OPINION and ORDER
DOMINGUEZ, District Judge.
In the instant case, Plaintiffs’1 request that the Court reconsider the Opinion and Order issued on March 11, 1996, partially denying and partially granting Defendants’ motion. (Docket No. 83). Defendants2 then filed an opposition to said motion for reconsideration (Docket No. 88) to which Plaintiffs replied. (Docket No. 100). After a careful reanalysis of the record and of the Court’s March 11, 1996, Opinion and Order, the Court finds no merit to Plaintiffs’ contentions and DENIES the motion for reconsideration.
FACTS
The object of the present motion for reconsideration revolves around a letter entitled “Joint Venture in Puerto Rico” (“joint venture letter”), dated October 24, 1989, signed by both parties. The issue is whether that agreement was or was not a contract between the parties.3 Plaintiffs contend that both parties entered into a contract with Defendants and Defendants breached said contract.4 The relationship between the parties commenced in February of 1988 when Defendants approached Plaintiffs regarding the development of a marina village. In the 1980’s, Plaintiffs conceived this idea of a marina village and had, in fact, been working on developing this idea.5 See Docket No. 54, p. 16. The following month Defendants submitted a plan for the marina village, which envisioned a “full-scale world class mega resort.” 6 See Docket No. 54, p. 18. Then in July of 1988, Trafalgar House proposed to carry out the entire project, including finane[86]*86ing.7 A year later and after the Shelleys had paid a $150,000 commitment fee to a- bank, Trafalgar House submitted to the Shelleys “final, bound sets of the Turnkey and Construction Management contracts to be executed along with the Shareholders Agreement. ...” (Emphasis ours). Id. at 35.
On October 17, 1989, a draft of a formal “Heads of Agreement” was sent to the Shelleys in advance of negotiations that were to be held in London the following week.8 As included in Plaintiffs’ Statement of Triable Issues of Material Facts, Plaintiffs provide that they were unhappy with the October 17th draft agreement because the agreement did not “underscore” Trafalgar House’s obligations. Moreover, the Shelleys would only deal exclusively with Trafalgar House if “there was a mutually binding commitment between the parties to secure those conditions and to close the new Shareholder Agreement within a short time____” Id. at 43. From October 17, 1989 to October 24, 1989, S.W. Shelley traveled to London to negotiate a final agreement with Defendants. Three other drafts were completed during that time, the last being the October 24, 1989, joint venture letter — the object of this Opinion and Order.
ANALYSIS
The Court will begin by revisiting the analysis completed in the March 11, 1996, Opinion and Order, in which this Court found that the parties did not agree upon a binding joint venture as to the development of the marina project. Notwithstanding Plaintiffs’ argument that the Court erred in granting summary judgment because of the general rule that issues of intent are for the fact finder, summary judgment was proper in the instant ease. Finally, Plaintiffs’ contention that the joint venture letter is merely one of three contracts is unmeritorious. The Court AFFIRMS the previous decision that there was no breach of contract because a contractual agreement was not reached.
I. Joint Venture Letter
It is not possible at this time to enter into a totally binding agreement because there are a number of matters ... which have still to be clarified to our satisfaction .... [I]t is the intention of the [parties] to endeavor to resolve all outstanding matters and to enter into a legally binding Shareholders’ Agreement within [90 days].
See Docket No. 7, October 24, 1989, Joint Venture Letter.
The language included in the aforementioned paragraph strikes the Court in the same chord as the last time the Court examined this matter. The language of the preliminary agreement is clear. There was no contract, at most, the Court agrees with Plaintiffs that there are genuine issues of material fact as to whether there was an agreement to agree.
