Shepherd Real Estate Subsidiary, LLC - 1901 Halstead Series v. Commonwealth Edison Company

2024 IL App (1st) 221766-U
Appellate Court of Illinois·Decided January 24, 2024·No. 1-22-1766·Unpublished·Cited by 1 cases

Opinion

2024 IL App (1st) 221766-U No. 1-22-1766

Order filed January 24, 2024 Third Division

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS FIRST DISTRICT

SHEPHERD REAL ESTATE SUBSIDIARY, LLC— ) Appeal from the 1901 HALSTED SERIES, ) Circuit Court of ) Cook County.

Plaintiff-Appellee and Cross-Appellant, )

)

v. ) No. 20 CH 2866 )

COMMONWEALTH EDISON COMPANY, ) Honorable ) Thomas More Donnelly, Defendant-Appellant and Cross-Appellee. ) Judge, presiding.

JUSTICE VAN TINE delivered the judgment of the court.

Presiding Justice Reyes and Justice D.B. Walker concurred in the judgment.

ORDER

¶1 Held: We affirm the trial court’s award of lost profits and escalation costs over defendant’s contention that the evidence of those damages was speculative and that the “new business rule” barred recovery of lost profits. We also affirm the trial court’s ruling that prejudgment interest was not available on plaintiff’s trespass claim.

¶2 Plaintiff Shepherd Real Estate Subsidiary, LLC—1901 Halsted Series (Shepherd) sued defendant Commonwealth Edison Company (ComEd) for trespass, alleging that a ComEd power

line running under Shepherd’s property at 1901 North Halsted Street delayed and increased the cost of constructing an apartment building. Following a bench trial, the trial court entered judgment in Shepherd’s favor on its trespass claim and awarded $1,311,403.57 in damages, including $1,116,683 in lost profits and $126,744.76 in escalation costs. ComEd appeals the award of lost profits and escalation costs, arguing that the evidence of those damages was speculative and that the “new business rule” barred recovery of lost profits. Shepherd cross-appeals, arguing that the trial court erred in ruling that prejudgment interest was not available on its trespass claim. For the following reasons, we affirm.

¶3 I. BACKGROUND

¶4 The lawsuit arose out of the construction of an apartment building at 1901 North Halsted Street in Chicago. 1 Shepherd’s complaint alleged that in July 2019, its representatives found ComEd employees working on the property and, as a result, discovered that a live ComEd power line ran underneath the middle of the property. According to Shepherd, ComEd’s easement for the power line had expired in 1945 and ComEd refused to relocate the power line. Shepherd sued ComEd in the Chancery Division of the circuit court of Cook County, alleging one count of ejectment and one count of trespass. The parties settled the ejectment count and the remaining trespass count was transferred to the Law Division for trial.

¶5 A. Motion in Limine

¶6 Prior to trial, ComEd filed a motion in limine to bar Shepherd from seeking prejudgment interest. ComEd argued that, under Illinois law, prejudgment interest is recoverable only when

1 There is some indication that the building is on the 1800 block of North Halsted but, to avoid confusion, we refer to the building as 1901 North Halsted.

authorized by statute or agreement of the parties, or as an equitable remedy, none of which applied to Shepherd’s trespass claim. Shepherd argued that (1) ComEd’s so-called motion in limine was, in fact, an untimely motion for summary judgment on Shepherd’s claim for prejudgment interest, (2) prejudgment interest was a proper equitable remedy for trespass, and (3) the trial court should decide Shepherd’s claim for prejudgment interest after hearing the evidence. The trial court granted ComEd’s motion in limine. The court reasoned that Shepherd presented no legal authority to support prejudgment interest on its trespass claim after having settled the ejectment claim that sought equitable relief in the form of an injunction.

¶7 B. Trial

¶8 1. Construction of 1901 North Halsted

¶9 At trial, the evidence established that Tom Gibbons is the president of Shepherd, a real estate company that owns approximately 15 properties on the north side of Chicago.2 Tom’s son, Martin Gibbons, is Shepherd’s property manager. In 2009, Shepherd acquired a property at 1901 North Halsted. In 2017, Shepherd employed an architect to design a 12-unit apartment building on the property. Shepherd hired contractors for the project without formal bidding or written contracts, and there was no written schedule for construction. Shepherd obtained a construction permit on June 10, 2019, and estimated that construction would take approximately 15 months. Construction was to begin in July 2019 and finish in October 2020.

¶ 10 On July 1, 2019, Tom and Martin Gibbons found ComEd personnel and equipment on the property without permission or prior notice and learned that a live ComEd power line ran under the middle of the property. ComEd’s easement for the power line had expired in 1945. In August

2 For brevity, we set forth only the trial evidence relevant to the issues on appeal.

2019, ComEd offered to relocate the power line at Shepherd’s expense. Shepherd later agreed to grant ComEd an easement outside the building’s footprint so ComEd could relocate the power line to that area.

¶ 11 In the meantime, Shepherd proceeded with construction above and around the power line. Much of the excavation work had to be completed by hand to avoid hitting the power line, which added additional time to the project. By February 2020, Shepherd had completed enough excavation and foundation work to begin construction of the building. ComEd began relocating the power line in March 2021 and finished in November 2021. Water lines, sewer lines, and the building’s sprinkler and drainage systems could not be installed until ComEd finished moving the power line. In addition, the building’s plumbing, electrical, heating, and air conditioning systems had to be installed “from the top down,” meaning that those systems could not be connected in the basement until the power line was relocated. Shepherd completed construction in August 2022.

¶ 12 The COVID-19 pandemic did not delay construction, nor did labor or material shortages or city inspections. Shepherd received a partial occupancy permit for the building on September 7, 2022. As of trial in October 2022, Shepherd had not received a full occupancy permit because staircase handrails still needed to be installed. Martin expected that it would take approximately 60 days to lease all 12 units once Shepherd received the full occupancy permit.

¶ 13 2. Lost Profits

¶ 14 Shepherd called Michael Nathan Brock, an expert in construction delay and damages evaluation. Brock testified that Shepherd’s construction time estimate of 15 months was reasonable based on the average time to complete a 10 to 19-unit apartment building in the Midwest as

reported by the National Association of Homebuilders. Construction was delayed by 22 months, which Brock attributed to the ComEd power line.

¶ 15 Brock estimated lost profits by using the Multiple Listing Service (MLS) to approximate reasonable rental rates for each of the units at 1901 North Halsted. MLS is available to real estate agents and brokers and “shows rental activity, purchase activity and active listings of real estate.” Through MLS, Brock found 24 comparable apartments in Lincoln Park and Old Town that were built within five years of 1901 North Halsted, and which had similar square footage, bedrooms, and bathrooms. He also examined photographs of the comparable apartments to confirm that they had a similar appearance and finish to the apartments at 1901 North Halsted. Among these 24 comparable apartments, the average rental price for a two-bedroom was $2.84 per square foot per month in 2021 and $3.21 per square foot per month in 2022. The average rental price for a three- bedroom was $3.12 per square foot per month in 2021 and $3.28 per square foot per month in 2022.

Free access — add to your briefcase to read the full text and ask questions with AI

Shepherd Real Estate Subsidiary, LLC - 1901 Halstead Series v. Commonwealth Edison Company, 2024 IL App (1st) 221766-U (Ill. Ct. App. 2024).

2024 IL App (1st) 221766-U (Shepherd Real Estate Subsidiary, LLC - 1901 Halstead Series v. Commonwealth Edison Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

PML Development LLC v. Village of Hawthorn Woods
2025 IL App (2d) 240191-U (Appellate Court of Illinois, 2025)