Shed World v. Jim Funicelli

CourtNew Jersey Superior Court Appellate Division
DecidedAugust 8, 2025
DocketA-3137-23
StatusUnpublished

This text of Shed World v. Jim Funicelli (Shed World v. Jim Funicelli) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shed World v. Jim Funicelli, (N.J. Ct. App. 2025).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-3137-23

SHED WORLD,

Plaintiff-Appellant,

v.

JIM FUNICELLI,

Defendant-Respondent. _________________________

Submitted June 3, 2025 – Decided August 8, 2025

Before Judges Susswein and Perez Friscia.

On appeal from the Superior Court of New Jersey, Law Division, Ocean County, Docket No. DC-004906-23.

Michael B. Cooke, attorney for appellant.

Respondent has not filed a brief.

PER CURIAM

This case arises from a dispute concerning a contract for the delivery of a

prefabricated shed. The contract price was $10,662.50. Defendant James

Funicelli paid $2,000 to plaintiff Shed World when he placed the order, leaving a balance of $8,662.50. Defendant determined after the shed was delivered that

it did not include customized features as per the contract. Plaintiff filed suit to

recover the outstanding balance.

Following a bench trial, plaintiff appeals the April 29, 2024 Special Civil

Part order denying its claim for breach of contract and granting defendants

counterclaim for breach of contract. The trial court allowed defendant to keep

the shed without requiring him to pay the balance due reduced by the amount

defendant paid to a contractor to fix the shed. After reviewing the record in light

of the parties' arguments and governing legal principles, we affirm the trial

court's denial of plaintiff's breach of contract claim against defendant and its

finding that plaintiff breached the contract. However, we remand for the trial

court to make more detailed findings on why defendant should not be required

to pay at least a portion of the balance due, accounting for the amount defendant

paid to a third-party contractor to fix the shed and such other equitable

considerations the trial court deems relevant in determining damages.

I.

We discern the following pertinent facts and procedural history from the

record. On July 16, 2022, the parties entered into a written contract for the sale

of a shed. Per the contract terms, plaintiff agreed to deliver a shed with

A-3137-23 2 customized features, including an interior partition wall, a countertop cutout,

and bifold doors. Defendant agreed to pay $10,662.50, with a $2,000 deposit.

The contract did not include terms regarding delivery dates.

Plaintiff delivered the shed on September 6, 2022 and thereafter emailed

defendant that "[y]ou still have an outstanding balance on our shed of

$8[,]662.50 . . . . As of Saturday, October 1, 2022 if the balance is not paid in

full we will consider this a theft and we will take all the appropriate actions

against you."

On October 3, 2022, defendant replied to the email, refusing to pay the

remaining balance because:

1) The entry door to the "front" area of the shed was supposed to be right up to the partition wall - it is not - it is centered. The side wall will have to be reworked to move the door.

2) The [four] service doors on the front of the shed are too large and heavy to be functional (made incorrectly) - the panels should be half the size that they are. The hardware is not adequate.

3) The [four] service doors, when open on the entry side, block access to the entry door. Extremely poor design with no thought given as to functionality/usability.

4) This front opening was also to be prepped and braced for a stone bar top/counter to be installed - it is not prepped in any way, the doors are flush and would have

A-3137-23 3 to be cut to accommodate any counter at all, and there is no bracing of any kind. The entire wall will have to be reworked as well as the doors.

5) Although a relatively minor issue, the service door color is incorrect.

Defendant proposed to either: deduct the repair costs from the balance owed

and pay the remainder to plaintiff "immediately," allow plaintiff to make the

modifications, or plaintiff could return defendant's security deposit and take the

shed back. At trial, defendant testified that it cost $4,105 to correct the shed to

include the customized features.

In May 2023, plaintiff filed a complaint against defendant alleging breach

of contract. Defendant's answer included breach of contract and fraud

counterclaims.

The court held a bench trial on January 30 and February 20, 2024. Shed

World's owner and defendant testified.

