Shawn Ibrahim, Inc., Mahmood Aktar and Muhammad Amin v. Suncoast Environmental and Construction,Inc. Sunnyland Development, Inc. Ajaz R. Siddiqui And Najeeb R. Siddiqui

Court of Appeals of Texas·Decided July 6, 2015·No. 01-14-00583-CV·Published

Opinion

Opinion issued July 2, 2015

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-14-00583-CV ——————————— SHAWN IBRAHIM, INC., MAHMOOD AKTAR, AND MUHAMMAD AMIN, Appellants V. SUNCOAST ENVIRONMENTAL AND CONSTRUCTION, INC., SUNNYLAND DEVELOPMENT, INC., AJAZ R. SIDDIQUI, AND NAJEEB R. SIDDIQUI, Appellees

On Appeal from the 61st District Court Harris County, Texas Trial Court Cause No. 2011-02593

MEMORANDUM OPINION ON REHEARING

This is a suit to collect on an unpaid promissory note. Shawn Ibrahim, Inc.,

and its guarantors, Mahmood Aktar and Muhammed Amin, appeal from a bench trial, in which the trial court found that they had defaulted on a $200,000 note in

favor of Sunnyland Development, Inc. The trial court found for Sunnyland,

awarding it $453,667.59 on the note and attorney’s fees of $63,591.79. On appeal,

Ibrahim, Aktar, and Amin contend that the trial court (1) misinterpreted a standby

creditor’s agreement that precludes judicial enforcement of the note, thus barring a

judgment against them; (2) miscalculated the interest rate and offsets in

determining the amount due; and (3) erred in declining to find merit in their usury

counterclaim. After we issued our opinion in this case, Ibrahim, Aktar, and Amin

moved for rehearing. We deny the motion for rehearing; we withdraw our opinion

and judgment and issue this opinion and judgment in their stead. We affirm.

Background

In 2004, Ibrahim, whose president is Aktar, contracted with Suncoast

Environmental and Construction, Inc. for construction of a convenience store,

truck stop, and restaurant. Suncoast was the general contractor. Sunnyland was

the developer and loaned the money to Ibrahim for the project. Ajaz and Najeeb

Siddiqui together own Suncoast. Ajaz solely owns Sunnyland, and he is the

president of Sunnyland and Suncoast.

In 2005, Ibrahim executed a promissory note to Sunnyland for $200,000 and

signed a deed of trust. Aktar and Amin personally guaranteed the note. The note

required Ibrahim to make monthly payments of $2,930.04, “beginning on July 1,

2 2006 and continuing until the unpaid principal and accrued, unpaid interest have

been paid in full.” Payments would be applied to accrued interest before reducing

principal. The note provided for two interest rates: a general “annual interest rate”

of 9%, but one of 18% on “matured, unpaid amounts.” The promissory note did

not explicitly provide a date on which interest would begin to accrue. It also did

not expressly specify whether the interest rates were simple or compound interest

rates, other than to describe them as “annual” rates.

In the event of a default, the note required Sunnyland to give Ibrahim written

notice of default and 10 days to cure it. The deed of trust provided for acceleration

of payment on the principal balance and earned interest if Ibrahim defaulted on the

note and did not cure the default within 10 days after receiving notice. The note

also contained a clause regarding potential usury, requiring that any interest in

excess of the maximum rate allowed by law would be credited against the principal

amount owed or refunded.

Ibrahim failed to repay the note as agreed. Instead of making monthly

payments beginning in July 2006, over the next four years, Ibrahim made seven

payments: $10,000 in August 2008; $12,000 in September 2008; $10,000 in

February 2010; $10,000 in June 2010; $5,000 in August 2010; $5,000 in

September 2010; and $5,000 in October 2010. An eighth payment of $25,000,

paid in June 2006, is contested on appeal.

3 In January 2008, the Houston-Galveston Area Local Development

Corporation (“HGAC”), a community development corporation, and Sunnyland

signed a standby creditor’s agreement benefitting Ibrahim and its guarantors. In

the standby agreement, Sunnyland agreed to take no action to enforce the note

against Ibrahim or its guarantors without the written consent from HGAC, subject

to certain exceptions.

Course of Proceedings

Initially, Ibrahim sued Suncoast Environmental and Construction, Inc.,

Sunnyland Development, Inc., and the Siddiquis for breach of their construction

contract, among numerous other claims. Sunnyland and the Siddiquis

counterclaimed against Ibrahim, Aktar, and Amin for the amounts due on the note.

The construction claims settled, leaving the note and the usury claims for trial.

After a bench trial, the trial court rendered judgment in favor of Sunnyland.

