Shaw v. McPhail Electric Co.

544 S.W.2d 497, 1976 Tex. App. LEXIS 3354
CourtCourt of Appeals of Texas
DecidedNovember 18, 1976
DocketNo. 19028
StatusPublished
Cited by2 cases

This text of 544 S.W.2d 497 (Shaw v. McPhail Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaw v. McPhail Electric Co., 544 S.W.2d 497, 1976 Tex. App. LEXIS 3354 (Tex. Ct. App. 1976).

Opinion

GUITTARD, Justice.

McPhail Electric Company recovered a judgment against Martin B. Shaw, the owner of a residence, enforcing a mechanic’s and materialman’s lien in the amount of $548.30. Shaw appeals, contending that McPhail Electric Company does not qualify either as an original contractor or as a subcontractor under the Hardeman Act, Tex.Rev.Civ.Stat.Ann. arts. 5452, 5453 (Vernon Supp.1976), and has not complied with the notice requirements of that Act. Ap-pellee contends that it should be treated as an original contractor under the sham contractor statute, Tex.Rev.Civ.Stat.Ann. art. 5452-1 (Vernon Supp.1976) and that the lien was properly secured by filing the lien affidavit with the county clerk and mailing two copies to the appellant in the time and manner required of original contractors by article 5453(1). We agree. Accordingly, we affirm the judgment.

Appellee McPhail Electric Company installed electrical fixtures and performed other services pursuant to an oral agreement between Leían McPhail, president of McPhail Electric and Ralph Salyers, on behalf of Salyers & Walley, Inc. The fixtures and other apparatus' were installed in a house being built by Salyers & Walley on land owned by Ralph Salyers and Ben Caballero. Salyers himself took McPhail to the building site and showed him the work to be done by McPhail Electric.

Appellee’s employees installed the specified electrical apparatus on February 25 and 26 and March 4 and 18 of 1974. Meanwhile, on March 6, Salyers and Caballero conveyed the tract on which the work was being done to appellant Shaw. Appellee sent bills for its work to Salyers & Walley and received one check from Salyers & Walley in part payment. On failure to receive further payment, appellee filed a mechanic’s and materialman’s lien affidavit with the county clerk on April 24,1974, and sent copies by certified mail to Salyers & Walley and to appellant.

Appellee sued Salyers & Walley on the debt and sued appellant for enforcement of the lien. Salyers & Walley failed to an[499]*499swer, and a default judgment was entered against it for the amount claimed. After trial without a jury, judgment was entered against appellant, giving him the option of paying appellee the sum of $548.30, which the court found to be the value of the electrical apparatus installed, or allowing appellee to enter upon the property and remove the fixtures subject to the lien. Shaw alone appeals from this judgment.

Appellant’s points of error present four contentions: (1) that appellee failed to qualify for a statutory lien as a subcontractor because there is no evidence establishing a contractual relationship between Salyers & Walley, Inc., and any owner of the property or any original contractor; (2) that the appellee failed to qualify for a constitutional or statutory lien as an original contractor because there is no evidence to establish a contract between appellee and the owner; (3) that appellee does not have an enforceable lien because it failed to give notice to the persons who owned the property at the time the work was done; and (4) that the trial court’s finding that all the materials listed on appellee’s invoice were specially fabricated, was against the overwhelming weight and preponderance of the evidence.

We do not consider the first and fourth contentions because they are immaterial to the judgment and to this appeal. The first is immaterial because appellee did not plead that it had the status of a subcontractor with regard to this construction job and on this appeal it expressly disclaims any subcontractor’s lien. The fourth contention has no significance on this appeal because the judgment is not based on the trial court’s finding that the materials were specially fabricated. Special fabrication of materials is significant only where such materials have not been delivered or incorporated into the construction, article 5452(1). Such materials, less their salvage value, may be included in the lien claim because they may have limited usability elsewhere. In this case, all of the materials for which a lien is claimed were installed at the construction site.

Pertinent to this appeal, however, is appellant’s second contention, that there is no evidence in the record establishing ap-pellee’s status as an original contractor. The trial court held that appellee was entitled to the status of an original contractor under the sham contractor statute, article 5452-1(1), which provides in part:

Whenever any owner of real property shall enter into any contract with a corporation for the construction or repair of any house, building or improvements thereon, and said owner can effectively control the corporation with whom such contract is made, through the ownership of voting stock therein, interlocking directorships or otherwise . . . any person, firm or corporation who, under a direct contractual relationship with said person or corporation and who may labor, specially fabricate material, or furnish labor or material to be used in the prosecution of the work under such contract shall be deemed to be in a direct contractual relationship with the owner and may perfect his lien against the property in the same manner as any other original contractor.

Although the judge made no specific findings of fact concerning the contractual relationship between Salyers & Walley, Inc., and the owners, Salyers and Caballero, or concerning whether said owners could effectively control Salyers & Walley, Inc., the evidence introduced at trial is sufficient to bring the case within the sham contractor statute. The evidence, though brief, is undisputed. Leían McPhail was contacted by Ralph Salyers early in 1974 concerning completion of the electrical work at the subject housing project. Salyers asked McPhail to come out to the project. When McPhail arrived, Salyers showed him around and pointed out the work to be done. At this time and also at the time the work began, Salyers was one of the owners of the tract where the project was located. All bills for materials and services rendered by appellee were addressed and mailed to Salyers & Walley, Inc., and appellee received one check from Salyers & Walley in partial payment. This evidence supports an [500]*500inference that Salyers & Walley, Inc. had some sort of contract with the owners. Since it is undisputed that Ralph Salyers was one of the owners of the land and was also the person who acted for the corporation in contracting with McPhail for the electrical work, and since “Salyers” is one of the names used in the corporate name, we hold that the evidence supports the further inference that the owners of the land had “control” of the corporation within the meaning of the sham contractor statute. Thus the trial court was authorized to treat appellee as a contractor in a direct contractual relationship with the owner and as entitled to perfect his lien against the property in the same manner as any other original contractor, that is, by taking the steps prescribed by article 5453(1), without complying with the additional requirements applicable to subcontractors in article 5453(2). Da-Col Paint Manufacturing Co. v. American Indemnity Co., 517 S.W.2d 270, 272-73 (Tex.1974).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
544 S.W.2d 497, 1976 Tex. App. LEXIS 3354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-v-mcphail-electric-co-texapp-1976.