Shirley's Iron Works, Inc. v. City of Union

743 S.E.2d 778, 403 S.C. 560, 2013 WL 2325263, 2013 S.C. LEXIS 123
CourtSupreme Court of South Carolina
DecidedMay 29, 2013
DocketAppellate Case No. 2010-170066; No. 27256
StatusPublished
Cited by72 cases

This text of 743 S.E.2d 778 (Shirley's Iron Works, Inc. v. City of Union) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shirley's Iron Works, Inc. v. City of Union, 743 S.E.2d 778, 403 S.C. 560, 2013 WL 2325263, 2013 S.C. LEXIS 123 (S.C. 2013).

Opinion

Justice KITTREDGE.

This case concerns the interplay between the Subcontractors’ and Suppliers’ Payment Protection Act (SPPA)1 the Tort Claims Act (TCA)2, and this Court’s opinion in Sloan Construction Co. v. Southco Grassing, Inc. (Sloan I), 377 S.C. 108, 659 S.E.2d 158 (2008). When subcontractors Shirley’s Iron Works, Inc. and Tindall Corporation (collectively Respondents) did not receive full payment from the general contractor Gilbert Group, LLC (Gilbert) for their work on a public construction project for the City of Union (the City), they filed suit, asserting the City failed to comply with the statutory bond requirements pertaining to contractors working with subcontractors on public projects found in the SPPA. The circuit court granted summary judgment to the City. The court of appeals reversed and remanded. Shirley’s Iron Works, Inc. v. City of Union, 397 S.C. 584, 726 S.E.2d 208 (Ct.App.2009). We granted a writ of certiorari to review the court of appeals decision. We now affirm in part, reverse in part, and remand. Further, we clarify Sloan I and hold that a governmental entity may be liable to a subcontractor only for breach of contract for failing to comply with the SPPA bonding requirements.

I.

In 2002, the City issued a request for proposals for the design and construction of a spec building. Thereafter, the City contracted with Gilbert for the project, the cost of which totaled approximately $875,000. Gilbert entered into contractual agreements with various subcontractors, including Respondents. The City did not require Gilbert to secure a payment bond, and it is undisputed no payment bond was secured. Ultimately, Gilbert failed to fully compensate all of the subcontractors after they completed work on the project.

At the project’s completion, the City contended it owed $111,270 on its contract with Gilbert. Respondents also had significant unpaid invoices.3 After the City was notified of [565]*565Gilbert’s failure to pay its subcontractors,4 the City offered to distribute the balance of its contract with Gilbert to the unpaid subcontractors in exchange for a release of the City’s liability. The City offered each Respondent $25,000. Upon Respondents’ refusal to accept the offer and execute a release in favor of the City, the City distributed their pro rata portions to the other unpaid subcontractors.

In 2003, Respondents filed a Complaint against the City, alleging the City should be required to pay the amounts owed under their respective subcontracts because the City failed to require Gilbert to secure a payment bond in violation of S.C.Code Ann. section 29-6-250.5 Respondents also requested attorney’s fees pursuant to S.C.Code Ann. section 15-77-300 (Supp.2012).6 The City filed an answer denying Respondents’ allegations. The City also filed a third-party complaint against Gilbert, alleging Gilbert was negligent in failing to acquire a payment bond.

In 2004, Judge Paul Short granted the City’s motion to strike Respondents’ request for attorney’s fees.7 No appeal was taken from the order granting the motion to strike.

In August 2005, Respondents filed an Amended Complaint against the City and Gilbert, asserting third-party beneficiary status of the contract between the City and Gilbert, alleging [566]*566Gilbert failed to pay Respondents for their work, and contending the City failed to require Gilbert to secure a payment bond in violation of the SPPA. This Amended Complaint was considerably more detailed than the original complaint. In the “Facts” section, Respondents contended section 29-6-250(1) created an obligation on the City to ensure that a payment bond is in place to protect subcontractors and is a term of the City’s contract with Gilbert. Respondents asserted they were third-party beneficiaries of the City’s contract with Gilbert because the bonding requirements of section 29-6-250 serve to protect Respondents as subcontractors and are “legislatively mandated contractual obligations” incorporated into the contract as a matter of law. Respondents argued they were damaged by the City’s breach of its statutorily imposed contractual obligation to secure a payment bond from Gilbert. Respondents asserted causes of action for (1) “[violation of S.C.Code Ann. [section] 29-6-250,” (2) attorney’s fees for violation of S.C.Code Ann. section 27-1-15, (3) negligence, (4) quantum meruit, and (5) attorney’s fees and prejudgment interest.