Defendant testified that plaintiff decided to deliver the shed when it was

"raining cats and dogs." Despite his assertion to plaintiff that he did not want it

delivered during the storm, defendant testified that plaintiff stated that "it doesn't

matter . . . we'll deliver it, anyway, in the rain." Defendant testified that he was

not able to notice the problems with the shed until after the rain stopped, stating:

A-3137-23 4 When I tell you it was . . . raining cats and dogs, it was just a torrential downpour. I was using an umbrella and getting wet with an umbrella. The [delivery] guy was a really nice guy . . . . He said, sign this [delivery certificate], I signed this, and I ran back in the house. . . . I didn't even look at the shed that day or the day after, because it was still raining. When we finally went to look we realized there were problems with opening the door, and then realized there was no cut- out for the counter done at all.

Based on the parties' testimony, the trial court issued an oral opinion

followed by a two-page written order. The court found that plaintiff's witness

was untruthful, "inconsistent[,] and contradictory." In contrast, the court found

defendant credible, stating:

I found that he had the ability to know what he was talking about. I found his testimony to be reasonable. I found his demeanor on the stand to be good. I found him to be truthful, not evasive. I found him to be willing to answer questions. I found his testimony to be believable. And for the most part, I didn't find his testimony to be inconsistent or contradictory.

The court found that defendant discovered several issues with the shed

after he gave it a thorough inspection two days after the rain stopped. The court

examined the written contract, which includes customized features for a

"counter cut out [and] frame" and "bifold doors." The court assessed whether

the customizations were made, concluding "[t]here weren't bifold doors.

There . . . wasn't the support for the countertop, bracing."

A-3137-23 5 The court addressed other deficiencies claimed by defendant, finding:

Number one, the entry door to the front area of the shed was supposed to be right up to the partition wall and it's not. It is centered. The sidewall may have to be reworked to move the door. Now, the [c]ourt's review indicates that this is one of those rare instances where I disagree with . . . defendant. The diagram in P-1A clearly indicates that the door is to be centered. So the [c]ourt finds that he's wrong with respect to that.

However, [defendant is] right with respect to the rest. The four service doors on the front of the shed are too large and heavy to be functional, made incorrectly. The panels should be half the size they are. The hardware is not accurate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony D'agostino v. Ricardo Maldonado (068940)
78 A.3d 527 (Supreme Court of New Jersey, 2013)
Lane v. Oil Delivery, Inc.
524 A.2d 405 (New Jersey Superior Court App Division, 1987)
Kearny PBA Local 21 v. Town of Kearny
405 A.2d 393 (Supreme Court of New Jersey, 1979)
Meshinsky v. Nichols Yacht Sales, Inc.
541 A.2d 1063 (Supreme Court of New Jersey, 1988)
Maglies v. Estate of Guy
936 A.2d 414 (Supreme Court of New Jersey, 2007)
Sons of Thunder, Inc. v. Borden, Inc.
690 A.2d 575 (Supreme Court of New Jersey, 1997)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
State v. Gandhi
989 A.2d 256 (Supreme Court of New Jersey, 2010)
Conway v. 287 Corporate Center Associates
901 A.2d 341 (Supreme Court of New Jersey, 2006)
County of Morris v. Fauver
707 A.2d 958 (Supreme Court of New Jersey, 1998)
Meyers v. Henderson Construction Co.
370 A.2d 547 (New Jersey Superior Court App Division, 1977)
Richardson v. UNION CARBIDE IND. GASES, INC.
790 A.2d 962 (New Jersey Superior Court App Division, 2002)
Kieffer v. Best Buy
14 A.3d 737 (Supreme Court of New Jersey, 2011)
Sachau v. Sachau
17 A.3d 793 (Supreme Court of New Jersey, 2011)
Manahawkin Convalescent v. Frances O'neill (071033)
85 A.3d 947 (Supreme Court of New Jersey, 2014)
State v. Kevin Gamble (071234)
95 A.3d 188 (Supreme Court of New Jersey, 2014)
Globe Motor Company v. Ilya Igdalev(074996)
139 A.3d 57 (Supreme Court of New Jersey, 2016)
Custom Communications Engineering, Inc. v. E.F. Johnson Co.
636 A.2d 80 (New Jersey Superior Court App Division, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Shed World v. Jim Funicelli, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shed-world-v-jim-funicelli-njsuperctappdiv-2025.