Sheet Metal Workers' International Ass'n, Local Union No. 2 v. McElroy's, Inc.

500 F.3d 1093, 182 L.R.R.M. (BNA) 2623, 2007 U.S. App. LEXIS 20627, 2007 WL 2430127
CourtCourt of Appeals for the Tenth Circuit
DecidedAugust 29, 2007
Docket06-3189
StatusPublished
Cited by6 cases

This text of 500 F.3d 1093 (Sheet Metal Workers' International Ass'n, Local Union No. 2 v. McElroy's, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheet Metal Workers' International Ass'n, Local Union No. 2 v. McElroy's, Inc., 500 F.3d 1093, 182 L.R.R.M. (BNA) 2623, 2007 U.S. App. LEXIS 20627, 2007 WL 2430127 (10th Cir. 2007).

Opinion

TACHA, Chief Circuit Judge.

Defendant-Appellant McElroy’s, Inc. (“McElroy’s”), a mechanical contractor, and Sheet Metal Workers’ International Association, Local Union No. 77 (now merged with Plaintiff-Appellee Local Union No. 2, hereinafter “Union”) entered into a pre-hire agreement authorized by § 8(f) of the National Labor Relations Act (“NLRA”). See 29 U.S.C. § 158(a). McElroy’s and the Union performed under the contract for nearly three years when McElroy’s notified the Union that it intended to terminate the agreement on its expiration date. The Union insisted that under the terms of the agreement — specifically the “interest arbitration” clause— McElroy’s was obligated to negotiate for renewal of the contract. After McElroy’s refused to negotiate, the Union submitted the dispute to arbitration before the National Joint Adjustment Board (“NJAB”), a private alternative dispute resolution body. The NJAB held a hearing on the matter and then directed the parties to execute a three-year renewal agreement with specified terms. McElroy’s refused to comply and the Union filed an action in federal district court to enforce the NJAB’s decision. See 29 U.S.C. § 185(a). The District Court determined that the agreement required interest arbitration 1 and enforced the NJAB’s decision imposing a renewal agreement. McElroy’s appeals. Exercising jurisdiction pursuant to 28 U.S.C. § 1291, we AFFIRM the District Court’s order.

I. Background

The pre-hire agreement includes an expiration date of May 31, 2005. The agreement is based on the standard Sheet Metal Workers pre-hire agreement and includes an “extension clause” and an “interest arbitration clause.” The extension clause, Article XIII, Section 1(A), provides that the agreement “shall continue in force from year to year” after the expiration date “unless written notice of reopening is given [to the other party] not less than ninety (90) days prior to the expiration date.” If such notice is given, the agreement continues in force and effect “until conferences relating thereto have been terminated by either party, provided, however, that the contract expiration date ... shall not be effective in the event proceedings under Article X[,] Section 8 are not completed prior to that date.” Article X, Section 8 is the interest arbitration clause, which provides that “any controversy or dispute arising out of failure of the parties to negotiate a renewal of this agreement shall be settled” pursuant to the procedure set forth in that section. Relevant to this appeal, if “negotiations for renewal of this Agreement become deadlocked ... either party may submit the dispute to the [NJAB]” for arbitration. 2 The unanimous *1096 decision of the NJAB is final and binding upon the parties.

On February 25, 2005, McElroy’s faxed a letter to the Union giving notice of its intent to terminate the agreement on the expiration date, May 31, 2005. The same day, in response to this notice, the Union mailed a letter to McElroy’s seeking to reopen negotiations in accordance with Article XIII. McElroy’s did not respond. The Union made several additional written requests to McElroy’s to negotiate a renewal agreement, but McElroy’s either ignored or denied all of these requests. As a result, on May 26, 2005, five days prior to the agreement’s expiration date, the Union submitted the dispute to the NJAB.

The NJAB scheduled a hearing for June 27, which McElroy’s elected not to attend. Instead, McElroy’s submitted a letter and memorandum to the NJAB setting forth its view that it had no obligation to bargain with the Union. On June 28, the NJAB issued an order directing McElroy’s and the Union to execute a new three-year pre-hire agreement with terms as set forth in the NJAB’s order.

On July 28, 2005, after McElroy’s refused to execute a renewal contract, the Union filed suit in federal district court to enforce the NJAB’s order. The District Court (1) rejected McElroy’s argument that either party unilaterally could terminate the agreement on its expiration date; (2) held that the interest arbitration provision of Article X applies to this case because there was a “controversy or dispute arising out of failure of the parties to negotiate a renewal of the agreement”; (3) honored the finding of the NJAB that the procedural requirements for arbitration through the NJAB had been met; and (4) enforced the NJAB’s order to execute a renewal agreement but removed from the renewal agreement the interest arbitration clause under Article X, Section 8. McEl-roy’s appeals.

II. Discussion

McElroy’s argues, first, that it had an absolute right to terminate the agreement upon the contractual expiration date without any obligation to negotiate for a renewal agreement, and second, that it was under no obligation to arbitrate the dispute under the interest arbitration clause because there was no “negotiation” for renewal of the contract resulting in a “deadlock” that could trigger Article X, Section 8 procedures. The ultimate question thus posed is whether the agreement bound McElroy’s to engage in interest arbitration. See AT & T Techs., Inc. v. Comm’ns Workers of Am., 475 U.S. 643, 648, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986) (“[Arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit.” (quotation omitted)). Whether the parties have submitted a particular dispute to arbitration — that is, the “question of arbitrability” — is for the court to decide. See Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 83, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002) (“[T]he question of arbitrability! ] is an issue for judicial determination unless the parties clear *1097 ly and unmistakably provide otherwise.” (quotations, alteration, and emphasis omitted)).

McElroy’s claims the national labor policy, as set forth in the NLRA, 29 U.S.C. § 151 et seq., and decisions of the National Labor Relations Board (“NLRB”), permit a party to a pre-hire agreement unilaterally to terminate an agreement on its expiration date without any obligation to negotiate a renewal agreement. While we agree that McElroy’s is under no statutory obligation to negotiate a renewal contract, we conclude that the terms of the pre-hire agreement — specifically the extension and interest arbitration clauses — create a contractual obligation to do so when one party timely gives notice of reopening. Nothing in the NLRA, the NLRB’s decisions, or this Court’s precedent releases McElroy’s from this bargained-for contractual obligation.

Section 8(f) of the NLRA, 29 U.S.C. § 158

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
500 F.3d 1093, 182 L.R.R.M. (BNA) 2623, 2007 U.S. App. LEXIS 20627, 2007 WL 2430127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheet-metal-workers-international-assn-local-union-no-2-v-mcelroys-ca10-2007.