Shell Oil Co. v. S.S. Tynemouth

205 F. Supp. 838, 1962 U.S. Dist. LEXIS 4715
CourtDistrict Court, E.D. Louisiana
DecidedJune 6, 1962
DocketNo. 5152
StatusPublished
Cited by3 cases

This text of 205 F. Supp. 838 (Shell Oil Co. v. S.S. Tynemouth) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shell Oil Co. v. S.S. Tynemouth, 205 F. Supp. 838, 1962 U.S. Dist. LEXIS 4715 (E.D. La. 1962).

Opinion

ELLIS, District Judge.

On November 9, 1960, Shell Oil Company entered into an agreement with The Texas Pipeline Company whereby Texas was to make its terminaling facilities at Pilottown, Louisiana, available to Shell for a period of five years commencing not later than July 1, 1961. The agreement provided that Shell would move a daily average of 25,000 barrels of crude petroleum through these facilities and pay 30 per barrel terminaling and load charge as provided in Texas’ Interstate Commerce Commission Tariff Number 582. It was understood by both parties that the Texas facilities would be those of a common carrier and subject to ICC regulations. Texas was to provide additional storage tanks, mooring piling clusters, additional pumping equipment, a deeper berth for tankers, breasting lines, and was to make numerous repairs. Texas was to provide personnel and facilities for securing ships in berth.

[839]*839On or before the 20th of each month Shell was to advise Texas of the quantities of petroleum it elected to deliver and load during the following month, delivery schedules and tanker loading dates. Shell did not have exclusive use of the terminal facilities. An amendment (dated July 3, 1961) to the original contract provided that additional shore ballast facilities, if necessary, were to be installed at Shell’s option and expense, and such ballast facilities had to be removed at the termination of the agreement. At the time of the incident in suit, no such facilities had been added by Shell.

On March 8, 1961, apparently the day before Shell was to make its first shipment of oil through the terminaling facilities, the S/S TYNEMOUTH; a British Flag Steamship, owned by the defendant, collided with the Texas dock. As a result Shell was unable to use the terminaling facilities and necessarily had to find other accommodations.

Shell brings a libel in rem against the S/S TYNEMOUTH and in personam against the Burnett Steamship Company, Limited, for Shell’s out-of-pocket expenses of terminaling its oil elsewhere.1 This section does not create a new right but makes available a new remedy for a preexisting cause of action, United States v. Matson Navigation Company, 9 Cir., 201 F.2d 610, 617; All-America Cables & Radio v. S/S Dieppe, 93 F.Supp. 923, and directs the district courts to exercise admiralty and maritime jurisdiction of the United States already conferred by Article 3, Section 2 of the Constitution and as authorized by the Judiciary Acts.2

Based on the pleadings and the formal agreement in the record, defendant moves for summary judgment under Rule 563 on the theory that a negligent tortfeasor is beyond the reach of a party contracting with the injured party. The pleadings do not indicate that there is a genuine issue of material fact, and therefore a summary judgment would be appropriate.4

Libellant merely alleges that it has a cause of action against such a tortfeas- or for its damages.

This being the case, the issue resolved itself into a question of law; and the law, maritime and civil, state and federal, is uniform in holding that a tort to the person or property of one party does not render the tortfeasor (vessel) liable to another (Shell) merely because the aggrieved party (Shell) was under a contract with another unknown to the wrongdoer. Robins Dry Dock & Repair Company v. Flint, 275 U.S. 303, 48 S.Ct. 134, 72 L.Ed. 290 (1927); Foret v. Board of Levee Commissioners of Orleans Levee District, 169 La. 427, 125 So. 437 (1929).5

[840]*840, Libellant alleges a right of recovery because of its status as a lessee and cites numerous cases in support thereof,6 and Article 27037 of the Louisiana Civil Code. Conceding, per arguendo, that libellant is a lessee, all cited eases involve litigation between landlord and tenant and all precede the rule set forth in the Robin and Foret cases, as adopted and approved in the Forcum-James case, 231 La. 953, 93 So.2d 228.

Libellant directs the court’s attention to Briggs v. Aiken, supra, which presents a problem close to the one at hand, however, this case does not stand for the proposition that libellant is entitled to a successful action under Article 2703, as will be seen below.

In that case the second floor of a building at No. 1102 St. Charles Avenue, New Orleans, Louisiana, was subleased to the plaintiff. Construction of a service station on adjacent premises necessitated removing and rebuilding a common wall. A general contractor sub-contracted the shoring of the wall.

After the work was begun the second floor wall collapsed on plaintiff inflicting bodily injuries and damaging her personal belongings. Suit was filed against both landowners, lessee and general and subcontractors. The Court found, as a matter of fact, that the walls were not in a defective or dangerous condition and that the accident was caused by improper shoring of the upper walls.

A pertinent portion of that opinion holding sub-contractor responsible and the grounds under which the action was to be brought is as follows:

“At the outset, in the consideration of this case, it is of dominant importance for a correct conclusion as to the law governing this litigation, to determine whether the action is one purely ex delicto arising under Articles 2315 and 2316 of the Civil Code, or whether it be an action ex contractu as well as ex delicto arising from the contractual obligations found in the leases or other contracts existing between the parties involved in these proceedings. * * * ”

The Court cited Reynolds v. Egan, supra, and Article 2703 only in passing and neither the ease nor the Article provided the substantive law upon which the decision was grounded. After an elaborate discussion of Articles 670,8 2315,9 2316 10 and 2322,11 of the Code the court came to the conclusion that “This suit, in its last [841]*841analysis, is but an action ex delicto based on Articles 2315 and 2316 of the Code. # *

The gist of the holding is that Article 2703 is merely directive and a reference to a cause of action already granted by Articles 2315 and 2316 and that reference to the general tort law of Louisiana, as evidenced from the ForcumJames litigation, is not at all in the furtherance of libellant’s claim.

The plaintiff in Briggs received an award of $7,500.00 for bodily injuries and damages to her personal property. Nowhere in the opinion was a claim made for loss of use or interference with her contract rights, and our attention has not been directed to such a case. Nor could research find one.12

It is quite difficult to place Shell in a position with greater rights than the charterer in Robin, the employee in Foret, or the bridge maintenance contractor in Forcum-James.

In two of these cases the plaintiffs had a proprietary interest far greater than that available to Shell and still recovery was denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Commerce & Navigation Co. v. the M/V Marathonian
392 F. Supp. 908 (S.D. New York, 1975)
Rockaway Blvd. Wrecking & Lumber Co. v. Raylite Electric Corp.
26 A.D.2d 9 (Appellate Division of the Supreme Court of New York, 1966)
Shell Oil Co. v. S.S. Tynemouth
211 F. Supp. 908 (E.D. Louisiana, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
205 F. Supp. 838, 1962 U.S. Dist. LEXIS 4715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shell-oil-co-v-ss-tynemouth-laed-1962.