Shirley R. Hulsey v. Build Art, LLC

Supreme Court of Alabama·Decided April 17, 2026·No. SC-2025-0564·Published

Opinion

Rel: April 17, 2026

Notice: This opinion is subject to formal revision before publication in the advance sheets of Southern Reporter. Readers are requested to notify the Reporter of Decisions, Alabama Appellate Courts, 300 Dexter Avenue, Montgomery, Alabama 36104-3741 ((334) 229-0650), of any typographical or other errors, in order that corrections may be made before the opinion is printed in Southern Reporter.

SUPREME COURT OF ALABAMA OCTOBER TERM, 2025-2026

SC-2025-0564

Shirley R. Hulsey

v.

Build Art, LLC

Appeal from Tuscaloosa Circuit Court (CV-20-900281)

MENDHEIM, Justice.

Shirley R. Hulsey appeals from a summary judgment entered by the Tuscaloosa Circuit Court in favor of Build Art, LLC ("Build Art"), in

her tort action against Yellow Hammer Capital Management, LLC ("Yellow Hammer"), Build Art, and fictitiously named defendants.

In December 2011, Hulsey and her husband purchased their residence in Tuscaloosa as joint tenants with the right of survivorship. In August 2017, Yellow Hammer purchased the lot adjacent to Hulsey's residence ("lot 22"). Lot 22 was at a higher elevation than and sloped toward Hulsey's lot. Also, Hulsey's lot had a retaining wall along much of its length, near or on the common boundary with lot 22. Between the retaining wall and Hulsey's residence was a side yard that was several feet wide.

According to an affidavit from Marcus Minges, the managing member of Build Art, Yellow Hammer retained Build Art to construct a residence on lot 22. Build Art is owned by Yellow Hammer and Minges. In November 2017, Build Art applied for a building permit, which it received. In approximately January 2018, Build Art began construction on the residence with the assistance of a number of subcontractors. According to Minges, "[t]here was no need for excavating and/or grade work on Lot 22 because the lot was build ready when Build Art began work." Minges also averred that "Build Art's employees did not perform

excavations or grading on the project. Build Art did not supply excavating equipment for use by any of its subcontractors. Build Art did not exercise control over the manner in which any excavation, grading, or landscaping of Lot 22 was performed." However, in Build Art's interrogatory answers that Hulsey filed in opposition to its motion for a summary judgment, it responded as follows:

"7. Please identify the persons or entities who designed, reconfigured, constructed excavated, cut, filled and performed work to Lot 22 Neptune's Cove at NorthRiver Phase One.

"ANSWER: [Build Art] object[s] to this Interrogatory as being vague. Without waiving this objection, Marcus Minges."

Construction on the lot-22 residence was completed, and a certificate of occupancy was issued in August 2019.

A preconstruction picture of lot 22 reflects a slight downward slope in the side yard from Hulsey's residence to near the bottom of the retaining wall. According to Hulsey's deposition testimony, she had never seen any water coming off of lot 22 onto her lot before construction began on lot 22. Hulsey stated that lot 22 originally was not flat but was "a turtle back … where the water would flow back to the front. … So when they went in there to make that land level enough to do a

foundation, it took that drainage away." She stated that she first noticed water coming onto her lot from lot 22 in April 2018, "when the [silt fence] screen … overloaded with mud and caused it to breach, and that's when it dumped in my yard." Hulsey stated that when the silt fence collapsed, "it dumped close to four inches of dirt in my backyard that flowed almost all the way through my backyard," filling up the sloped area that drained the side yard between the lots and her back yard and "creating a dam" that restricted the water flow from her property. She stated that, after the silt fence failed, she brought the issue to "the contractor's attention," but he did nothing about it. Hulsey stated that, after lot 22 was graded and construction was completed, the silt fence was removed and water continued to flow onto her property thereafter. Postconstruction pictures of the side yard at issue reflect that the slope from the retaining wall was toward, rather than away from, Hulsey's residence.

John Stevens, a civil engineer who had been retained by Hulsey, testified in his deposition that he had experience on hydrology issues and the "flow of water from rain." He stated that he had designed stormwater systems and also had provided structural reports to various clients. He stated that he did not consider himself an expert in the field of hydrology,

but considered himself a "semi-expert," which he defined as meaning that he did not take jobs that he did not understand. When asked about jobs that he had taken on in the last 10 years regarding the flow of water, Stevens stated that some were for businesses, "but most of them [were] homes that they can't stop water from getting in" and "[t]here's damage because of the water getting into the homes -- … -- either slabs or crawl space."

