Sholar Group Architects, P.C. v. Sooper Credit Union

97 P.3d 258, 2004 WL 352094
CourtColorado Court of Appeals
DecidedSeptember 13, 2004
Docket02CA2559
StatusPublished
Cited by1 cases

This text of 97 P.3d 258 (Sholar Group Architects, P.C. v. Sooper Credit Union) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sholar Group Architects, P.C. v. Sooper Credit Union, 97 P.3d 258, 2004 WL 352094 (Colo. Ct. App. 2004).

Opinion

Opinion by

Judge MARQUEZ.

In this proceeding arising out of arbitration of a construction contract dispute, plaintiff, Sholar Group Architects, P.C., appeals the trial court’s order confirming the arbitrator’s corrected award in favor of defendant, Sooper Credit Union. We reverse and remand.

Plaintiff and defendant entered into a series of three agreements for plaintiff to provide design services and construction for the remodeling of defendant’s office building. Work was completed and payment made pursuant to two of the agreements. When a dispute arose over labor charges under the remaining agreement, plaintiff commenced an arbitration proceeding with the American Arbitration Association (AAA), as provided in the agreement.

Following a five-day hearing, the arbitrator awarded plaintiff $199,338, with costs of the arbitration to be borne equally by the parties. Plaintiff then filed an application for confirmation of the arbitration award and a motion for correction and modification in the district court, alleging obvious mathematical errors that would increase the award by approximately $11,200. On the same day, defendant filed a motion to correct award calculations. Defendant alleged that because both the disputed inflated labor charges and the corrected charges were included, computational errors in the original award would cause it to “double-pay” labor charges.

The arbitrator replied to the parties that he “did miscalculate some figures in the body of [his] initial award” and was “prepared to correct that miscalculation,” but needed specific direction from the trial court. Subsequently, the trial court submitted defendant’s motion to the arbitrator, and he issued his corrected award, giving defendant $223,063 plus a portion of the arbitration fees. Upon defendant’s motion, the trial court confirmed the corrected award.'

I.

Plaintiff contends that the trial court erred in confirming the corrected award 'and failing to reinstate the original award because the arbitrator exceeded his statutory powers to modify the original award and improperly redetermined the merits of the case. We agree.

As a threshold matter, the agreement at issue provided that arbitration was to be conducted in accordance with the “Construction Industry Mediation or Arbitration Rules of the American Arbitration Association” then currently in effect. The rules allow a party, after the initial award, to “request that the arbitrator correct any clerical, typographical, technical or computational errors in the award,” and the arbitrator “is not empowered to redetermine the merits of any claim already decided.” AAA Construction Industry Arbitration Rule R-49 (2001).

In their motions to correct, both parties cited pertinent Colorado statutes, and the trial court submitted defendant’s motion to the arbitrator for consideration in accordance with § 13-22-211, C.R.S.2003. However, at oral argument defendant’s counsel argued that the arbitration rules provided broader grounds for modification. This argu *260 ment was not raised before the trial court, and defendant has provided no authority in support. In view of defendant’s reliance on the statutes before the trial court, we consider the question waived and proceed with an analysis under the statutes. See First Interstate Bank v. Cent. Bank & Trust Co., 937 P.2d 855 (Colo.App.1996)(arguments not presented to, considered by, or ruled upon by trial court may not be raised for first time on appeal).

Upon application of a party, the court shall vacate an award where the arbitrators exceeded their powers. Section 13-22-214(l)(a)(III), C.R.S.2003. In the absence of appropriate grounds to modify, vacate, or correct an award, a trial court is required to affirm the award without review of the merits. McNaughton & Rodgers v. Besser, 932 P.2d 819 (Colo.App.1996).

Section 13-22-211 provides in part that the arbitrator’s authority to modify or correct an award is limited:

On application of a party or, if an application to the court is pending under section 13-22-213, 13-22-214, or 13-22-215, on submission to the arbitrators by the court under such conditions as the court may order, the arbitrators may modify or correct the award upon the grounds stated in section 13-22-215(l)(a) and (l)(c) or for the purpose of clarifying the award.

Section 13-22-215(1) provides that the award shall be modified or corrected where:

(a) There was an evident miscalculation of figures or an evident mistake in the description of any person, thing, or property referred to in the award;
[[Image here]]
(e) The award is imperfect in a matter of form, not affecting the merits of the controversy.

Thus, when an arbitrator issues an award and delivers it to the parties, amendment or modification of the award by the arbitrator is permitted only under the narrow circumstances listed in § 13-22-211. Applehans v. Farmers Ins. Exch., 68 P.3d 594 (Colo.App.2003).

A.

We agree with plaintiffs assertion that the arbitrator exceeded his powers to modify the award because the corrected award does not properly remedy an “evident miscalculation of figures.”

Plaintiff relies on Foust v. Aetna Casualty & Insurance Co., 786 P.2d 450, 451 (Colo.App.1989), and In re Marriage of Gavend, 781 P.2d 161 (Colo.App.1989), both of which quote Morrison-Knudsen Co. v. Makahuena Corp., 66 Haw. 663, 669, 675 P.2d 760, 765 (1983), as follows: “An ‘evident miscalculation of figures’ refers only to ‘mathematical errors committed by arbitrators which would be patently clear to a reviewing court.’ ” Plaintiff asserts, pursuant to Applehans, the term “evident miscalculation of figures” can only mean mathematical errors that appear on the face of the award. According to plaintiff, because an arbitrator may modify the award only on the same limited grounds as may a reviewing court, the arbitrator cannot review the record of the arbitration, and the arbitrator must rely solely upon the information contained within the four corners of the original award. While we apply a slightly different standard, we agree the corrected award cannot stand.

The division in Foust concluded that modification of an arbitration award is authorized under § 13-22-215(l)(a) “only if it seeks to effectuate the clearly expressed intent of the arbitrator by correcting a mathematical error without altering his conclusion on the merits.” Foust v. Aetna Cas. & Ins. Co., supra, 786 P.2d at 451-52. In Foust,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sooper Credit Union v. Sholar Group Architects, P.C.
113 P.3d 768 (Supreme Court of Colorado, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
97 P.3d 258, 2004 WL 352094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sholar-group-architects-pc-v-sooper-credit-union-coloctapp-2004.