The joint venture letter provided a New York choice of law clause, which the Court found valid and enforceable. See Trafalgar House, 918 F.Supp. at 521. New York law provides that the joint venture letter does not constitute a contract.9 In Teachers Ins. & Annuity Ass’n of America v. Tribune Co., the court outlined the two types of binding preliminary agreements. 670 F.Supp. 491, 498 (S.D.N.Y.1987). See also Arcadian Phosphates, Inc. v. Arcadian Corp., 884 F.2d [87]*8769, 72 (2d Cir.1989) (following the Teachers Ins. court’s analysis of the two types of binding preliminary agreements); P.A. Bergner & Co. v. Martinez, 823 F.Supp. 151, 155 (S.D.N.Y.1993) (same). The first type, which is preliminary only in name and inapplicable to the present case, arises when the parties agree to the terms of the contract, “including the agreement to be bound.” Id. This preliminary agreement constitutes a contract, “bindfing] both sides to their ultimate contractual objective ... despite the anticipation of further formalities” and not merely a binding agreement to agree, as is possibly exemplified by the October 24th joint venture letter. Id. The second type of preliminary agreement merely binds parties to continue good faith negotiations to achieve a consensus as per open terms and “does not commit the parties to their ultimate contractual objective.” Id. The joint venture letter falls within the latter type of preliminary agreement. There were open terms to be negotiated and the letter explicitly states that it is not binding.
II. Summary Judgment Was Proper
Plaintiffs contend that the Court erred in granting summary judgment and finding that there was no joint venture contract. Plaintiffs maintain that there exist genuine issues as to the parties’ intent when signing the October 24, 1989, joint venture letter. The argument follows the general rule that issues of intent should be left to the trier of fact and as such summary judgment should have been denied. The Court emphatically disagrees.
The Federal Rule of Civil Procedure 56(c) provides in pertinent part that “judgment sought shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” The purpose of summary judgment is “to pierce the boilerplate of the pleadings and assay the parties’ proof in order to determine whether the trial is actually required.” Wynne v. Tufts Univ. Sch. of Med., 976 F.2d 791, 794 (1st Cir.1992). The Court must then perform a two prong analysis to determine whether summary judgment is proper. First, is the contested fact material.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION and ORDER
DOMINGUEZ, District Judge.
In the instant case, Plaintiffs’1 request that the Court reconsider the Opinion and Order issued on March 11, 1996, partially denying and partially granting Defendants’ motion. (Docket No. 83). Defendants2 then filed an opposition to said motion for reconsideration (Docket No. 88) to which Plaintiffs replied. (Docket No. 100). After a careful reanalysis of the record and of the Court’s March 11, 1996, Opinion and Order, the Court finds no merit to Plaintiffs’ contentions and DENIES the motion for reconsideration.
FACTS
The object of the present motion for reconsideration revolves around a letter entitled “Joint Venture in Puerto Rico” (“joint venture letter”), dated October 24, 1989, signed by both parties. The issue is whether that agreement was or was not a contract between the parties.3 Plaintiffs contend that both parties entered into a contract with Defendants and Defendants breached said contract.4 The relationship between the parties commenced in February of 1988 when Defendants approached Plaintiffs regarding the development of a marina village. In the 1980’s, Plaintiffs conceived this idea of a marina village and had, in fact, been working on developing this idea.5 See Docket No. 54, p. 16. The following month Defendants submitted a plan for the marina village, which envisioned a “full-scale world class mega resort.” 6 See Docket No. 54, p. 18. Then in July of 1988, Trafalgar House proposed to carry out the entire project, including finane[86]*86ing.7 A year later and after the Shelleys had paid a $150,000 commitment fee to a- bank, Trafalgar House submitted to the Shelleys “final, bound sets of the Turnkey and Construction Management contracts to be executed along with the Shareholders Agreement. ...” (Emphasis ours). Id. at 35.
On October 17, 1989, a draft of a formal “Heads of Agreement” was sent to the Shelleys in advance of negotiations that were to be held in London the following week.8 As included in Plaintiffs’ Statement of Triable Issues of Material Facts, Plaintiffs provide that they were unhappy with the October 17th draft agreement because the agreement did not “underscore” Trafalgar House’s obligations. Moreover, the Shelleys would only deal exclusively with Trafalgar House if “there was a mutually binding commitment between the parties to secure those conditions and to close the new Shareholder Agreement within a short time____” Id. at 43. From October 17, 1989 to October 24, 1989, S.W. Shelley traveled to London to negotiate a final agreement with Defendants. Three other drafts were completed during that time, the last being the October 24, 1989, joint venture letter — the object of this Opinion and Order.
