Sherman R. Smoot Co. v. United States Department of Transportation

516 F. Supp. 260, 28 Cont. Cas. Fed. 81,303, 1981 U.S. Dist. LEXIS 17877
CourtDistrict Court, District of Columbia
DecidedApril 16, 1981
DocketCiv. A. 81-0511
StatusPublished
Cited by1 cases

This text of 516 F. Supp. 260 (Sherman R. Smoot Co. v. United States Department of Transportation) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sherman R. Smoot Co. v. United States Department of Transportation, 516 F. Supp. 260, 28 Cont. Cas. Fed. 81,303, 1981 U.S. Dist. LEXIS 17877 (D.D.C. 1981).

Opinion

MEMORANDUM OPINION

JOYCE HENS GREEN, District Judge.

Pending before the Court are the cross-motions of the parties for summary judgment and that of the defendants to dismiss this action. Plaintiff, the Sherman R. Smoot Company (“Smoot”) of Columbus, Ohio, seeks injunctive and declaratory relief as well as damages against defendants, the United States Department of Transportation (“DOT”) and the Federal Railroad Administration (“FRA”). The Secretary of Transportation (“the Secretary”) has delegated to the FRA the authority to implement the Northeast Corridor Improvement Project (“NECIP”) aimed at rehabilitating the rail corridor between Boston, Massachusetts and Washington, D. C. The NECIP includes track maintenance and reconstruction as well as the refurbishing of fifteen stations along the corridor, including Baltimore Penn Station in Baltimore, Maryland. A dispute over the project in Baltimore underlies this complaint.

Smoot is an enterprise owned by individuals who qualify as disadvantaged under 15 U.S.C. § 631 and are therefore entitled to participation in the program set out in Section 2[8](a) of the Small Business Act, which authorizes the Small Business Administration (“SBA”) to contract with procuring agencies for government work and then to subcontract the actual work to a firm that qualifies as a minority business. On March 7, 1980, the FRA Contracting Officer wrote to the SBA expressing an interest in negotiating with Smoot for the project at the Baltimore Penn Station and enclosing a summary of the work then estimated to cost between four and six million dollars. The SBA responded on March 31 naming Smoot as capable of performing the work and requesting that the procurement for the Baltimore project be reserved for a Section 2[8](a) award to the SBA. In a letter of April 15, the Contracting Officer notified SBA of FRA’s commitment to award a contract under § 2[8](a) to the SBA, with the requirement that Smoot begin work on the project no later than September 30, 1980. The officer additionally indicated that specifications and estimates would be available for Smoot approximately May 15, 1980. On May 22, preliminary, but not final specifications were forwarded to Smoot.

The Contracting Officer sent on June 20, 1980 a construction format to the SBA for Smoot’s perusal, but the letter from the Officer indicated that FRA had not been able to make available final specifications on May 15 and anticipated that SBA should receive the documents no later than July 15. SBA was requested to inform FRA if this delay would hinder start-up by the September 30 projected date. SBA responded on July 7 that if the additional materials were received on July 15 and if negotiations began no later than August 15, sufficient time would be provided to commence work on September 30. On July 8, 1980, FRA furnished the complete specifications to the SBA. Between this date and August 14, Smoot, representatives of the procuring agency, and the agency’s engineer met to discuss the project, Smoot raising a number of questions concerning the scope of the work to be done.

On August 14, the FRA sent to SBA a summary of its estimate, followed two weeks later with a complete detailed cost estimate with supporting materials. The FRA’s estimate was $4,551,400 for the basic *262 work plus $130,000 for some additional mechanical work. Smoot submitted its proposal on September 4, 1980, amounting to $7,808,026 plus $178,673 for the mechanical repairs. Given the great difference between the two estimates, the parties met in mid-September to negotiate their respective prices. Additionally, FRA raised questions concerning alleged excesses in Smoot’s cost estimates. On September 17, Smoot submitted a revised proposal of $7,058,217 for the basic project, a reduction of about $800,000. Approximately two weeks later, Smoot sent a telegram to FRA citing the price reduction and requesting a detailed itemized cost estimate which it claims never to have received.

The Defense Contract Audit Agency provided DOT on October 8 with an audit report of Smoot that concluded that Smoot’s cost was unacceptable, with nearly $2 million as unsupported. After further negotiations, the FRA informed the SBA by letter of October 14 that the FRA would raise the amount it was willing to pay by $500,000 to approximately $5,000,000 based on an informal adjustment to the cost estimate, and FRA added an additional $500,-000 to reflect its desire that the contract be awarded under Section 2[8](a). FRA requested SBA’s reply by October 17. On October 21, the parties met for more negotiations and the SBA offered to sign a contract for $6.25 million, making up the amount to Smoot’s estimate of $7 million with its own funds authorized for business development. FRA asserted that it could pay no more than $5.5 million, and the SBA responded by requesting another cost estimate, which the FRA ordered on October 23. Six days later, FRA requested from SBA a response to its offer of $5.5 million. SBA responded on November 4,1980 with a “final price” of $6.25 million and an allegation that the FRA’s cost estimate had no true basis in fact.

The revised estimate was completed November 19 and it reflected that a more realistic cost would approach $5 million; FRA that day wrote to SBA and reaffirmed its $5.5 million proposal, requesting a rapid response to avoid the need to place the contract on the open market and out of the § 2[8](a) program. On November 28, the Contracting Officer recommended to the head of the NECIP that the § 2[8](a) award be cancelled and that the project be placed for bids on the open market. SBA responded on December 4 that submission of the project for competitive bids would violate section 2[8](a) and requested that the matter be submitted to the Secretary for review; six days later, the Contracting Officer notified SBA that he was exercising his discretion not to award a 2[8](a) contract for the Baltimore Penn Station. SBA sent a telegram to FRA on December 11 requesting that the notice for competitive bids be withdrawn for one more review, which FRA agreed to complete. On December 30, FRA decided to open the project for competitive bids.

On January 6, 1981, SBA protested the decision to withdraw the contract from § 2[8](a) status, and two days later the SBA requested from the Secretary a review of the entire collapse of negotiations. Bids for the project were due on March 4, but on March 3, plaintiff filed a motion for a temporary restraining order to prevent FRA from opening the bids. The next day, the Court denied the motion and the bids were opened March 5. FRA received two bids, one from a small business for $4.8 million plus $750,000 for the additive work, and the other for $5,962 million plus $150,000. On April 2, the day before oral argument was to be heard on the merits of Smoot’s complaint, the Secretary of Transportation, Drew Lewis, affirmed the FRA’s decision to withdraw the contract from § 2[8](a) status on the ground that despite a good faith effort by FRA, negotiations were not fruitful in reaching an agreement and, despite the fact that further negotiations might possibly have been successful, the FRA properly decided that further delay would only increase the cost of the project and thus was justified in receiving competitive bids.

The question presented by defendants’ motions is whether FRA’s withdrawal *263

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris Systems International, Inc. v. United States
32 Cont. Cas. Fed. 72,486 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
516 F. Supp. 260, 28 Cont. Cas. Fed. 81,303, 1981 U.S. Dist. LEXIS 17877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sherman-r-smoot-co-v-united-states-department-of-transportation-dcd-1981.