According to Stevens, the foundation of Hulsey's residence was failing, the house was sinking, and he had recommended that helical piers be used to shore up the side of the house nearest to lot 22. He also had recommended that pressure grouting be used to support any hollow area under the slab. Stevens testified that cracks on the side of Hulsey's residence were "the type of cracks you see when the footing is moving." According to Stevens, he did not think that there was any possible cause for the cracks other than the soil being saturated under the slab.

In March 2020, Hulsey filed a complaint against Yellow Hammer, Build Art, and numerous fictitiously named defendants, including those persons "whose names [were] not yet known and who [had] performed

services on all or part of Lot 22, or adjacent to Lot 22."1 Hulsey alleged that Yellow Hammer, Build Art, and the fictitiously named defendants had caused her and her residence to suffer damage based, in part, on the defendants having

"knowingly, intentionally, recklessly, wantonly and/or negligently effected demolition, clearing, grading, development and construction as part of their efforts to develop and sell a new house on Lot 22. The erection of the house on Lot 22 (such work includes, but is not limited to[,]

design, demolition, construction clearing, grading, repair, and the maintenance associated therewith) was done in such a manner that such activity has caused the wrongful flooding of surface waters, silt and debris onto the Hulsey Property via surface water run-off."

Hulsey alleged against "all the defendants" claims of trespass, nuisance, wrongful infliction of mental anguish and emotional distress, negligence, wantonness, and a violation of her common-law right regarding the natural flow of surface water as discussed in Sargent v. Lambert Construction Co., 378 So. 2d 1153, 1155 (Ala. Civ. App. 1979). In addition to requesting compensatory and punitive damages, Hulsey also

1Hulsey's husband also was a plaintiff. However, he died on December 15, 2021. Pursuant to Rule 24, Ala. R. Civ. P., Build Art filed a suggestion of death regarding Hulsey's husband. After no substitution was made for him, Build Art filed a motion to dismiss his claims, which the circuit court granted.

requested permanent injunctive relief regarding the allegedly altered water flow from lot 22 onto her lot.

Build Art filed an answer denying Hulsey's allegations and alleging numerous affirmative defenses. Yellow Hammer filed a motion to dismiss, which also included a statement denying Hulsey's allegations. A hearing was set to be held on June 29, 2020, on the motion to dismiss. On June 30, 2020, the circuit court entered an order that stated that Yellow Hammer's motion to dismiss was moot.

Free access — add to your briefcase to read the full text and ask questions with AI

Shirley R. Hulsey v. Build Art, LLC, (Ala. 2026).

Shirley R. Hulsey v. Build Art, LLC (Shirley R. Hulsey v. Build Art, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dzwonkowski v. Sonitrol of Mobile, Inc.
892 So. 2d 354 (Supreme Court of Alabama, 2004)
Goldome Credit Corp. v. Player
869 So. 2d 1146 (Court of Civil Appeals of Alabama, 2003)
Hammock v. Wal-Mart Stores, Inc.
8 So. 3d 939 (Supreme Court of Alabama, 2008)
Schlarb v. Lee
955 So. 2d 418 (Supreme Court of Alabama, 2006)
Baker v. Bennett
644 So. 2d 901 (Supreme Court of Alabama, 1994)
CLARKE-MOBILE COUNTIES GAS v. Prior Energy Corp.
834 So. 2d 88 (Supreme Court of Alabama, 2002)
HARPER SALES v. Brown, Stagner, Richardson, Inc.
742 So. 2d 190 (Court of Civil Appeals of Alabama, 1999)
Brown v. Whitaker Contracting Corp.
681 So. 2d 226 (Court of Civil Appeals of Alabama, 1996)
Robinson v. Computer Servicenters, Inc.
360 So. 2d 299 (Supreme Court of Alabama, 1978)
Branch v. Southtrust Bank of Dothan, N.A.
514 So. 2d 1373 (Supreme Court of Alabama, 1987)
Sargent v. Lambert Const. Co.
378 So. 2d 1153 (Court of Civil Appeals of Alabama, 1979)
Harlan Home Builders, Inc. v. Hayslip
58 So. 3d 102 (Supreme Court of Alabama, 2010)
American General Finance Co. v. Estate of Hurston
955 So. 2d 420 (Supreme Court of Alabama, 2006)
Ronda Scott v. Advanced Pharmaceutical Consultants Inc
84 F.4th 952 (Eleventh Circuit, 2023)