ANALYSIS
The Court will begin by revisiting the analysis completed in the March 11, 1996, Opinion and Order, in which this Court found that the parties did not agree upon a binding joint venture as to the development of the marina project. Notwithstanding Plaintiffs’ argument that the Court erred in granting summary judgment because of the general rule that issues of intent are for the fact finder, summary judgment was proper in the instant ease. Finally, Plaintiffs’ contention that the joint venture letter is merely one of three contracts is unmeritorious. The Court AFFIRMS the previous decision that there was no breach of contract because a contractual agreement was not reached.
I. Joint Venture Letter
It is not possible at this time to enter into a totally binding agreement because there are a number of matters ... which have still to be clarified to our satisfaction .... [I]t is the intention of the [parties] to endeavor to resolve all outstanding matters and to enter into a legally binding Shareholders’ Agreement within [90 days].
See Docket No. 7, October 24, 1989, Joint Venture Letter.
The language included in the aforementioned paragraph strikes the Court in the same chord as the last time the Court examined this matter. The language of the preliminary agreement is clear. There was no contract, at most, the Court agrees with Plaintiffs that there are genuine issues of material fact as to whether there was an agreement to agree.
The joint venture letter provided a New York choice of law clause, which the Court found valid and enforceable. See Trafalgar House, 918 F.Supp. at 521. New York law provides that the joint venture letter does not constitute a contract.9 In Teachers Ins. & Annuity Ass’n of America v. Tribune Co., the court outlined the two types of binding preliminary agreements. 670 F.Supp. 491, 498 (S.D.N.Y.1987). See also Arcadian Phosphates, Inc. v. Arcadian Corp., 884 F.2d [87]*8769, 72 (2d Cir.1989) (following the Teachers Ins. court’s analysis of the two types of binding preliminary agreements); P.A. Bergner & Co. v. Martinez, 823 F.Supp. 151, 155 (S.D.N.Y.1993) (same). The first type, which is preliminary only in name and inapplicable to the present case, arises when the parties agree to the terms of the contract, “including the agreement to be bound.” Id. This preliminary agreement constitutes a contract, “bindfing] both sides to their ultimate contractual objective ... despite the anticipation of further formalities” and not merely a binding agreement to agree, as is possibly exemplified by the October 24th joint venture letter. Id. The second type of preliminary agreement merely binds parties to continue good faith negotiations to achieve a consensus as per open terms and “does not commit the parties to their ultimate contractual objective.” Id. The joint venture letter falls within the latter type of preliminary agreement. There were open terms to be negotiated and the letter explicitly states that it is not binding.
II. Summary Judgment Was Proper
Plaintiffs contend that the Court erred in granting summary judgment and finding that there was no joint venture contract. Plaintiffs maintain that there exist genuine issues as to the parties’ intent when signing the October 24, 1989, joint venture letter. The argument follows the general rule that issues of intent should be left to the trier of fact and as such summary judgment should have been denied. The Court emphatically disagrees.
The Federal Rule of Civil Procedure 56(c) provides in pertinent part that “judgment sought shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” The purpose of summary judgment is “to pierce the boilerplate of the pleadings and assay the parties’ proof in order to determine whether the trial is actually required.” Wynne v. Tufts Univ. Sch. of Med., 976 F.2d 791, 794 (1st Cir.1992). The Court must then perform a two prong analysis to determine whether summary judgment is proper. First, is the contested fact material. A material fact is one that could affect the outcome of the suit under the governing law. The existence of such a fact precludes the entry of summary judgment. Factual disputes that are irrelevant to the suit’s outcome are to be disregarded. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Second, the court must determine whether the dispute is genuine. A genuine issue is defined as a dispute when based on the evidence a reasonable jury could return a verdict for the nonmoving party. Anderson, 477 U.S. at 248, 106 S.Ct. at 2510.