Thereafter, Judge Steven John granted the City’s motion to strike Respondents’ claims for attorney’s fees and prejudgment interest. Judge John noted that Judge Short’s previous order stated Respondents’ original complaint sounded in tort, and that attorney’s fees and prejudgment interest were not available under the TCA. Judge John held that Judge Short’s unappealed order “constitute^] the law of the case,” which he was “bound to apply.”

Subsequently, both parties moved for summary judgment. Judge John Few granted the City’s motion for summary judgment on all of Respondents’ causes of action and denied Respondents’ motion. Judge Few found Respondents’ claims sounded in tort and were barred by the TCA. Additionally, Judge Few held that a governmental entity’s violation of the SPPA does not give rise to a private cause of action by a subcontractor.8 Respondents appealed, and the court of appeals reversed and remanded.

[567]*567Specifically, the court of appeals reversed Judge Few’s findings with respect to Respondents’ negligence claim, holding that the SPPA provided for a tort cause of action which was not governed by the TCA. The court reasoned that Sloan I supported its conclusion. Additionally, the court of appeals held Judge John’s and Judge Short’s previous orders stating Respondents’ claims sounded in tort were not the law of the case and Respondents’ Amended Complaint, when read as a whole, sufficiently pled a third-party beneficiary breach of contract cause of action for violation of the SPPA. Concluding a ruling on the merits would be premature, the court of appeals remanded to the circuit court for findings regarding Respondents’ tort, breach of contract, and quantum meruit claims to determine liability and damages.9 This court granted the City’s writ of certiorari to review the court of appeals opinion.

II.

In reviewing a grant of summary judgment, the appellate court applies the same standard as the trial judge under Rule 56(c), SCRCP. Bovain v. Canal Ins., 383 S.C. 100, 105, 678 S.E.2d 422, 424 (2009). Summary judgment is proper if, viewing the evidence in a light most favorable to the nonmoving party, there is no genuine issue of material fact and the moving party is entitled to a judgment as a matter of law. Id.

III.

A.

With the enactment of the TCA in 1986, the legislature intended to remove the common law bar of sovereign immunity in certain circumstances, but only to the extent legislatively authorized. See S.C.Code Ann.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joe Adams, Jr. v. Betty Ogbuneke
Court of Appeals of South Carolina, 2025
State v. Larry J. Scipio, Jr.
Court of Appeals of South Carolina, 2025
The Estate of Fannie M. Champion v. Ronald L. Hallman
Court of Appeals of South Carolina, 2025
Martha Coleman v. Jeffrey Coleman
Court of Appeals of South Carolina, 2025
Janet Mewshaw v. Philip Pringle
Court of Appeals of South Carolina, 2025
Cynthia Strong v. Jack Strong
Court of Appeals of South Carolina, 2025
Crescent Homes SC, LLC v. CJN, LLC
Court of Appeals of South Carolina, 2024
Summerlake Townhomes HOA v. True Homes, LLC
Court of Appeals of South Carolina, 2024
Julia Sibley-Jones v. Decide4Action, Inc. (2)
Court of Appeals of South Carolina, 2024
Saundra Hoffman v. State Farm
Court of Appeals of South Carolina, 2024
Josh Hawkins v. American Airlines
Court of Appeals of South Carolina, 2024
Stephanie Gardner v. Berkeley County Sherriff's Office
Court of Appeals of South Carolina, 2024
Olivia M. Thompson v. College of Charleston
Court of Appeals of South Carolina, 2023
Amenhotep Myers v. SCDMV
Court of Appeals of South Carolina, 2023
Michael Halsema v. Paige Earley
Court of Appeals of South Carolina, 2023
Jordan v. Marian J. Kirk
Court of Appeals of South Carolina, 2023
Innovative Waste Management v. Crest Energy Partners
Court of Appeals of South Carolina, 2023

Cite This Page — Counsel Stack

Bluebook (online)
743 S.E.2d 778, 403 S.C. 560, 2013 WL 2325263, 2013 S.C. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shirleys-iron-works-inc-v-city-of-union-sc-2013.