection & Ins. Co., 273 Conn. 86, 92-93, 868 A.2d 47 (2005). Here, the parties’ arbitration agreement was unrestricted,2 thus limiting the scope of review. Nonetheless, courts can vacate an award even in the case of an unrestricted submission when “(1) the award rules on the constitutionality of a statute . . . (2) the award violates clear public policy . . . [or] (3) the award contravenes one or more of the statutory proscriptions of [General Statutes] § 52-418. . . . [Section] 52-418 (a) (4) provides that an arbitration award shall be vacated if the arbitrators have exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.” (Citation omitted; internal quotation marks omitted.) Industrial Risk Insurers v. Hartford Steam Boiler Inspection & Ins. Co., supra, 94. Here, [474]*474Haverson claims that the arbitrator’s award contravenes the proscriptions of § 52-418 (a) (4) because a mutual, final and definite award was not made. We disagree.

Our Supreme Court in Industrial Risk Insurers stated: “In our construction of § 52-418 (a) (4), we have, as a general matter, looked to a comparison of the award with the submission to determine whether the arbitrators have exceeded their powers. . . . [A]n award that manifests an egregious or patently irrational application of the law is an award that should be set aside pursuant to § 52-418 (a) (4) because the arbitrator has exceeded [his] powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.” (Citations omitted; internal quotation marks omitted.) Id., 94-95. In this case, the arbitrator was bound to abide by the construction industry arbitration rules of the association. The arbitrator did not exceed his powers under those rules or so imperfectly execute them that a mutual, final and definite award was not made.

A

Haverson claims that the arbitrator failed to render an award within the time frame required by the submission. Rule 42 of the construction industry arbitration rules provides that “[t]he award shall be made promptly by the arbitrator and, unless otherwise agreed by the parties or specified by law, no later than 30 calendar days from the date of closing the hearing, or, if oral hearings have been waived, from the date of the [association’s] transmittal of the final statements and proofs' to the arbitrator.” The arbitrator informed the parties on March 22, 2004, that the hearing would be closed on March 29, 2004, therefore requiring him to render an award by April 28, 2004. Haverson contends that the closing date should have been on March 16, 2004, when [475]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fain v. Benak
205 Conn. App. 734 (Connecticut Appellate Court, 2021)
Telman v. Hoyt
194 Conn. App. 377 (Connecticut Appellate Court, 2019)
DeRose v. Jason Robert's, Inc.
Connecticut Appellate Court, 2019
Benistar Employer Services Trust Co. v. Benincasa
207 A.3d 67 (Connecticut Appellate Court, 2019)
Hall v. Hall
191 A.3d 182 (Connecticut Appellate Court, 2018)
Ray v. Ray
173 A.3d 464 (Connecticut Appellate Court, 2017)
Rose B. v. Dawson
169 A.3d 346 (Connecticut Appellate Court, 2017)
Fort Trumbull Conservancy, LLC v. Alves
57 A.3d 898 (Connecticut Appellate Court, 2013)
Fort Trumbull Conservancy, LLC v. City of New London
43 A.3d 679 (Connecticut Appellate Court, 2012)
Girolametti v. Rizzo Corp.
77 A.3d 217 (Connecticut Superior Court, 2012)
Swanson v. City of Groton
977 A.2d 738 (Connecticut Appellate Court, 2009)
Minichino v. Minuit
952 A.2d 62 (Connecticut Appellate Court, 2008)
Harris v. Commissioner of Correction
947 A.2d 7 (Connecticut Appellate Court, 2008)
Konefal v. Konefal
945 A.2d 484 (Connecticut Appellate Court, 2008)
Lefebvre v. Zarka
940 A.2d 911 (Connecticut Appellate Court, 2008)
Chase v. Cohen
519 F. Supp. 2d 267 (D. Connecticut, 2007)
Skinner v. Doelger
915 A.2d 314 (Connecticut Appellate Court, 2007)
Mangiante v. Niemiec
910 A.2d 235 (Connecticut Appellate Court, 2006)
Valentine v. LaBow
897 A.2d 624 (Connecticut Appellate Court, 2006)
Shore v. Haverson Architecture & Design, P.C.
894 A.2d 988 (Supreme Court of Connecticut, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
886 A.2d 837, 92 Conn. App. 469, 2005 Conn. App. LEXIS 505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shore-v-haverson-architecture-design-pc-connappct-2005.