Shewmake v. DelGreco

926 So. 2d 348, 2005 WL 2680015
CourtCourt of Civil Appeals of Alabama
DecidedOctober 21, 2005
Docket2040016
StatusPublished
Cited by2 cases

This text of 926 So. 2d 348 (Shewmake v. DelGreco) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shewmake v. DelGreco, 926 So. 2d 348, 2005 WL 2680015 (Ala. Ct. App. 2005).

Opinions

The defendant Jack Shewmake appeals a judgment in favor of the plaintiffs Al DelGreco and Lisa DelGreco. We reverse the trial court's judgment and render a judgment in favor of the DelGrecos in the amount of $866.49.

On March 13, 1999, the DelGrecos entered into a written contract with Shewmake and Jim Kelly regarding the remodeling of the DelGrecos' house ("the contract"). The remodeling consisted of adding a playroom and a hobby room underneath an existing wooden deck, replacing the existing wooden deck with a concrete deck, adding a screened-in porch, and adding a third garage. In pertinent part, the contract stated:

"Job Description: Addition to existing house according to plans and specs provided by owner. Addition to be done in a timely and workmanlike manner. Exterior and interior to match existing structure as closely as possible.

"Walls, trim and ceiling of main structure to match existing. Flooring to be carpet with 28.00/sy allowance. Sheet rock walls, acoustic ceiling, driveway and walks to be extended as per owners' specifications. Paint colors to be selected by owners.

"Best effort has been made to give an accurate estimate for the costs of this job. Allowances have been provided as a guideline to help control costs.

"Any addition requirements by the Greystone ACC will be added to the estimated cost and paid by the owners. "[The DelGrecos] will be responsible for all labor and materials performed and/or delivered to this site. Any work performed by [Shewmake and Kelly] will be paid as sub-contract labor. (such as clean up, trim work, painting, punch list, etc.)

"[Shewmake and Kelly] to work on a fee of [$]35,000.00 for overseeing construction, obtaining material, scheduling subcontractors and quality control.

"Subcontractors must be paid on Friday of each week by 3:30 p.m.

"Supplier[s] to be paid before the 10th of each month and bills will be discounted if applicable. If special order items are necessary, deposits or advance payment may be required.

". . . .

"Fee Schedule: *Page 350

"[$]3,000.00 due upon signing of contract

"[$]6,000.00 due 1st of each month beginning April 1 for five months

"[$]2,000.00 due along with remaining balance of monthly installments upon final inspection."

The estimated costs and allowances for the labor and materials totaled $114,000.

The remodeling of the DelGrecos' house began in April 1999. A substantial amount of work had been completed by late July 1999. In late July or early August 1999, a subcontractor, Concrete Designs and Coatings, LLC ("Concrete Designs"), poured the new concrete deck in forms installed by Shewmake and Kelly for a contract price of $5,626. However, after the new concrete deck was poured, the DelGrecos noticed that it allowed rain to leak into the new playroom and hobby room underneath it. They also noticed several other less significant problems with the remodeling work that needed to be corrected. The DelGrecos complained to Shewmake and Kelly regarding all of these problems. Shewmake and Kelly attempted to correct the problems; however, they had not yet successfully corrected the leak in the concrete deck when Mr. DelGreco told Shewmake in November 1999 that the DelGrecos would not pay Shewmake and Kelly any further money until Shewmake and Kelly had corrected the leak in the concrete deck. After this conversation, Shewmake and Kelly did not perform any further work on the DelGrecos' house.

When Shewmake and Kelly ceased working on the DelGrecos' house in November 1999, the DelGrecos employed an architect to determine what needed to be done to correct the defects in the work completed by Shewmake and Kelly. The DelGrecos then employed a substitute contractor to correct the leak in the concrete deck and to complete the remodeling project. In order to eliminate the leaking in the concrete deck, the substitute contractor demolished the concrete deck installed by Shewmake and Kelly and installed a new concrete deck in its place.

On March 6, 2000, the DelGrecos sued Shewmake, Kelly, and Concrete Designs, alleging breach of contract, negligence, fraud, misrepresentation, the tort of outrage, and breach of warranty. The defendants answered the complaint. Shewmake and Kelly asserted the affirmative defense of set-off. In addition, Concrete Designs asserted a cross-claim against Shewmake and Kelly to recover the $5,626 Shewmake and Kelly had agreed to pay Concrete Designs for pouring the initial concrete deck. Before trial, the DelGrecos settled their claims against Concrete Designs on a pro tanto basis.

At a bench trial on October 30, 2003, the trial court received evidence ore tenus regarding the DelGrecos' claims against Shewmake and Kelly and regarding Concrete Designs' cross-claim against Shewmake and Kelly. Kelly did not appear for trial.

The evidence at trial established the following facts. The DelGrecos paid Shewmake and Kelly a total of $96,497.78. This total consisted of $21,000 in fees and $75,497.78 for labor and materials. The $75,497.78 for labor and materials included amounts for extras the DelGrecos requested after the written contract had been executed. The DelGrecos paid the architect $1,496.13 for inspecting the work performed by Shewmake and Kelly. The DelGrecos paid the substitute contractor $18,470.36 to demolish the concrete deck Shewmake and Kelly had installed and to install a new one. In addition, the DelGrecos paid the substitute contractor approximately $57,000 to complete the remodeling of their house. *Page 351

Shewmake paid $14,800 for labor and materials used in the remodeling work he and Kelly completed for which the DelGrecos did not reimburse him. In addition, Shewmake owes a supplier $4,300 for materials used in the remodeling work he and Kelly completed for which the DelGrecos did not reimburse him. The DelGrecos did not pay Shewmake and Kelly $14,000 of the $35,000 contractors' fee contemplated by the contract. Shewmake estimated that the labor and materials necessary to complete the work he had agreed to perform would have cost approximately $10,000 to $12,000.

At trial, the DelGrecos asked the trial court to award them as damages the $96,497.78 they had paid Shewmake and Kelly, the $1,496.13 they had paid the architect, and the $18,470.36 they had paid the substitute contractor to replace the concrete deck installed by Shewmake and Kelly. The DelGrecos expressly waived any claim to recovery of the approximately $57,000 they had paid the substitute contractor to complete the remodeling of their house.

On November 3, 2003, the trial court entered a final judgment awarding the DelGrecos $119,966.49 on their claims against Shewmake and Kelly, jointly and severally, and awarding Concrete Designs $5,626 plus $1,436.22 in prejudgment interest on its cross-claim against Shewmake and Kelly, jointly and severally.1

On December 2, 2003, pursuant to Rule 59, Ala. R. Civ. P., Shewmake moved the trial court to alter, amend, or vacate the judgment, or to order a remittitur, or to order a new trial. In support of his Rule 59 motion, Shewmake argued that the trial court had erred because, Shewmake said, the trial court had not used the correct measure of damages in determining how much the DelGrecos were entitled to recover. Specifically, Shewmake argued that the correct measure of damages was the difference between the market value of the remodeling work completed by Shewmake and Kelly and the market value of the remodeling work as warranted. Shewmake cited McLendon Pools, Inc. v. Bush, 414 So.2d 92 (Ala.Civ.App. 1982), and Alabama Pool Construction Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Youngblood v. Ellis
983 So. 2d 1122 (Court of Civil Appeals of Alabama, 2007)
Shewmake v. DelGreco
926 So. 2d 348 (Court of Civil Appeals of Alabama, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
926 So. 2d 348, 2005 WL 2680015, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shewmake-v-delgreco-alacivapp-2005.