The First Circuit has advised district courts that they must proceed with caution when there exist issues of intent. Coll v. P.B. Diagnostic Sys. Inc., 50 F.3d 1115, 1121 (1st Cir.1995). See also Oliver v. Digital Equip. Corp., 846 F.2d 103, 109 (1st Cir.1988); Stepanischen v. Merchants Despatch Transp. Corp., 722 F.2d 922, 928 (1st Cir.1983); Lipsett v. University of P.R., 864 F.2d 881, 895 (1st Cir.1988). Notwithstanding the First Circuit’s advice to proceed with care, an issue of intent does not preclude summary judgment. “Even in cases where elusive concepts such as motive and intent are at issue, summary judgment may be appropriate if the nonmoving party rests merely upon conclusory allegations, improbable inferences, and unsupported speculation.” Medina-Muñoz v. R.J. Reynolds Tobacco Co., 896 F.2d 5, 8 (1st Cir.1990). The Court must still perform the aforementioned summary judgment analysis. In performing said analysis, this Court found and today affirms the decision that there exists no genuine issue as to the intent of the October 24, 1989 joint venture letter. The parties did not intend, as explicitly stated, to enter into a binding joint venture agreement at that time.
Moreover, as per New York law, the courts have stated that when intent is readily determined by the agreement then intent becomes a matter of law and appropriately decided at the summary judgment stage. See Arcadian Phosphates, 884 F.2d at 73. In the instant case, the parties’ intent is readily apparent. Plaintiffs contend that ambiguity lies in the [88]*88last paragraph of the letter which states that “it is not possible at this time to enter into a totally binding agreement because there are a number of matters ... still to be clarified to our satisfaction.” Again, the Court finds no ambiguity; a contract was not conceived of at that time.10 “[A] party that wishes to be bound can very easily protect itself by refusing to accept language that shows an intent not to be bound.” Arcadian Phosphates, 884 F.2d at 69. (Emphasis added).
III. All-in-One Letter
Plaintiffs contend that the October 24, 1989, joint venture letter pertained only to equity participation, i.e. shareholders’ agreement. Notwithstanding the fact that a shareholders’ agreement was never finally drafted, as was contemplated in the joint venture letter, the parties had nonetheless previously entered into both a turnkey contract and construction management contract. As Plaintiffs argue, no contractual shareholders’ agreement was breached in November of 1990 when Defendants decided to forgo further negotiations with Plaintiffs, but that day the other alleged contracts were breached. In sum, Plaintiffs allege that Defendants breached their contractual obligation “to undertake to carry out ourselves on your behalf [sic] the entire development.” See Docket No. 100, p. 5.
This Court refuses to create new contracts where the intent of the parties was clear. The October 24, 1989, joint venture letter was an all-in-one letter contemplating the future execution of not only the equity participation of Trafalgar House but also the development, construction, management of the marina village project. All these terms were related, and the Court refuses to bind the parties to contracts that they explicitly stated they were not bound to.
Plaintiff alleges that notwithstanding the fact that a shareholder’s agreement was never reached, there are material facts in controversy as to whether there existed construction management contracts and turnkey contracts. The Court differs. Plaintiffs themselves have provided submittals to this Court which clearly demonstrate that the construction management contracts and turnkey contracts depended on the execution of the shareholders’ agreement. “In June 1989, Trafalgar submitted to the Shelleys final, bound sets of the Turnkey and Construction Management contracts, to be executed along with the Shareholders Agreement formalizing the PRMR. Trafalgar prodded the Shelleys to sign the construction contracts prior to executing the Shareholders Agreement, but the Shelleys insisted on a comprehensive closing, including the execution of the partnership agreement as agreed and as contemplated under the B.V. loan terms.” See Docket No. 54, p. 35.
The Court agrees wholly with Defendants’ logical conclusion that the joint venture letter encompassed the turnkey and construction management aspects of the marina village project and since no final contract was ever negotiated there was never a breach of contract. The joint venture letter provides that “[f]or the avoidance of doubt it is confirmed that paragraphs 22,23, 24, and 25 above shall be binding on the parties.”11 Only the afore[89]*89mentioned paragraphs bound the parties on October 24, 1989. The parties failed to bind themselves contractually to the turnkey and construction management portion of the letter.12 Today, the Court refuses to force the parties into areas they never intended to visit. The freedom not to contract should be protected with the same zeal as the freedom to contract.
IT IS SO ORDERED.