It submitted findings of fact and conclusions of law. Relevant to this appeal, the

trial court found:

• The Note referred to the Deed of Trust and the Deed of Trust had an acceleration clause.

• Shawn Ibrahim, Inc. owes Sunnyland as of March 1, 2014 . . . $453,667.59 . . . on the $200,000 note.

• Akhtar and Amin owe Sunnyland as of March 2014 . . . $453,667.59 . . . as absolute guarantors.

4 • The $200,000 installment loan calls for an annual rate of 9%, which started to accrue when the loan was made. All installments that remained unpaid were to earn interest at the annual rate of 18%.

• The requisite 10-day demand notice was sent by certified mail in January 2010 to Counter-Defendants.

• The unpaid interest related to unpaid installments become principal.

• Although the Standby Creditor Agreement prohibited payment from Ibrahim, it does not prohibit payment from third parties and, in this case, the absolute guarantors of the Note, Akhtar and Amin.

• Sunnyland did not demand usurious interest.

• Sunnyland is excused from any [usury] penalties.

• Sunnyland’s expert correctly calculated the note by giving effect to all of the terms of the note.

Discussion

At the outset, we note that the Ibrahim and the guarantors provided only

limited excerpts from the trial court reporter’s record. The Texas Rules of

Appellate Procedure provide:

If the appellant requests a partial reporter’s record, the appellant must include in the request a statement of the points or issues to be presented on appeal and will then be limited to those points or issues. . . . The appellate court must presume that the partial reporter’s record designated by the parties constitutes the entire record for purposes of reviewing the stated points or issues. This presumption applies even if the statement includes a point or issue complaining of the legal or factual insufficiency of the evidence to support a specific factual finding identified in that point or issue.

5 TEX. R. APP. P. 34.6(c). If a party fails to submit his statement of points or issues,

it creates the presumption that the omitted portions of the record support the trial

court’s findings. Bennett v. Cochran, 96 S.W.3d 227, 229 (Tex. 2002) (citing

Richards v. Schion, 969 S.W.2d 131, 133 (Tex. App.—Houston [1st Dist.] 1998,

no pet.). Ibrahim did not notify this court of, or include in the record on appeal, its

request for a partial reporter’s record made to the court reporter in the trial court.

Nor did it designate its accompanying statement of issues filed in the trial court as

part of the appellate record. Nor did it mention either the partial designation or its

accompanying statement of issues in its appellate briefing. For the first time on

rehearing, it references its request for a partial reporter’s record and attaches the

Free access — add to your briefcase to read the full text and ask questions with AI

Shawn Ibrahim, Inc., Mahmood Aktar and Muhammad Amin v. Suncoast Environmental and Construction,Inc. Sunnyland Development, Inc. Ajaz R. Siddiqui And Najeeb R. Siddiqui, (Tex. Ct. App. 2015).

Shawn Ibrahim, Inc., Mahmood Aktar and Muhammad Amin v. Suncoast Environmental and Construction,Inc. Sunnyland Development, Inc. Ajaz R. Siddiqui And Najeeb R. Siddiqui (Shawn Ibrahim, Inc., Mahmood Aktar and Muhammad Amin v. Suncoast Environmental and Construction,Inc. Sunnyland Development, Inc. Ajaz R. Siddiqui And Najeeb R. Siddiqui) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
Bennett v. Cochran
96 S.W.3d 227 (Texas Supreme Court, 2002)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Merry Homes, Inc. v. Chi Hung Luu
312 S.W.3d 938 (Court of Appeals of Texas, 2010)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Richards v. Schion
969 S.W.2d 131 (Court of Appeals of Texas, 1998)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Quality Infusion Care, Inc. v. Health Care Service Corp.
224 S.W.3d 369 (Court of Appeals of Texas, 2006)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Gallagher v. Fire Insurance Exchange
950 S.W.2d 370 (Texas Supreme Court, 1997)
Anglo-Dutch Petroleum International, Inc. v. Haskell
193 S.W.3d 87 (Court of Appeals of Texas, 2006)
RE/Max of Texas, Inc. v. Katar Corp.
961 S.W.2d 324 (Court of Appeals of Texas, 1997)
Shoberg v. Shoberg
830 S.W.2d 149 (Court of Appeals of Texas, 1992)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Chapman v. Abbot
251 S.W.3d 612 (Court of Appeals of Texas, 2007)
Moore v. Altra Energy Technologies, Inc.
321 S.W.3d 727 (Court of Appeals of Texas, 2010)
Adams v. H & H Meat Products, Inc.
41 S.W.3d 762 (Court of Appeals of Texas, 2001)
First Bank v. Tony's Tortilla Factory, Inc.
877 S.W.2d 285 (Texas Supreme Court, 1994)